Majority
Headnote
Gontraator — failwe to perforin a substantial part of the work — a sub-contractor cannot recover under a ■mechanic's lien.The referee decided that the plaintiffs had a valid lien upon the premises of the appellant for the sum of $561.45, and that the defendant Emberson had a valid lien against the same premises for the sum of $252.38. On September 14, 1891, one Charles W. Banham entered into a contract with the appellant for the construction of a building, and on the same day entered into another contract with the “Children’s Fold” for the construction of a building on the appellant’s land with the appellant’s consent. The plaintiffs furnished material which was used in the buildings and filed their lien on March 23, 1893.
The referee found that at the time said lien was filed there was earned by Banham under said contract more than the sum of $561.45,
We agree with the plaintiffs’ counsel that Winmill’s relation to the transaction, so far at least as plaintiffs are concerned, was that of a sub-contractor, and that plaintiffs’ rights were in no way affected by the arrangement between Banham and Winmill by which the payments to be made under the contract were apportioned between them. But it appears that when the sixth payment came due two certificates were given, one of which for $1,140 was indorsed by Banham and delivered to Winmill. There is no question but that sum was then due to Winmill, and, on March eleventh, the Sheltering Arms paid to him upon it the sum of $500. The indorsement and delivery of this certificate to Winmill was an assignment to him pro tcmto of the sixth payment for a good consideration, and as it was executed and delivered before the plaintiffs’ lien was filed, gave to Winmill a preferential right to the amount due on the contract, and a subsequent lien- could not defeat his right to the money. (Lauer v. Dunn, 115 N. Y. 405 ; Stevens v. Ogden, 130 N. Y. 182 .)
There were other small sums paid to Winmill after the plaintiffs’ lien was filed, but none of them represented money due to Banham under the contracts, and were not applicable to the payment of the plaintiffs’ lien.
We are of the opinion that the only sum to which the plaintiffs’ lien attached was the sum of $100 due for extra work. Emberson was a sub-contractor with Winmill, who, after Banham abandoned his contract, entered into an agreemant with the Children’s Fold to complete its building. It does not appear whether Winmill’s com tract was verbal or in writing or what the terms of payment were.
Emberson alleged in his answer that such a contract was entered into between Winmill and the Children’s Fold with the knowledge
The case in respect to the facts stated cannot be distinguished from Larkin v. McMullin ( 120 N. Y. 206 ) or Hollister v. Mott (132 id. 18).
It was held in those cases that when there was a failure on the part of the contractor to perform a substantial part of the work, and no provision in the contract for its completion by the owner in the event of the failure of the contractor, and no understanding between them that the owner should proceed with the work, , and no failure on the part of the owner to perform his obligation under the contract, a sub-contractor could not recover.
There is in such a case nothing due to the contractor upon which the sub-contractor’s lien can attach.
We are also of the opinion that .the contract was not substantially performed by Winmill. The finding in the supplemental report in this respect does not amount to a substantial performance.
The testimony is that Winmill left the work uncompleted, and new contracts were made with other mechanics for its completion. The abandonment of the work was willful and precludes a recovery by a sub-contractor. (Van Clief v. Van Vechten, 130 N. Y. 571 ; Anderson v. Petereit, 86 Hun, 600 .)
The judgment in favor of Emberson must, therefore, be reversed and a new trial granted, with costs to abide the event. The recovery in favor of the plaintiffs must be reduced to $100 and
Pratt, J., concurred; Dykman, J., dissented.
Judgment in favor of Emberson reversed and new trial granted, costs to abide event. Judgment in favor of plaintiffs reduced to $100 and costs, and, as so reduced, affirmed, without costs.
Cases cited
- Lauer v. Dunn 115 N. Y. 405 p. 71
- Stevens v. Ogden 130 N. Y. 182 p. 71
- Larkin v. McMullin 120 N. Y. 206 p. 72
- Van Clief v. Van Vechten 130 N. Y. 571 p. 72