Majority — McKenna J.
Syllabus
APPEAL FROM THE COURT OF CLAIMS.delivered, the opinion of the court.
The question in this case is the legality of certain deductions made by the Postmaster General from the amount
The controversy turns upon the application of certain acts of Congress, granting parts of the public domain to appellant and to companies with which it has agreements. The acts provide that the United States mails shall be transported on such roads at such rates as Congress may by law direct. Act of May 15, 1856, 11 Stat. 9 , c. 28; Act of March 3, 1857, 11 Stat. 195 , c. 99. Subsequently it was provided as follows:
“Sec. 13. That railroad companies, whose railroad was constructed in whole or in part by a grant of land made by Congress on the condition that the mails should be transported over their road at such price as Congress should by law direct, shall receive only eighty per centum of the compensation authorized by this act.” Act of July 12, 1876, 19 Stat. 78 , 82, c. 179.
The postal route begins at Minneapolis tand consists of land-aided and non-land-aided roads. The following diagram, taken from the Government’s brief, though not drawn to any scale of measurement, exhibits with enough accuracy for illustration the aided and non-aided parts of the route and the companies which received aid.
It will be observed that appellant is the direct beneficiary of the road from St. Paul south 237.81 miles to a point north from a place marked as Le -Mars. It used the other parts of the route under the contracts with the other companies, and it is- found that from some time prior to October 1, 1900, appellant used the tracks of such other companies to “form a continuous route for the operation of its mail trains, made up of its own rolling stock and controlled and operated by its
The contract of the appellant with the Iowa Falls and Sioux City Railway Company may be said, as far as the question in the case is concerned, to be substantially the same. Its provision as to the use of tracks is more comprehensive. It permits also appellant to do local business, • sixty per cent of gross receipts of which, however, are to be paid to the C?wa Fails Company. There is a provision for maintenance repairs, based on car mileage. The rental stipulated, is ;><50 per mile for the use of each mile of main track.
It is found that appellant had no part in the construction of the tracks of the Great Northern Company or of the Illinois Central Company, and received no benefit on account of their construction by grants of land or otherwise; that ever since the construction of the tracks the respective companies owning them have operated trains and transported United States mails over them, and that the use of the tracks by those companies does not appear to have been limited by appellants
The contentions of the parties are foreshadowed by the facts which we have recited. It may be conceded, appellant says, that the grants of land to the companies to which they were made “completed contracts between them and the United States,” and it may be further conceded, it is said, “that by these contracts privity was established between the United States and these various railroad companies.” But succession to the obligation of the contract is denied because appellant “has not succeeded to the title or any part of the title of these respective roads, nor has it in any way directly or indirectly received any benefit from the respective grants or done any other thing which creates privity of contract between it and the United States or which makes it, in the language of the thirteenth section of the act of 1876, a railroad company ‘whose railroad was constructed in whole or in part by a grant of land/ ” etc.
This distinction is earnestly insisted on and is made the foundation of the argument of the appellant. It makes irrelevant, it is urged, the consideration of the obligations of the other companies, and by overlooking it the Court of
The order denying application for injunction was pleaded in the Court of Claims, as it appears from the opinion of the court, as res judicata of the "subject-matter” there involved, and therefore the full breadth of the contentions of the railroad company in the Circuit Court and of the decision of that court was considered by the Court of Claims, and all of the elements of decision and all the distinctions which depended upon them the court must have taken into account in rendering its decision.
We are brought then to the question whether the decision of the court was right. Certain concessions are made by appellant at the outset of the argument. It is conceded that the acceptance of the land grants by the "owned and aided companies” completed a contract between them and the United States, and that privity was established between them and the United States. That is privity (we use the word, as we presume that counsel does, in the sense of party for the United States, and the companies are parties', not successors, to rights or obligations) of contract, a personal obligation, that is, not an obligation which attached to the property and covered every use of it. This is necessarily what appellant means, though it is confused in discussion.
And further, it points out, as we have seen, that it has not succeeded “to the title or any part of the title” of the roads, nor “directly or indirectly receives any benefit from the respective grants.” And, finally, it urges that if appellant “is a mere licensee, owing no contractual duty as a corporate individual to the Government, owning no railroad property which is pledged to the Government as security for the performance of any duty, and operating its trains on the joint track in such manner as to interfere in no wise with its licensor in the transaction of its business and the performance of its contractual duty to the Government, it is difficult to understand how appellant can be held to fall within the terms of the thirteenth section of the act of 1876, or why it does not stand upon the same footing as any other company without privity with the United States.”
This is stating by periphrase the simple proposition that there is a contract only between the United States and each of the aided companies, in which such company “has bound itself ” [we quote from appellant’s brief] “ to operate trains for the transportation of the Government business.” And “ whenever” appellant says “one of these companies shall fail to perform its duty, whatever relief the United States may be entitled to must be sought by appropriate proceedings directed against the delinquent company.” Appellant joins to this'as a concession that the “railroad property” of an aided company “is pledged to secure the performance” of its obligation. In what way is not pointed out, or how the security can be availed of.
The opposite contention to that of appellant is, therefore, what it was decided to be by the Court of Claims, that the ■ obligation is upon the property of an aided, company, and
We have noticed and commented on one concession of appellant. Another is made, which we quote with its qualifications, as follows: “We do not contend that a land-aided road can be sold, either in whole or in part, so as to avoid its obligations to the government. To this extent we concede that the obligation runs with the railroad aided by land grant, but the act does not say that companies permitted simply to run trains on the road shall suffer reductions. They receive no aid from the grant, and are neither within the terms or the reason of the statute.” .Of course, the statute did not deal with other companies or with deductions. It would be very strange if it had. It either imposed a service on the companies or on the road as well. ■ If on the companies alone, there would necessarily be exclusion of all others. If on the roads as well, it would comprehend all that used them. If a difference in degree of use or a participation in the use by other companies than the aided ones, had been intended it would have been expressed. The concession as to the effect of the sale or lease of the road is fatal. As we have already said, the obligation is either upon the aided companies, to be enforced by remedies against them, or it is on the property as well, and if on the property, necessarily on it by whatever company or person it is used.
It is further contended in the brief filed for the Great Northern that the condition of earning its grant was the building of a single track and it or its grantors, it is said, has provided several. It has therefore, it is further said, “a surplus of track capacity and, by contract, permits the Omaha [appellant] and other companies to run their trains over its tracks.” To this it is only necessary to reply that the service that the Government reserved was coextensive with
Again, it is urged that if the Omaha Company had built its own road there would be no assertion of a right to deduct from its mail pay, and that it is to run over the Great Northern, the latter riot being made thereby less useful or efficient, is fob its purpose equivalent to building its own road. An answer to this is contained in what we have said. We may add, however, that the appellant no doubt considered the advantages and disadvantages of the alternative presented before making its selection, but it could not have supposed, nor can we admit, that it could lessen rights in property because it could acquire like property for itself.
Union Pacific v. Chicago &c. Ry. Co., 163 U. S. 564 , and Lake Superior & Mississippi R. R. Co. v. United States, 93 U. S. 442 , are cited as authorities against eur conclusion. We content ourselves by saying that they have not that effect. On United States v. Astoria Company, 131 Fed. Rep. 1006 , we have commented.
Judgment affirmed.