Majority
Headnote
Contract for pvMia work—Sweties—Substitution, of other than those mentioned in bid, after its acceptance—when not allowed.The defendants, Ives, Wykoff, Yan Sickeen and Palmer, were appointed by the Supreme Court, commissioners to lay out, open and grade Atlantic averiue, in the town of New Lots, Kings county, under an act of the legislature, passed in 1869,[1] which act- was amended in 1870.[2] Under these acts, the commissioners, as such, were to enter upon the lands taken for the avenue, and cause the same to be properly regulated, graded, graveled, curbed, etc., in such manner and on such plans, as, in their judgment, should be necessary. The act contains no directions as to any manner in which they shall contract for the doing of the work, or for any advertisement for proposals. The commissioners, however, did, in November, 1870, publish a notice, to the effect that, for the space of two weeks, proposals would be received for the regulating, grading, curbing, guttering and preparing the avenue, according to certain plans and specifications to he seen at their office. The specifications referred to, contained the following provisions, to wit: “ Each estimate must be accompanied by the consent, in writing, of two persons, with their respective place of business or residence, who shall be satisfactory to the commissioners, so that, should the contract be awarded to the persons making the bid, they will, on its being so awarded, become bound as sureties, each and severally, in the sum of $10,000, to insure the faithful performance - of the contract.”
The plaintiff put in a bid, which, on the face of it, purported to be a bid for furnishing the materials for the work in question, and named, as his securities, “ William Miles and Samuel Gr. Adams, both real estate owners in the town of New Lots.”
* Sess. Laws of 1869, p. 404.
† † Sess. Laws of 1870, vol. 2, p. 1434.
The plaintiff, being unable to procure Mr. Miles to become one of his sureties, tendered Mr. Devlin, as such surety, in place of Miles; and thereupon, after the time specified in their notification to the plaintiff had expired, the commissioners awarded the contract to the defendants, Moore and Sturges. The plaintiff thereupon commenced this suit in equity, to restrain the commissioners from awarding the contract to any other person, and from collecting any money from the town of Hew Lots; to pay for doing the work, and to restrain the supervisor of the town of Hew Lots from issuing the bonds of the town of Hew Lots to pay for the work, and to restrain Moore and Sturges from doing the work under the contract awarded to them. On the trial, the complaint was dismissed, upon the ground that the commissioners were not legally bound to accept of Mr. Devlin as a surety for the performance of the contract by the plaintiff, even though Devlin was sufficiently responsible. Without conceding that a suit in equity can be maintained in such a case, we think that the decision at the Special Term was clearly right, upon the ground on which it was. then placed. The authorities relied upon by the plaintiff’s counsel, to show that, where there is a contract to take “ good security,” or “ a good indorsed note,” or when words creating a similar obligation are used in a
The judgment must be affirmed, with costs of the appeal.
Present — Baenaed, P. J., Tappen and Taloott, JJ.
Judgment affirmed, with costs.