Majority — McKenna J.
Syllabus
ERROR TO THE CIRCUIT COURT OP THE UNITED STATES FOR THE EASTERN DISTRICT OP LOUISIANA.delivered the opinion of the court.
Defendant in error was indicted for violation of the act.
The indictment set out in proper form that defendant in error had violated the law by permitting and requiring his employés engaged in building a public levee on the Mississippi River, which was part of the public wdrks of the United States, to work more than eight hours “ on the 17th day of August, 1908, at a time and under circumstances when there was no extraordinary emergency, for the reason that at that season of the year, to-wit, during the months of August, September, October, and November and December, the waters of the Mississippi River annually ■ fall below the level of the surrounding land and are retained within the banks of said river without the necessity of any artificial levees, as was true on August 17, 1908.” It is further charged that the levees were being constructed in the usual and ordinary course of levee building done annually for the increase in size and strength of such levees, in preparation for the high waters that come down the river, the levees being of standard size and sufficient to resist usual high water, but not unusual high waters, that occasionally, although not every year, come down the river, it being the policy, rule and custom of the Government to increase the standard of levees by destroying inferior levees and replacing them with stronger and higher ones year by year until the levees shall all be brought to a standard able to withstand any unusual floods. And it is further charged that the particular
Defendant demurred to the indictment, on the ground that it did not set forth any offense against the laws of the United States or any violation of the laws of the United States. The demurrer was sustained.
In passing upon the demurrer the court said that the defendant rested his case upon the proposition “that the building of levees on the Mississippi River, in the Eastern District of Louisiana, at all times presents an extraordinary emergency,” and hence that the work on the river is exempt from the operation of the law. The court took judicial notice of the fact asserted and sustained the conclusion from it. The court said that certain facts were within the common knowledge of the people of the district, which, taken in connection with the specific allegations of the indictment,, overcame the mere conclusion of the pleader that no extraordinary emergency existed, and instanced the following: The work on the levees was absolutely necessary for the preservation of property
From these facts the court assumed the existence of others, as follows ( 180 Fed. Rep. 502 , 503):
“It is true that the months of August, September, October, November and December are the most favorable for levee building, but there is no certainty that during any part of these months the river will maintain a low Stage. When the river is bank full, necessarily no levees can.be built. Statistics of the river’s height, at New Orleans, show that during the past 25 years the river has been bank full on nearly every day of the year, and these statistics may well apply to the locality where the defendant was working. An unprecedented rain, or an early freeze followed by a thaw, anywhere in the valley of the Mississippi River or its tributaries, might unexpectedly cause the river to rise at New Orleans. No one can foresee or anticipate, the acts of nature, and who can say that a few days’ more time, in which it might have become solidified, would not have so materially added to the levee’s strength as to enable it to withstand the pressure, and without which it might signally fail.”
The Government insists that the qourt assumed too extensive a judieial knowledge, and urges that the most important of the assumed facts, that the river has been bank full almost' every day in the year, and the extension of the fact to the locality where defendant was working, is contradicted by the official hydrographs, 1871 to 1907 and 1907 to 1911, attached to the Government’s brief, from which it appears that, at Carrollton, which is a
The building and repair of levees on the Mississippi Rivér is one of the most important and conspicuous of the public works of the United States, and if it had been intended to exempt it from the provisions of the act of August 1, 1892, which declared a public policy in regard to labor, it would have been expressed. There is no hardship in this to a contractor. He has before him the law and the conditions affecting the work which he may undertake and can govern himself accordingly.
Judgment reversed, and cause remanded with directions to overrule the demurrer.