Majority
Headnote
Assessment ■ — when invalid under chapter 335 of 1813 —the commencement of the work the day prior to the act talcing effect sustains the assessment.This action was brought to recover sums paid by plaintiffs for two assessments for sewers in the Boulevard. The first was an assessment for sewers between Ninety-second and One Hundred and Sixth streets, and the second an assessment for sewers between Sixty-first and Seventy-seventh streets. By the judgment the plaintiffs recovered the first but were nonsuited as to the second, and it is from the refusal to allow a recovery for the second assessment paid that the plaintiffs appeal, while the defendant appeals from so much of the judgment as allows any recovery.
Questions involving assessments for the improvement of the Boulevard have been before this court and the Court of Appeals so many times that it is unnecessary to recite the facts at length, it
Between the years 1872 and 1876 the construction of the Boulevard between Fifty-ninth and One Hundred and Fifty-fourth streets was in progress by men employed by days’ work and not by contract. This construction included, not only the regulating and grading of the Boulevard, but the building of the sewers. With respect to the latter, the area to be covered being nearly five miles long and the grades varying greatly, it was divided for purposes of sewerage into five sections, which when completed resulted in five assessments, one for each of these sections or. subdivisions, the assessments being confirmed in-1881. The charter of 1873 (Chap. 335, Laws of 1873) went into effect on the 30th of April of that year, and required that all contracts must be let at public letting, if for more than $1,000, “ excepting such works now in progress as are authorized by law or ordinance to be done otherwise than by contract.” (§ 91.) The work on the sewers was all done by days’ work, and the amount upon each section was greatly in excess of $1,000.
When the question was first presented it was sought to sustain the legality of the assessment for the entire sewer by claiming that the work in- progress upon one section was work in progress upon each subdivision thereof. This, however, was disposed of by the Court of Appeals (Matter of Blodgett, 91 N. Y. 117 ) adversely to the city.
Upon the authority of that case the assessment levied upon the plaintiffs’ property for the section of the sewer between Ninety-second and One Hundred and Sixth streets was void, it being conceded that it was for more than $1,000 and was all done, not by contract, but by days’ work admittedly commenced after the passage of the charter of 1873. (Tripler v. Mayor, 125 N. Y. 617 ; 139 id. 1.) Although conceding the technical illegality of such assessment, the defendant insists that no recovery for money so paid can be had, upon the ground that the remedy by suit of this nature has been taken away by statute and that the payment must be considered to have been made voluntarily. Upon this claim the recent decision of this court in Mutual Life Ins. Co. v. Mayor ( 79 Hun, 482 ) is controlling upon this court.
In The Matter of Blodgett (supra) it is said: “We have recently considered the meaning of this phrase (work in progress), as used in the charter, and the scope and purpose of the exception thereby declared (Matter of Weil, 83 N. Y. 543 ). In that case wo expressed the opinion that the purpose of the exception was to avoid the evil and complication arising from an application of the contract system to work already commenced and moving towards completion in a different manner, and was descriptive of cases where the city was already committed to a specific mode of doing the work, and could not change the system without complication or confusion. * * * The exception of the charter had an evident purpose and aim. The general and dominant idea was to do all of the city’s work by the contract system, and that only was intended to be exempted which was already begun — which was ‘in progress’ on a system and in a mode of its own, and -which could not be interfered with unless at the peril of evil consequences.”
Under this definition of what is meant by the phrase “ work in progress,” a close question is presented whether such work as was done on the day preceding the taking effect of the charter was sufficient to bring it within the exception and permit of its being continued otherwise than by contract. On one side it can be urged with much force that work could have been stopped at once without occasioning any complication or confusion, or evil consequences to the city, and a contract let therefor without such action coming in conflict with any different system. On the other hand, the making of the surveys, profiles, etc., coupled with the fact that work had been actually commenced, argues strongly for the validity of the assessment under a liberal construction of the language used in the charter. When we recall the advantage and benefit that this boule
Dissent
¥e are, therefore, of the opinion that the judgment was right and should be affirmed, without costs to either party upon this appeal.
Yan Brunt, P. J., concurred.
(dissenting):
I concur in that part of the prevailing opinion which sustains the recovery for §2,844.85, but dissent from that portion which denies the plaintiffs’ right to recover §7,371.83, the amount of the assessment collected, with interest, on account of the work done on the second section between Sixty-first and Seventy-seventh streets.
Section 91 of chapter 335 of the Laws of 1873 provides :
“ Whenever any work is necessary to be done to complete or perfect a particular job, or any supply is needful for any particular purpose, which work and job is to be undertaken or supply furnished for the corporation, and the several parts of the said work or supply shall together involve the expenditure of more than one thousand dollars, the same shall be by contract, under such regulations concerning it as shall be established by ordinance of the common council, excepting such works now in progress as are authorized by law or ordina/nce to be done otherwise than by contract.”
The exception in italics relates to particular works in progress April 30, 1873, when the statute took effect, which had then been authorized by law or ordinance to be done otherwise than by contract. Two conditions must have existed April 30, 1873, to bring the Boulevard sewer within the exception : (1) The work must have been in progress, and (2) it must have been “ authorized by law or ordinance to be done otherwise than by contract.” Our attention has not been called to any law or ordinance authorizing this particular work to be done otherwise than by contract. On the contrary, the undisputed evidence is that there was no such ordinance, and so, the work on this sewer is not within the exception. (Chap. 137, Laws of 1870, § 104; Matter of Robbins, 82 N. Y. 131 .)
Notwithstanding the statute and the fact that there was no law or
The judgment should be modified by increasing the amount of the recovery by $7,371.83, and, as modified, affirmed, with costs in favor of the plaintiffs and against the defendant.
Judgment affirmed, without costs to either party.
Cases cited
- In re Blodgett 91 N. Y. 117 p. 571
- Tripler v. Mayor, Aldermen & Commonalty 125 N. Y. 617 p. 571
- In re Weil 83 N. Y. 543 p. 572
- In re Robbins 82 N. Y. 131 p. 573