Majority
Headnote
Action to recover da/mages for the breach of a contract — when prematurely brought.We think the action was prematurely brought. By it the plaintiff sought to recover damages for an alleged breach of a contract by which the defendants agreed to pay for sixty cases of goods on June 10, 1891, the plaintiff on its part having stipulated to have them ready for delivery ten days earlier, or June first.
Plaintiff notified defendants prior to June first that the goods were ready for delivery. Defendants did not make full payment on June tenth, but a little later, about June twenty-second, they ordered the plaintiff to deliver to them some of the goods. Thereafter, and before August fifth, four cases were delivered to them. Defendants insisted that the goods were not in accordance with the contract in several respects, one being that the buttons on the garments delivered only had two holes, whereas it yras agreed that they should have four.
Plaintiff yielded to defendants’ contention regarding the buttons, and agreed to allow to the defendants, because of the error in such respect, fifteen dollars a case for each of the four cases delivered, and to substitute buttons with four holes in the place of those on the fifty-six cases of goods then in. plaintiff’s factory. In accordance therewith the plaintiff, by its representative, sent the defendants a check for sixty dollars inclosed in a letter, of which the following is a copy:
“New York, August 5, 1891.
“Messrs. Weil, Haskell & Co., New York:
“Gentlemen — Enclosed find check for $60, in settlement of claim °jc of wrong buttons on cases 1487, I486, 1474, and 1476 delivered by the Lackawanna Mills.
“ The balance of the order shall have buttons,as last year and as per samples from which order was taken. I am
“ Yery truly yours,
“A. S. HAIGHT.”
Thereafter the plaintiff put buttons with four holes on the remaining garments in place of those then on, but it had not completed the work when this action was brought.
The evidence is to the contrary. Edward Gr. Connor, plaintiff’s superintendent, testified with reference to a call made upon the plaintiff by a Mr. Lampman, representing the defendants, who presented a letter of introduction from his employers, bearing date August nineteenth, in which they requested for him the courtesy of {lie plaintiff.
The witness said that Lampman called the day following the date of the letter, which would be August twentieth. On his cross-examination he testified: “ Q. When were those buttons changed ? A. The girls were working on them at the time that the messenger -from Woil, ITaskell & Co. was there. Q. When did they finish them ? A. Oh, within a day or two after he was there. Q. Do you recollect that? A. Well, I couldn’t s^y for certain what day they were finished.
“ The Court. — He doesn’t ask for certain; he asked within what time.
“ Q. The letter was dated August 19th. It must have reached you about the 20th. Now, I want to know how long after August 20th was it before the buttons were changed ? A. Well, not over two days. Q. And then they were all completed? A. Tes, sir; didn’t take only about three days to do the whole thing.”
Lampman testified that he arrived at Scranton, where plaintiff’s mills were situated, early in the evening of the nineteenth, and •called at the mills on the twentieth, and had cases of the goods opened for his inspection. Replying to the question whether the buttons had been changed, he answered “ No, sir.” This action was commenced on the nineteenth day of August, necessarily, therefore,
Tlie judgment should be reversed and a new trial granted, with costs to the appellants to abide the event.
"V an Brunt, P. J., and Foiilett, J., concurred.
Judgment reversed, new trial granted, with costs to appellants to abide the event.