p. 7160. Lawton, for the appellant.
1. The ground of dismissal does not appear, and no reason is given in the case ; we must, therefore, look into the pleadings, and if, upon the case they present, an action can he maintained, a new trial must be granted. The defendants’ counsel did not pretend any surprise, nor suggest that they had been misled; they did not even oppose the motion to amend.II. The complaint is upon a contract for the construction' of three steam screw propellers, averring breaches, and specially setting forth the damages amounting to $45,447.19 ; but as the damages for non-performance were settled, fixed and liqui-, dated by the parties in the' contract at $20,000, judgment for that sum only was claimed.III. The defendants take issue upon that portion of the contract which states the modelling of the vessels and the specifications for building, &c. They deny that the damages were in fact fixed or liquidated, and claim that the words of the contract must be regarded merely as a penalty. They deny that the plaintiff had performed his part of the contract. They aver that the contract was waived by the parties, and a new agreement had between them, which they set forth ; that the time for completion had been extended. They admit that the vessels were not completed until long after the 1st day of March, 1863, but do not aver that they were ever completed. They admit the payment of $68,000, (about $10,000 more than ever became due by the terms of the contract,) and wind up with two counter-claims, amounting to $23,000 ; and thus the whole controversy between the parties is set forth in the pleadings, and fully placed before the court.IV. The contract was duly executed and delivered under the hands and seals of the parties, and no fraud is alleged or pretended; and in it they have fixed, settled and liquidated the damages at $20,000, and they are bound by it. The words are plain and their meaning unmistakable, and the court will not alter it or make a new contract for them.1. The damages were settled, fixed and liquidated by the
p. 717contract; the damages were uncertain and difficult to be ascertained. (Clement v. Cash, 21 N. Y. Rep. 256 , 258, 259. Westcott v. Thomson, 18 id. 363, 367 . Norton v. Woodruff, 2 id. 153, 16, 469. Cotheal v. Talmage, 5 Seld. 551.)2. If not, then the court should have ruled, as claimed in the answer, “ that the words were to be regarded merely as a penalty,” and allowed the trial to proceed, leaving the parties to their remedy, by motion, if harm should result to either ; this would have been fair, just and legal. It was just such decisions as this, that certain sections of the Code were adopted to prevent. (Code, §§ 169,170,173,174.)3. Although it does not in either view of the case seem to require an amendment for the trial of the case, yet, regarding the case as the court did, the amendment ought to have been allowed.V. The complaint sets forth a cause of action, and there is no rule, practice or law by which the plaintiff can be turned out of court, without being allowed the attempt, at least, to prove it. The prayer is always for such judgment as the plaintiff supposes himself entitled to, but the recovery is upon the cause of action. (Code, § 142, subd. 3.) As to what a cause of action is, see Meyer v. Van Collem, ( 28 Barb. 231 .)
YI. The summons is no part of the trial record; in this case, it was not before the court, and no point was made upon it, and none can be raised here for the first time. If wrong, the only remedy is by motion at the special term.VII. The complaint was improperly and arbitrarily dismissed, and a trial should be allowed, with costs to abide the event.Ban Marvin, for the respondents.
I. The court decided rightly in dismissing the complaint. The plaintiff was not, upon the allegations of the complaint, entitled to the relief he demanded. The sum of $20,000 in the last clause of the contract was a penalty. The words cc liquidated damages ” do not determine the question. The intent of the parties is to be gathered from a consideration of
p. 719at all, can only be claimed upon a total, and not upon a partial failure to perform. The complaint states a case of partial performance by the defendants. (Reynolds v. Brady, 37 Eng. Law and Eq. 123.)Y. The plaintiff was not entitled to the relief asked for in his complaint, and in the opening of his counsel, and he did not ask to be allowed to establish or prove any other case entitling him to relief. The only request made by his counsel was to be allowed to amend the prayer of his complaint, so as to allow him to prove the actual damages, and when his request was denied, although he stated that he was prepared to prove the actual damages, yet he did not offer or ask leave to do so. (Bishop v. Houghton, 1 E. D. Smith, 566. Reubens v. Joel, 3 Kern. 488. Towle v. Jones, 19 Abb. 449 .)YI. The decision of the court denying the plaintiffs motion to amend cannot be reviewed on appeal, nor is it the subject of an exception. (Gould v. Rumsey, 21 How. 97 . McQueen v. Babcock, 13 Abb. 268 .) And if it could, the amendment asked for would not" have benefited the plaintiff, as it would not have permitted the introduction of any evidence, except what was already admissible.
The admission and exclusion of evidence does not depend upon the prayer of the complaint, but upon the allegations and statements therein.By the Court,
The complaint in this case was dismissed on the trial, undoubtedly, on the ground that it showed no right to recover the liquidated damages claimed by the plaintiffs’ counsel in his opening. In this the court would probably have been right, if the complaint showed no other cause of action. By the terms of the agreement set out in such complaint, no other act was required to be performed by the plaintiff but the payment of money. So that the clause as to liquidated damages, as to him, could only be construed as a penalty. (Bagley v. Peddie, 16 N. Y. Rep. 469 . Beale v. Hayes, 5 Sandf. 640 . Lampman v. Cochran,
p. 72016
N. Y. Rep. 275 .) And could not be construed differently as to the defendants.
(See Lampman v.
Cochran, ubi sup.)But the complaint did show a good cause of action in the agreement therein set forth and its breach, and even averred special damages thereby. The fault committed by the plaintiffs’ counsel in his opening, of claiming liquidated damages only, was forthwith repaired, by stating his ability to prove the special damages, and asking leave to amend the demand of relief in his complaint for that purpose, if necessary, the moment it was brought to his attention by the motion of the counsel for the defendants. He had as yet no opportunity of offering any evidence, so that if the dismissal was not sustained by an inherent vice in the complaint, it was erroneous. If the opening of the plaintiffs’ counsel, in stating an untenable point of law, to wit, that he was entitled to the sum fixed as liquidated damages, could be relied on, in case he adhered to it, to sustain such dismissal, its abandonment as soon as made relieves the case of that difficulty.
The prayer for relief becomes of course wholly immaterial after the defendant has answered ; the plaintiff being entitled to any which the case made in his complaint warrants. (Code, § 275.) The dismissal of the complaint was therefore erroneous, and there must be a new trial,