Majority
Headnote
Foreclosure of a mechanic’s lien by a sub-contractor — assignment by the contractor of an installment due him— the assignee not a necessary party.This action was brought to foreclose a large number of mechanics’ liens upon the appellant’s property. There are eleven plaintiffs,
Dissent
Thereafter, and on June 24,1894, the action was referred and the trial proceeded before the referee until February 11, 1895, when it was finally submitted to him for his decision, and on the trial said Cloughly was sworn as a witness on behalf of the owner.
The order appealed from was granted upon the plaintiffs’ motion and against the objection of the appellant Vreelaud, and permits the plaintiffs to make said Cloughly, Nichols & Co. defendants, and directs the submission to the referee to be set aside and the trial reopened and the issue raised or to be raised by the amended complaint to be determined in the action. The referee has made affidavit that he can render a complete determination of the controversy without the presence of any other parties than those now before the court, and it is apparent froin the foregoing statement that Cloughly, Nichols & Co. are not necessary parties to the determination of the claims asserted by the plaintiffs. Such being the fact, the order is unnecessary and the trial should not be delayed.
The order should be reversed, with ten dollars costs and disbursements, and the motion denied, with ten dollars costs.
DyicmaN, J., concurred.
(dissenting):
It is familiar law that where, upon a trial of an equity cause, it appears that the presence of other parties is desirable to effectuate the objects of the action, they may be brought in upon the application of any party interested. They may also be brought in by the court on its own motion.
Order reversed, with ten dollars costs and disbursements, and motion denied, with ten dollars costs.