Majority — Lamae J.
Syllabus
ERROR TO THE OIROUXT COURT OF THE UNITED STATES FOR THE DISTRICT,, OF ÍNDIANA.after stating the case as above, de-( livered the oninion of the court. '
The main questions to be determined in the first branch- of this case are these :
(1) Did the modification-of .the original specifications ancj profile, made, in August, 1884, fall within: the original con ‘tract, or-did it create a feature in the work to be done, so different from that originally contracted for as to put the defendants in error in a position to maké as to that feature a new contract ? -•
(3) Did the court err- in refusing to charge, as prayed, “that the plaintiffs [below] are entitled to recover only for so much excavation as was actually done for the purpose of making such ditch, excluding any portion of the borrow-pits dug exclusively"for the purpose of making the embankments”?
We shall briefly consider those questions seriatim.
First. ’A careful examination of the specifications and profile, and of the testimony in the case, all set forth in the bills of exceptions, satisfies us that the requirement to construct a continuous drainage ditch parallel to the embankment, four and one-third miles long, and of the dimensions ordered, did create a new'problem in the work not covered'by.the original contract. • The ditch was'required to have a fall of nearly two feet to the mile; to be two feet wide at the bottom at one end, and to increase in size to six-feet bottom width at the other end; ■ and throughout, the sides were required to be scaled one and one-half foot horizontal measure to one foot perpendicular. The testimony shows that' in one portion,- at least, it was nine, feet deep. It was made to drain off the water from the, prescribed area,' and to take the place of the county ditches. On this point McGrath, one of the defendants in error, testified that “ to make the borrow-pits serve for a ditch it was necessary to haul the earth from the high ground,.where the embankment was low, to the low grounds, where the embankment was - high, whereas but for the ditch, the earth from the embankment would have been taken directly from the' sides; that this in many places necessitated a longer haul of earth, and increased the cost of the embankment.”
Wasson, who was a sub-contractor, testified that before, the change was made he “had taken earth, from borrow-pits about twenty inches deep, and, afterwards -had to dig to the depth .of nine feet, to make the ditch, and was required to haul this extra excavation, some' of it six hundred feet.”
Robinson testified that “if the'work was changed so as to require a continuous ditch, it could not be done as cheaply as
Fisher, a witness for defendants in error, testified that “ he was a civil engineer of thirty-five years’ experience, and largely as railroad engineér. If the specification's .provided that the earth for embankment should be borrowéd' equally from both sides, and then a continuous ditch should be required to be made on one side of the embankment, it would necessitate a greater haul and would be more expensive. In consequence of the ditch a greater amount.of earth would have to be" taken from the side on whióh the ditch is made; One cannot' work to such an advantage in a narrow ditch as in a broad borrow-pit. The deeper you go, the harder the earth is to work.”
Outside of the testimony of the witnesses, it is manifest that to dig earth on a surface rolling and broken, as the profile shows' the surface to have been in this instance, for the sole purpose of constructing a level embankment, and without regard to the depth 'or extent or level of the pits thereby made, is a very different problem from the digging with the double view of the construction of such an embankment, and the making of a continuous ditch with prescribed directions and uniform bottom level for a length of more than four miles.
It is true that, as the plaintiff in error says, the profile shows ditching in these' same sections, covered by the original contract, to the amount of 4660 cubic yards; but it1 also- is true that those ditches were of a very different character, and imposed no such burden on the contractor as did the one in question. Indeed, the plaintiff in error itself treated the modification as a serious change, and especially so considered the ditch, before the controversy arose. In the correspondence between the two engineers of the company; which determined on it, it is spoken of as a new system.
• In Damon v. Granby, 2 Pick. 345 , the inhabitants of the' town of Granby had voted that certain persons thirteen in number should be a committee to procure a master builder, and superintend the building of a meeting-house for the town. On the trial of the case, which was an action of debt by the builder of the meeting-house pn the contract made with the comftttbtee, the defendants objected that the superintending committee had nó' authority to contract for the building of the house. The court held that the voté of the inhabitants gave to this committee the authority to enter into the contract. “ To superintend the building of the house,” says the court, i! includes the power to make the necessary contracts,” etc. See also Story on Agency, § 79;
Third. Nor do we think the court below erred in refusing to charge the jury that the defendants in error were only entitled to recover for such excavation as was actually done for • the purpose of making such ditch, as distinguished from such portion of, the ideal ditch as coincided in space with the' bor-ro w-pits, as portions thereof. In some cases, nay, in most cases, that worild be a proper charge, perhaps, but not in this
As to the second branch of the case, viz., that in respect to the .piling, it is objected by the plaintiff in error that. the instruction of the court was erroneous for the' following reasons: First. Because in spéaking of the 700 feet still not paid for, the court said: “ If you find upon the proof that there was an agreement between plaintiffs and Mr. -Hurlburt that these piles should be paid for at what they were reasonably worth,”' etc.; while there was no evidence tending to show that Hurlburt made the agreement therein supposed. But there was such evidence. Byan, one of the plaintiffs below, had testified that “ we ha’d no contract for this work, and before we began -it I had a conversation with Mr. Hurl-burt about it. I wanted to know what we would be paid for it, and he said that Mr. Yaughan would do what was right.” This was claimed to.be a contract for reasonable compensation. It was for the jury to say whether the conversation was with a contractual intent or not. The court had no right to assume as a matter of law that it was not, and refuse a
"We do not think that the acceptance of thirty cents for some of the trestles precluded the plaintiffs as to the value of others.
The judgment of the court below is
Affirmed.