Majority — Holmes J.
Syllabus
ERROR TO THE CIRCUIT COURT OP APPEALS FOR THE SEVENTH CIRCUIT.delivered the opinion of the court.
This is a suit to recover an alleged preference from the defendant in error. The Circuit Court of Appeals reversed.a judgment recovered by the plaintiff and ordered judgment for the defendant. 219 Fed. Rep. 397 ; 135 C. C. A. 139 . This writ of error was taken out before the passage of the Act of January 28,1915, c. 22, § 4, 38 Stat. 803,804 . .
The facts are these:.On May 9, 1910, the Warren Construction Company, the bankrupt, had contracted to do some construction for a railroad company, receiving monthly payments on account, and agreeing that if at any time there should be evidence of any lien for which the railroad might become liable and which was chargeable to the Warren Company the railroad might retain an amount sufficient to indemnify it. Should there prove to be such a claim after the payments were made the Warren Company agreed to refund all moneys the railroad might be compelled to pay in discharging any lien made obligatory in consequence of the Warren Company’s default. The Warren Company gave a bond with sureties for the performance of this contract. Later it made a
In 1911 the Root Company notified the railroad that it was not being paid and that it would not furnish more material unless the railroad would see that it was paid. The railroad gave the assurance and the Root Company continued to furnish the materials called for by its contract. Seemingly the payments continued to be unsatisfactory and on November 18, 1911, after the Root Company had performed its contract there was unpaid $12,895.34. On November 25, 1911, the Root Company filed statutory notices of its intention to hold a lien upon the railroad’s property for the amount then due. On January 12, 1912, after conferences of all parties concerned, a contract was made between the railroad, the Warren Company and its sureties, reciting controversy as to whether the Warren Company’s contract, had been performed, the filing of claims for hens and attachment suits for more than the sum admitted by the railroad to be due, and the railroad’s assertion of its right against the surety companies. This contract fixed $42,000 as a sum to be paid by the railroad in full settlement of the mutual claims between it and the Warren Company, and provided that with $20,000 to be. furnished by the surety companies the sum should be put into the hands of named, trustees ‘to be used in paying all. henable claims’ growing out of the construction contract. If the fund was not sufficient to pay henable claims in full, the surety companies were' to furnish the additional money necessary. After ah henable claims were paid, the balance, if any, of the fund was to be paid first to reimburse the surety companies for their contribution'
On April 10, 1912, a written contract was made between the railroad, the sureties, the Warren Company and the Root Company, which recited the claim of the Root Company and that the railroad had money, in its hands held back under its contract with the Warren Company for the purpose of protecting the road against liens, and agreed that. $6,447.67 should be paid to the Root Company by way of compromise, that the Root Company should assign its claim to the trustee under the former instrument, surrendering to the Warren Company notes for sixty per cent, of its claim, and that the trustee should reassign to the Root Company the unpaid portion of its claim when attachments against the fund had been disposed of. The payment was made the same day and the Root Company executed a release as agreed. The sum was a larger percentage than will be received by the unsecured creditors of .the Warren Company but a smaller one than that received by any other subcontractors with a lieh. The petition in bankruptcy was filed on July 18, 1912, and the above payment was a preference if it stood as a payment to an unsecured creditor in the circumstances on the date when it was made.
The Circuit Court of Appeals held that the instrument of January 12 created an equitable lien that justified the payment, although it was of opinion that the lien asserted by the Root Company could not have been enforced. The plaintiff in error contends that the provision in favor of ‘lienable claims’ was confined to those that were secured by a valid lien. We express no opinion as to whether the lien of the Root Company asserted against the property of the railroad could have been defeated by its contract with the Warren Company notwithstanding the Warren Company’s default. It is enough that we agree with the ultimate view of the Circuit Court of
Decree affirmed.
Cases cited
- Continental & Commercial Trust & Savings Bank v. Chicago Title & Trust Co. 229 U. S. 435 p. 161
- Coder v. Arts 213 U. S. 223 p. 161
- Globe Bank & Trust Co. of Paducah v. Martin 236 U. S. 288 p. 161
- 18 Wall. 624 18 Wall. 624 p. 162
- Greey v. Dockendorff 231 U. S. 513 p. 162
- Hewit v. Berlin Machine Works 194 U. S. 296 p. 162
- Ketchum v. St. Louis 101 U. S. 306 p. 162
- Knapp v. Milwaukee Trust Co. 216 U. S. 545 p. 162