Majority
Headnote
Building contract — mechanic's lien of material-man — application of balance of contract-p'ice in the case of the contractor’s default.I think the referee erred in his conclusion in this case. Under the contract the owner could go on and complete the work if the contractor refused or neglected to do so, and dediict the expenses from the amount of the contract.
If, after doing so, there is a balance left, or if the owner does not choose so to do, and then, after deducting what it would cost to complete the work from the contract-price there is a balance left, I think the lienor is entitled to that balance. ( Wright v. Roberts, 43 Hun, 413 ; affirmed, without opinion, in 118 N. Y., 672 ; Foshay v. Robinson, 43 N. Y. St. Rep., 20 ; Graf v. Cunningham, 109 N. Y., 369 ; Van Clief v. Van Vechten, 130 id., 571-581.)
The last case was one where the owner had gone on and completed the contract upon the default of the contractor, and the court said: “ The difference between the sum thus expended and the aggregate amount unpaid on the contract with Smalle upon the completion of the entire work, became due under the contract; to the extent of that sum, being the difference between $2,023 and $1,905.20, the lien of the plaintiffs attached, and they are entitled to a foreclosure for that amount.”
In Larkin v. McMullen ( 120 N. Y., 206 ), and Hollister v. Mott ( 132 N. Y., 18 ), there was not a substantial compliance with the contracts, and neither was there any provision in the contracts by which the owners could complete the contracts in case of the contractors’ default, and in those respects the cases are distinguished from those heretofore cited, the principles of which are recognized in both the Larkin and Hollister cases.
In the case before us, as we have seen, there was an express provision allowing the owner to complete the work, in case of the contractor’s default, and deduct the expense from the contract; the plain inference from that, it seems to me, is, that after making such deduction the balance, if any, would be payable to the contractor.
There is also another aspect of the case under which I think the plaintiff is entitled to recover.
The referee has found that the plaintiff has not substantially performed his contract, a conclusion in which I cannot concur, but which I will not discuss, but assume to have been correctly found : and the final decision arrived at by him is based upon that conclusion, that the contract not being performed by the contractor, there is nothing due him from the owner, and that there being nothing due the contractor, there is nothing to which the lien can attach.
The contract-price was $2,700. The referee has found that $2,509 was paid'upon the contract. That, by consent of the owner, work amounting to the sum of $102.69 ■ has not been performed by the contractor, and that work amounting to the sum of fifty-nine dollars, and twenty-five cents has been left unperformed without the consent of the owner.
The referee has also found that the contractor has performed extra work to the amount of $235.99. The contract contained this provision as to extra work: “ Should the owner, at any time during the progress of the said building, request any alterations, deviations, additions or omissions from the said contract, he shall be at liberty to do so, and the same shall in no way affect or make void the contract,. but will be added. or deducted from the amount of the contract, as the case may be, by a fair and reasonable valuation.”
An almost identical provision in a contract was passed upon in Garnsey v. Rhodes ( 45 N. Y. St. Rep., 145 ), and it was there held that the contractor could recover the value of the extra work, although he had hot completed the contract according to its terms.
The amount of the extra work is money due the contractor. ( Woodward v. Fuller, 80 N. Y., 312 .) In this case it is money due
For these reasons the judgment should be reversed, the referee ■discharged and a new trial granted, costs to abide the event.
Mayham, P. J., and Putnam, J., concurred.
Judgment reversed, new trial ordered, referee discharged, costs to abide event.