Majority
Headnote
A recovery on the foreclosure of a mechanic's lien — not a bar to an action on the contract — evidence that work was stopped — effect on appeal of a failure to take exceptions.This is an appeal from a judgment entered on the verdict of a-jury at a Circuit and an order denying defendant’s motion for a new trial. The action is to recover for the breach of an alleged contract by which the plaintiff was to do certain grading for the defendant,, and the plaintiff claimed both for work done under the contract and for loss of profits on the remaining work on the ground that he was-prevented by the defendant from performing his contract.
The first claim urged by the defendant, that the verdict was-against the weight of evidence, is manifestly unfounded. The plaintiff testified to an agreement with defendant to do the work. The-defendant admitted that he made an agreement upon the subject but testified that it was conditional, that is, he told the plaintiff that he (defendant) was about to make a contract with one Jones for the whole work, and that in case such contract was made plaintiff must look to Jones. This qualification the plaintiff denied. These were the only witnesses who testified to the terms of the agreement, and, under the circumstances, the statement of the plaintiff is far more-probable than that of the defendant.
The claim that the recovery in an action to foreclose a mechanic’s-lien for the work actually performed barred a recovery therefor in this action has been decided by this court adversely to the defendant. (Raven v. Smith, 71 Hun, 197 .)
The objections to the questions as to the relation of Jones to the
Tbe report made to plaintiff by bis workmen, that they bad been stopped by tbe defendant, accompanied by proof by plaintiff’s son that the defendant did stop tbe work, was competent to show tbe reason why plaintiff ceased tbe further performance of tbe contract.
If tbe copy of tbe notice given by plaintiff was improperly received in evidence it cannot have harmed tbe defendant, for it sufficiently appeared by other evidence that at tbe time tbe notice was given tbe defendant repudiated any contract with the plaintiff.
The evidence of Fairchild (the engineer) as to the quantity of grading he estimated, was competent. The plaintiff had testified to a contract for grading tbe triangular plot down to the level of its three boundaries, the highroad, the railroad and the pipe line. The estimate or computation of tbe engineer was of the quantity necessary to grade the land down to a higher level than that given by the plaintiff. Of course the defendant was not bound by Fairchild’s plans of grading, but, assuming that the plaintiff was unable to prove tbe quantity of excavation required by the contract as he stated it, certainly it was competent to prove a quantity that must necessarily have been included in his contract, and forego his claim to the remainder. Under tbe testimony of Fairchild the quantity calculated and stated by him must necessarily have been less than that required by tbe contract.
A juror asked tbe court if tbe notice given by tbe defendant tbe next day, that be was going to band tbe contract over to Jones, was binding on the plaintiff. Tbe court answered : “ Not unless be consents, no.” To this answer the defendant excepted. We think that it was correct*. Certainly tbe notice itself could not have bound plaintiff unless he consented, or unless the contract was subject to the qualification testified to by the defendant. If the
The judgment and order denying motion for a new trial appealed from should be affirmed, with costs.
Brown, P. J., concurred; Dykman, J., not sitting.
Judgment affirmed, with costs.