Majority
Headnote
Amendment of answer — building contract — abandonment by both pa/rties before completion.This action was brought to foreclose a mechanic’s lien. On the-26th day of August, 1890, the plaintiffs entered into a contract in writing with the defendant, Charles H. Scoville, to furnish the material and construct a dwelling house upon the premises of the defendant, Cora I. Scoville, for the sum of $3,980. The work was to be done in a workmanlike manner, according to the plans and specifications attached to the contract and under the direction and to the satisfaction of F. 'William Fisher, an architect. Charles H. Scoville was the husband of Cora I. Scoville, and he entered into, the contract with her knowledge and consent and for her benefit. The plaintiffs sublet the carpenter work to another person, who commenced work upon the construction of the building on the twenty-second day of September and continued work thereon until the third day of October, at which time he ceased work upon the premises, leaving the building unfinished. Subsequently this action was brought.
The trial court found as facts, that the building, as far as it had progressed, had not been constructed in accordance with the provisions of the contract, that improper materials had been furnished, and that the work had not been performed in a workmanlike manner. That on the thirtieth day of September notice was given to the plaintiffs to remove all labor and materials condemned by the architect and to provide materials called for in the specifications on or before the fourth day of October at nine o’clock a. m. That the plaintiffs expressed a willingness to remedy the defects, and through their employees did remedy certain defects, but not all. That on the third day of October they abandoned the work. That there
This judgment was ordered upon the theory that the defendants had abandoned the contract on their part, after the plaintiffs had committed a breach of the contract on their part. That the defendants, in using the plaintiffs’ material in the new structure, were obliged to pay therefor, less the sum of $123.50, which the defendants had suffered as damages in reconstructing the building to the point where it was abandoned by the plaintiffs.
The complaint alleged that on the 2d day of October, 1890, the defendants, without any just cause for so doing, notified the plaintiffs’ workmen to cease work upon the house and ordered them off the premises, forbidding them coming again upon the land, and that no work had been done or material furnished by the plaintiffs since.
The answer admitted that on or about the 2d day of October, 1890, the defendant, Charles H. Scoville, notified the plaintiffs and their workmen to cease work upon the said house, and that the plaintiffs have done no work and furnished no material since that time. But they deny that he so notified the plaintiffs and their workmen without just cause. It, therefore, stood admitted upon the pleadings that the plaintiffs and their workmen were ordered to cease work upon the house by the defendants, and the issue left to be tried in reference thereto was whether such order was justified.
TJpon the trial the defendants were permitted to give evidence that the plaintiffs and their workmen were not ordered to cease work upon the house and were not ordered off the premises, but, on the contrary, that they voluntarily abandoned the work. This evidence wras taken under the objection that it contradicts, the admissions in the answer. The court, however,, admitted the same, remarking, “ If it turns out they are precluded by the pleadings, that will end it.” No exception was taken to the ruling. After th,e evidence was closed an adjournment was taken for a number . of
There would be just cause for complaint on account of these rulings, were it not for the fact that the plaintiffs had first opened the door and given evidence in support of their allegation. Evidence upon this subject was given as a part of the plaintiffs’, affirmative case, and also upon the rebuttal. The question having thus been tried out, it was within the discretion of the trial court to permit the answer to be amended so as to conform to the evidence given.
As we have seen, the trial court found that the plaintiffs ceased work upon the house and contract, and by this act they forfeited their right to recover any of the installments under the contract thereafter to become payable. The building as far as it had progressed, became the defendants’. They had, however, paid nothing thereon, and had consequently suffered no damages, unless, as it is claimed, it was so defectively constructed as to make it necessary that it should be torn down. If so, it was but an obstruction upon their premises, which they had a right to tear down, move away, or dispose of as they saw fit. It was torn down at an expense of $40.50. The building was reconstructed according to the original plans and specifications. It cost $123.50 to reconstruct it to the point where it was abandoned by the plaintiffs. . This the trial court found was a proper item of damages to be deducted from the plaintiffs’ claim.
The plaintiffs were awarded judgment upon the theory that the defendants had abandoned the contract on their part. Their right to recover cannot be maintained unless thiá theory is supported by the evidence. And this brings us to a consideration of the defendants’ appeal.
Section 1 of the contract provides that “ the contractors shall within twenty-four hours after receiving written notice from the architect to that effect, proceed to remove from the grounds or building all materials condemned by him, whether worked or unworked, or to take down all portions of the work which the architect shall condemn as unsound or improper, or as in any way failing to conform to the drawing and specifications, and to the conditions of this contract. The contractors shall cover, protect and exercise due diligence to secure the work from injury, and all damage happening to the same by their neglect shall be made good by them.”
Section 12 provides, “ should the contractors at any time refuse or neglect to supply a sufficiency of properly-skilled workmen or of materials of the proper quality, or fail in any respect to prosecute the work with promptness and diligence, or fail in the performance of any of the agreements on their part herein contained, such refusal, neglect or failure being certified by the architect, the owner shall be at liberty, after three days’ written notice to the contractors, to provide any such labor or materials, and to deduct the cost thereof from any money then due or thereafter to become due to the contractors under this contract. And if the architect shall certify that such refusal, neglect or failure is sufficient ground for such action, the owner shall also be at liberty to terminate the employment of the
On the thirtieth day of September the architect certified that the work, labor and material upon the house was not being done in accordance with the plans and specifications. Thereupon the defendant, Charles H. Scoville, served upon the plaintiffs the following notice:
“ I herewith give you three days’ written notice, to expire October 4th, at 9 a. m., to remove all labor and materials condemned by the architect, Mr. E. ¥m. Eisher, and to provide such materials as are called for in the specifications.
“ I also notify you that I shall make use of the power given me under part twelve in the contract to terminate the employment of the contractor who shall do said carpenter work.”
And at the same time took from the plaintiffs’ possession the' plans and specifications.
It will be observed that the notice requires the plaintiffs to remove the materials condemned, and to provide such material as is-called for by the specifications. And in the same connection, notice-is given that they terminate the employment of the contractors, under the power given them under part twelve. So by the notice the plaintiffs’ right to proceed in the construction of the building was terminated, and yet they were required to provide the materials called for in the specifications. There appears to have been some
The defendants requested the trial court to find, that “ the defendant, Charles II. Scoville, took possession of the said building and material and employed other persons to take the building down, to the foundation, at an expíense of forty dollars and fifty cents, and to rebuild the same to the point where pilaintiffs had left it, and to compílete the same according to the original pilans and specifications at an expense of $4,480 for the carpenter work and materials, and of $150 for the sheet-metal, tin and galvanized iron work, making a total expense to defendant of $690.50 over and above the pírico agreed to be piaid to pilaintiffs.” This finding was refused. The request appears to be in accordance with the undispiuted evidence and might piropierly have been found. This would entitle the defendants to recover their counterclaim, were it not for the fact that they had terminated the contract by their notice of September thirtieth, and by their taking from the pilaintiffs the pilans and specifications.
True, the pilaintiffs abandoned the contract on the third day of October, as found by the trial court, but this was after the notice had been served upon them by the defendants to which we have referred. The defendants had no right to then terminate the employment of the pilaintiffs. This, as we have seen, could not be done until after October fourth, at nine a. m., and not then unless the architect should certify that the pilaintiffs had failed to correct the defects and pierfonn the contract. But the defendants having assumed to terminate the employment on the thirtieth, the pilaintiffs had the right to accepit the situation thus presented and themselves treat the contract as at an end.
- Tbe order appealed from should be affirmed, and tbe judgment should be modified by awarding to the plaintiffs the sum of $318, less $40.50, amounting to $277.50, with interest on that sum from the 13th day of November, 1891, and as so modified affirmed, with the costs of this appeal to the plaintiffs.
All concurred.
Order appealed from affirmed, and the judgment appealed from modified, as indicated in the opinion, with costs to the plaintiffs.