Majority — Butler J.
Syllabus
CERTIORARI to the circuit court of appeals for the NINTH CIRCUIT.delivered the opinion of the Court.
Petitioner sued in the United States court for the district of Idaho to recover damages alleged to have been sustained by reason of respondent’s negligence and false representations in respect of certain local improvement bonds. Respondent demurred to the complaint; the district court held that it failed to state a cause of action and dismissed the case. The Circuit Court of Appeals affirmed. 18 F. (2d) 860 . ' The petition to this Court for a writ of certiorari stated that the decision below conflicts with the decisions of this Court and of the Circuit Courts of Appeals for the Third and Eighth; Circuits.[1] The writ was granted. 275 U. S. 515 .
* Peake v. New Orleans, 139 U. S. 342 . District of Columbia v. Lyon, 161 U. S. 200 . Barber Asphalt Paving Co. v. City of Harrisburg, 64 Fed. 283 . Barber Asphalt Paving Co. v. City of Denver, 72 Fed. 336 . City of Mankato v. Barber Asphalt Paving Co., 142 Fed. 329 . Bates County, Mo., v. Wills, 239 Fed. 785 . Oklahoma City, v. Orthwein, 258 Fed. 190
A transcript of the proceedings and that certificate were submitted to the attorneys, who are acting for petitioner in this case, for examination as to the validity of the bonds. And they, it is alleged, relying upon the recitals in the bonds and the statements in the certificate, gave a written opinion that the bonds were valid. The complaint alleges that on July 13, 1921, petitioner, relying upon such recitals, certificate and opinion, purchased three of these bonds. And petitioner says that the statement in the certificate was material because no suit to enjoin the making of special assessments or to set them aside may be brought after the expiration of thirty days from
He insists that respondent was negligent in failing to have a proper estimate and valid assessments made and in causing the false certificate to be issued, and that the damages claimed were caused by the negligence and misrepresentation. The suit is for tort. The demurrer was rightly sustained, unless the complaint shows that a breach by respondent of some duty it owed petitioner caused the damage claimed.
Each bond states that respondent acknowledges itself to be indebted and promises to pay bearer the sum stated; it contains recitals to the effect that all the things by law required in respect of the creation of the district, the construction of the sewer and the issue of the bond in order to make it a valid obligation of the city have been done. It states that the total cost of the work has been assessed and that the assessments are liens upon the land; that provision has been made for, and the city guarantees, the collection of assessments sufficient to pay accruing interest and principal at maturity. But, as required by statute, each bond declares that the holder shall have no claim against the city except for the collection of the assessments; that his remedy in case of non-payment shall be confined to their enforcement, and that the interest and principal shall be payable out of that fund and not otherwise. The bonds are not negotiable. United States Mortgage Co. v. Sperry, 138 U. S. 313 , 343. It is clear
The bonds were void, as held in the Lucas case, because issued upon assessments made in excess of the engineer’s estimate. On the facts disclosed by the complaint, actionable negligence cannot be predicated. on the failure of respondent’s officers properly to exert their powers and perform their duties in respect of the estimate, assessment and contract for construction of the sewer. Such failure was not a breach of duty owed by respondent to petitioner. He had no relation to the matter until long after the bonds had been issued and sold to another. The facts showing their invalidity were disclosed by the transcript and known to the attorneys on whom he relied long before he purchased them. The complaint is not grounded on anything subsequently occurring.
It remains to be considered whether petitioner may recover by reason of the certificate issued March 8, 1921, falsely stating that there was no suit in respect of the creation of the district, the construction of the sewer or the issue of the bonds. No law required or authorized the making of any certificate. The statutes do not content-
This action is not based on contract. Recovery is not claimed on the ground that respondent was empowered to pay for the work out of funds belonging to it or upon any promise that it would do so. • As no actionable negligence or misrepresentation is shown, the lower courts rightly held that no cause of action is stated in the complaint. We find no conflict between the decision of the Circuit Court of Appeals in this case and the decisions referred to in the petition for this writ.
Judgment affirmed.
Cases cited
- 275 U. S. 515 275 U. S. 515 p. 537, p. 538
- Hitchcock v. Galveston 96 U. S. 341 p. 537
- Peake v. New Orleans 139 U. S. 342 p. 537
- District of Columbia v. Lyon 161 U. S. 200 p. 537
- New Orleans v. Warner 175 U. S. 120 p. 538
- Salt Lake City v. Hollister 118 U. S. 256 p. 538
- United States Mortgage Co. v. Sperry 138 U. S. 313 p. 540