Majority — Brand J.
Syllabus
APPEAL FROM THE COURT OF CLAIMS.delivered the opinion of the Court.
On August 30, 1905, claimant’s intestate entered into a contract with the United States to instal the interior fin
To recover that sum (and. others) the contractor brought this suit in the Court of Claims. He contended that, since the Government had caused some of the delay, the provision for liquidated damages became wholly inapplicable and was unenforceable; and that, since the Government had failed to prove actual damage, it was not entitled to any damages whatsoever. The court found that of' the 121 days of delay, only 61 days were chargeable to -the- contractor; and that the remainder were caused by the Government, after the date of the supplemental contract. It accordingly gave the claimant judgment (among other things) for $20,160, being that part of the amount withheld which represented the delay in excess of 61 days. 57 Ct. Clms. 7. The case is here on claimant’s appeal. Whether on these facts the provision for liquidated damages governs is the main question for decision.
The original contract provided that the contractor “ shall be allowed one day, additional to the time herein stated, for each'’ and every day of . . . delay [that may be caused by the Government] ”; “ that no claim shall be
The provision is not against public policy.' The law ■required that some provision for liquidated damages be inserted. Act of June 6, 1902, c. 1036, § 21, 32 Stat. 310 , 326. In construction contracts a provision giving liquidated damages for each day’s delay is an appropriate means of inducing due performance, or of giving compensation, in case of failure to perform; and courts give it effect in accordance with its terms, Sun Printing & Publishing Association v. Moore, 183 U. S. 642 , 673, 674; Wise v. United States, 249 U. S. 361 ; J. E. Hathaway & Co. v. United States, 249 U. S. 460 , 464. The fact that the Government’s action caused some of the delay, presents no legal ground for denying it compensation for loss suffered wholly through the fault of the contractor. Since the contractor agreed to pay at a specified rate for each day’s delay not caused by the Government, it was clearly the intention that it should pay for some days’ delay at that rate, even if it were relieved from paying for other days, because of the Government’s action. If it had appeared that the first 61 days’ delay had been due wholly
It is also assigned as error that the court sustained a deduction by the Government from the contract price of the amount'paid by it for certain repairs. The contract contained a guarantee, by the contractor of the condition of the work for one year after acceptance. The specifications provided for window sashes of solid oak. After the contract had been signed,- and before putting in the windows, the contractor called the architect’s attention to the fact that solid oak is not well suited for a damp climate and locality, like that of lower New York City;, and he suggested a modification of .the specifications to avoid warping. The. suggestion .was not accepted. By reason, in part, of warping which occurred within a year after ■acceptance of the work, extensive repairs became necessary. He was requested by the Government to make the repairs, but refused to do so. Then the Government had them made, by others.. The Court of Claims found-that
The contractor contends that the Government’s refusal to adopt the modification proposed relieved him from the obligation under the guarantee. The contention is fin-sound. He entered into a contract plain- and comprehensive in terms. There was no finding of mutual mistake,. or of fraud, misrepresentation or concealment on the part of the Government or any of its officers or employees. Under such circumstances, the contractor cannot be relieved from an obligation deliberately assumed. Wells Brothers Co. v. United' States, 254 U. S. 83 ; MacArthur Brothers Co. v. United States, 258 U. S. 6 . If the warping had been caused entirely by the adoption of wood unsuitable to the climate, it may be that, as a matter of construction, the guarantee would not extend thereto. But. the findings do not present such a case. The case is wholly unlike United States v. Spearin, 248 U. S. 132 ; United States v. Atlantic Dredging Co., 253 U. S. 1 ; United States v. Smith, 256 U. S. 11 .
Affirmed.
Cases cited
- Sun Printing & Publishing Ass'n v. Moore 183 U. S. 642 at 674 p. 488
- Wise v. United States 249 U. S. 361 p. 488
- J. E. Hathaway & Co. v. United States 249 U. S. 460 p. 488
- United States v. Bethlehem Steel Co. 205 U. S. 105 p. 489
- Carnegie Steel Co. v. United States 240 U. S. 156 at 164 p. 489
- United States v. United Engineering & Contracting Co. 234 U. S. 236 p. 489
- Wells Bros. v. United States 254 U. S. 83 p. 490
- MacArthur Bros. v. United States 258 U. S. 6 p. 490
- United States v. Spearin 248 U. S. 132 p. 490
- United States v. Atlantic Dredging Co. 253 U. S. 1 p. 490
- United States v. Smith 256 U. S. 11 p. 490