Majority
Headnote
A tender of cotton four days after the making of a contract for its sale and delivery (there being no time specified in the contract) is too late, and the purchaser is absolved from all obligation to receive it; what is a reasonable time is a question of law, to be determined from all the facts and circumstances in the case; and there being no facts or circumstances in the case which denoted an intention to allow any but an immediate delivery, a tender after four days was properly refused.By the Court:
There were no disputed facts in this case, and therefore no question for the jury. The main facts were sufficiently , established, and the only question to be examined is, whether upon such facts the direction of the learned justice was correct. The contract of sale was made on the 21st of November. On that day, and again on the next day, the defendants demanded a delivery. The cotton was not delivered, for the reason that it had not been discharged from the 'vessel. On the 25th a delivery was tendered and refused.
The contract did not specify any time for the delivery, nor were there any extrinsic facts or circumstances which can materially aid the court in determining upon the time the parties had in which to perform. The case must, therefore, be disposed of upon principles applicable to contracts, which are silent in respect to the time for their execution.
The question resolves itself into this: Did the demand made by the defendants on the 21st and 22d, and the inability, refusal, or neglect of the plaintiffs to deliver on those days, put an end to the contract and discharge the defendants; or, did the plaintiffs have until the 25th to make delivery ?
The general rule is, that where goods are to be delivered, and no time is specified in the contract, it is a presumption of law that
There is one fact in this case, which was proven, I suppose, with the view of aiding the Court in determining the question of reasonable time, which was, that at the time of the contract the cotton was on board the steamer “ Zodiac,” then reported as being in the harbor; that on coming up the bay she got aground, and her cargo had to be lightered to the city. That fact does not, however, in my judgment, help us in ascertaining what would be a reasonable' time for delivery, however much it might, under certain circumstances, perhaps, excuse a delivery. It was not contemplated by the parties that any casualty would prevent an immediate execution of the contract, and cannot, therefore, be presumed to have entered into their intentions.
I cannot find any thing in the contract, or in any surrounding-fact or circumstance, to excuse an immediate delivery, or at least a delivery on demand.
The commodity sold was capable of an immediate delivery, and no particular space of time was required to complete the sale by the symbolical delivery usual in such cases. The cotton was to be received by the purchaser upon the wharf. Placing it upon the wharf and giving an order for its delivery to the purchaser, would constitute a delivery, and it, would thereafter be his property and at his risk.
There is nothing in the character of the property sold that would indicate that four days would not be an unreasonable time for its delivery; nor is there any thing in the circumstances of the sale that would lead us to the conclusion that the plaintiffs had the right to tender performance on the fourth day after the sale.
If any thing is to be gained extrinsically, it is, that in the absence of express stipulations fixing the time of performance, parties intend and mean an immediate performance, provided, of course, the contract is capable of such performance; and it would not be unfair to presume that the parties, in the case before us, contemplated, as well as intended, that the cotton should be de
As I have said before, the casualty which prevented a delivery on that day cannot enter into the question of reasonable time; for it may very well be, that to the defendants the delivery on the day of purchase was of the very essence of the contract. They might have purchased for immediate re-shipment or re-sale, either or both of which would have been defeated by the plaintiffs’ delay.
I am of opinion, therefore, that the delay of four days in tendering a delivery was unreasonable, and that the refusal or neglect of the plaintiffs to deliver on the demand of the defendants relieved the latter from all responsibility.
The exceptions should he sustained, the verdict set aside, and a new trial ordered, with costs to defendants to abide the event.