Majority
Headnote
Ambiguous contract — interpi'eted by the action taken under it — contract to work a week of “seven days.”One of the defenses set up by the defendants is that the consideration of the weekly payment to be made or guaranteed by the defendants was in part for services to be peiffoimed on Sunday, and that the agi-eement in substance required the service to be so performed, and that, therefoi’e, the contract, under which plaintiffs claim, is illegal and void. It is not disputed that this result follows, provided the agreement is to be construed as requiring the machine to be run on Sunday. It was held by the tidal court as matter of law that the agi’eement should not be so construed, and that the contract, so far as this question was concerned, was a legal one. The appellants claim that this l’uling 'was ei’roneous.
The contract is dated June 25,1893, and that day was Sunday. It is, howevei-, shown that it was in fact executed on Monday, June twenty-sixth. The defendants had a pavilion and a saloon or restaurant near Salina pier on Onondaga lake, and it was understood by the parties that the plaintiffs’ machine was be placed near the defendants’ place of business, and it was so placed. It was run by steam powei’, an engine, and there was an organ connected with it. The machine commenced to run, according to the evidence on the part of plaintiffs, on Sunday, the second of July, and continued tó run every day, including Sundays, up to about the eighteenth of J uly, when practically it stopped by reason of the failure of defendants to furnish coal for the engine. Whether the plaintiffs ‘ were without fault, and Avere l’eady to pei’fonn on their part for the time covered by the claim in this action, weie questions litigated at the trial and found by the jury in favor of the plaintiffs. On the fifth of July the defendants paid the plaintiffs $150 for the first week’s
By the contract it was in effect agreed that for the work of every seven days constituting a week, from a certain time to a certain time, the plaintiffs should be guaranteed and receive a certain compensation. This was to be paid weekly, and, therefore, it must necessarily have been the intention that every day in the week should be occupied. It was seven days’ work in a week, the earnings of which were guaranteed at a certain amount and to be paid for weekly. In this view the contract could not, consistently with the intent of the parties, be construed to give ah option to plaintiffs to work on Sunday or not, as they chose. The number of days that the machine ran was a material element in the guaranty, and effect should be given to the words “ seven days.”
If the language of a writing is ambiguous or indefinite, the practical interpretation of it by both parties is a consideration of importance. (Woolsey v. Funke, 121 N. Y. 92 ; Dodge v. Zimmer, 110 id. 18.) As said in Insurance Co. v. Dutcher ( 95 U. S. 273 ): “ There is no surer way to find out what parties meant than to see what they have done.” In the present case it is undisputed that the machine was in fact run upon Sundays during the time it was run under the contract.
We are of the opinion that the trial court erred in holding as. matter of law that, so far as this question was concerned, the contract was legal. The judgment must, therefore, be reversed.
HARDifr, P. J., and Martin, J., concurred,
J udgment and order reversed on the exceptions and a new trial ordered, with costs to abide the event.