Majority — Brewer J.
Syllabus
APPEALS PROM THE COURT OF CLAIMS.after making the foregoing statement, delivered the opinion of the court.
This case turns on the release executed by the building company on May 18, 1896. It is contended by the claimant that it applies simply to 'claims springing out.of the construction of the vessel, and therefore has no application to the matters for which the judgment was rendered against the Government. The word “construction,” the company says, is limited'to the mere matter of building; that is, the furnishing of materials, the doing of work, and does not include delays or other matters outside the building of the vessel.
To rightly understand the. scope of this release we must consider the conditions of the contract, and especially the clause in it which calls for' a release. The contract was a large one, the price to be paid for the wor,k and material being over $3,000,000, and "the contract was evidently designed to cover all contingencies. Provision was made for changes in the specifications, for penalties on account of delays of the contractor, deductions in price on certain conditions, approval of the work by the Secretary of the Navy, forfeiture of- the contract, with authority to the Secretary to complete the vessel. The last paragraph contains the stipulations as to the amounts and times of payment with authority for increase of the gross amount upon certain conditions. The sixth clause of this paragraph makes special provision for the last payment, to be made “ when all the conditions, covenants, and provisions of said contract shall have been performed- and fulfilled by and on the part of the party of the first part,” and “on the execution of a final release to the United States in such form as shall be approved by the Secretary of the Navy, of all claims of any kind or description under or by virtue of said contract.” Evidently the parties contemplated and specially provided by this stipulation that the whole matter of the contract should be ended at the time of the final release and the last payment. That which was to be
Stipulations of this kind are not to be shorn t>f their efficiency, by any narrow, technical and close construction. The general language “all and all manner of debts,” etc., indicates a purpose to make an ending of 'every matter arising under or by virtue of,the contract. If parties intend to leave some things open and unsettled their intent so to do' should be made manifest. Here was a contract involving three millions of dollars, and after the work was done, the vessel delivered and accepted and this release entered, claims are presented amounting to over $500,000. Surely the' parties never intended to leave such a bulk of' unsettled matters. As bearing upon this matter, it may be noticed that while the release was signed and the contract between the building company and the Government closed on May 18, 1896, this action was not brought until August 10, 1897, nearly a year and á quarter thereafter.
We are of opinion that the parties by the release of May 18, 1896, which was executed in performance of the requirements of the original contract, - settled all disputes between the parties as to the claims sued upon.
The judgment of the..Court of Claims is reversed and the case .remanded with instructions to enter a judgment on the findings for the defendant-.
MR. Justice McKenna and- Mr. Justice Moody took no part in the decision of this cá'se. '