Majority — Holmes J.
Syllabus
APPEAL FROM THE COURT OF CLAIMS.delivered the opinion of the court.
This is an appeal from a judgment of the Court of Claims dismissing the claimant’s petition ■ upon demurrer. On August 15, 1908, the claimant made a contract with Captain Brown of the Engineers, acting for the United States, to excavate a channel from Beaufort Inlet to Pamlico Sound through Core and Adams Creeks in conformity with specifications made part of the contract. It was approved on September 10 and required the work to be begun within forty-five days after date of notification of approval, September 14, and to be-completed within eighteen months. The work not having been finished on time .$7,320 of the agreed compensation was withheld as liquidated damages and $210.50 as additional costs of superintendence and inspection, $7,530.50 in all, for which sum this suit is brought.
The petition alleges that after getting through Core Creek to and through the headwaters of Adams Creek to a point on tide water about five miles from its mouth, where for a mile and a half it averages more than .1200' feet wide and for the next three miles and a half 2500 feet, the stumps and roots of a submerged forest were encountered at about eight feet below the bottom of the water, which made it impossible to do the work with the ordinary machinery and in the ordinary way, or tó finish. the work by the time agreed. It is alleged that the forest was submerged by some abnormal force and violence of the elements, and that it could not have been discovered by the ordinary methods of inspection and was not discovered in fact, although the claimant and others and the Government had. exercised every known precaution and had made exhaustive examinations with the utmost care and skill. The petition sets up that this was a prevention ‘by abnormal, force and violence of the elements’ within
As has been implied already the contract agreed “that time shall be considered as an essential feature of this contract, and that in case of the failure upon the part of the party of the second part to complete this contract within the time as specified and agreed upon that the party of the first part will be damaged thereby, and the amount of said damages being difficult, if not impossible of definite ascertainment and proof, it is hereby agreed that the amount of said damages shall be estimated, agreed upon, liquidated, and fixed in advance, and they are hereby agreed upon, liquidated, and fixed at the sum of twenty (20) dollars for each division for each and every day the' party of the second part shall delay in the completion of this contract ” and the claimant agrees to pay that amount ‘as liquidated damages, and not by way of penalty.’ It is agreed further that the United States shall have the right to recover all costs of inspection and superintendence incurred by it during the period of delay, and that it may
There is a proviso that if the claimants 'shall by strikes, epidemics, local or state quarantine restrictions, or by the abnormal force or violence of the elements, be actually prevented from completing the work ... at the time agreed upon’ without contributory negligence on his part 'such additional time may, with the prior sanction of the Chief of Engineers, be'allowed him’ . . . 'as, in the judgment of the party of the first part, or his successor, shall be just and reasonable.’ As we have intimated, the specifications also state that the time allowed is considered sufficient ‘unless extraordinary and unforeseeable conditions supervene.’ The claimant further thinks that he finds some support for . his argument in á provision that ‘solid rock, large bowlders, and compact gravel will not have to be removed at the prices bid for ordinary excavation. If such materials should be encountered their removal, if required by the engineer, will be done under special agreement and paid for as extra work.’ On the other hand the claimant was' required to remove all trees and “The channel must be cleared of all snags, logs, roots, stumps, or wreckage that project into or encroach in any way upon the cross section, . . . the cost of same being included in the unit price bid for .excavation.” The claimant invokes a provision that the engineer’s decision as to quality, quantity and interpretation of the specifications shall be final; and this ends the statement of his case.
It is hopeless to argue against the provisions that we have recited, and the further express warning that each bidder ‘‘is expected to examine and decide for himself, as no allowance will be made should any of it prove to be otherwise than as stated,’ except as above recited with regard to solid rock, &c. It is suggested that the special agreement to be made for the removal of ‘such materials’
The allegations by which the claimant attempts to avoid his contract making time of the essence, that the damages were difficult to prove and that therefore they should be fixed at twenty dollars a day, are too specula
Judgment affirmed.
Cases cited
- United States v. Barlow 184 U. S. 123 p. 185
- 138 U. S. 187 138 U. S. 187 p. 185
- District of Columbia v. Gallaher 124 U. S. 505 p. 185
- Garrison v. United States 7 Wall. 688 p. 185
- United States v. Gibbons 109 U. S. 200 p. 185
- Kihlberg v. United States 97 U. S. 398 p. 185
- Sun Printing & Publishing Ass'n v. Moore 183 U. S. 642 p. 185
- Tayloe v. T. & S. Sandiford 7 Wheat. 13 p. 185
- United States v. Bethlehem Steel Co. 205 U. S. 105 p. 185, p. 190
- 175 U. S. 589 175 U. S. 589 p. 185
- Buren v. Digges ex rel. Libbey 11 How. 461 p. 185
- Carnegie Steel Co. v. United States 240 U. S. 156 p. 189