Majority — Brand J.
Syllabus
APPEAL PROM THE COURT OP. CLAIMS.delivered the opinion of the Court.
This is an appeal from the judgment of the Court of Claims which dismissed the petition on demurrer. Plaintiff’s claim is in character the same as that sued on in St. Louis, Kennett & Southeastern R. R. Co. v. United States, decided this day, ante, p. 346.. It is presented in the same manner; and the Government makes the same defense. The provision for settlement and release of claims here relied upon is substantially the same as in that case. But, in other respects, the contract is entirely different. It is in the form, known as the per diem, contract, which contains no operative provision other than that providing for settlement and release of claims.. The rést of the dócu-, ment consists of recitals and the testimonium clause. The consideration for the settlement and release is therein stated to be “ obtaining the advantages of the two days’ free time or,reclaim allowance and such other co-operation as is accorded to it by the Director General of Railroads.”
The petition alleges that the Director General gave no more than he would have been obliged by law to give had no agreement been made. This is not true.' But it is,- in any event, without legal significance. The plaintiff’s agreement embodying the release was under seal. Hence, it is binding even if without a consideration. The petition alleges, also; that the agreement “ was accépted by the
As in the St. Louis Company case, the Director General clearly had authority to enter into the agreement in question.
Affirmed.
Cases cited
- United States v. Child & Co. 12 Wall. 232 p. 352