Majority — Stone J.
delivered the opinion of the Court.
Respondent brought this suit in the District Court for Eastern Pennsylvania to recover on a bond given by petitioner, as surety, to secure the performance of a government construction contract as provided by the Heard Act, which requires the contractor to furnish a surety bond to the government as obligee, conditioned upon satisfactory performance of the contract and payment by the contractor for labor and material furnished by subcontractors for the construction. Act of August 13, 1894, 28 Stat. 278 ; as amended, Act of February 24, 1905, 33 Stat. 811 , and March 3, 1911, 36 Stat. 1167 ; 40 U.S.C.A., § 270. In authorizing suits on the bond, the Heard Act provides:
“ If no suit should be brought by the United States within six months from the completion and final settlement of said contract, then the person or persons supplying the contractor with labor and material shall . . . have a right of action . . . provided that . . . it . . . shall be commenced within one year after the performance and final settlement of the said contract and not later . . .”
The contract was for materials for use in the construction of an irrigation project and was entered into on behalf of the United States by the Department of the Interior under the provisions of the Reclamation Act of June 17,1902, 32 Stat. 388,389 ; 43 U.S.C.A., § § 391,419. Under date of June 16, 1927, the First Assistant Secretary of the Department of the Interior forwarded the claim of the contractor to the General Accounting Office “ for direct settlement,” by a letter which stated that the contract had been completely performed and that, after deducting a stipulated amount as. liquidated damage for delay in performance, the balance due was $8,889.30. The letter concluded: “The claim has received administrative examination, is approved for $8,889.30 and I recommend that the amount found due be paid” from a designated ap
The defense to the present suit on the bond was that it had been begun October 17, 1928, more than one year after performance and final settlement of the contract. The sole question presented is whether “ final settlement,” within the meaning of the Heard Act was effected by the action of the Interior Department of June 16, 1927, or only by the certificate of the General Accounting Office of October 26th. Judgment for the petitioner by the District Court was reversed by the Court of Appeals for the Third Circuit, 66 F. (2d) 302 , which held that the Budget and Accounting Act of 1921, 42 Stat. 23 , 31 U.S.C.A., §§ 41, et seq., had transferred the authority to make settlements of such contracts from the Department of the Interior to the General Accounting Office, that consequently final settlement did not occur until the action of the General Accounting Office upon the contractor’s claim, and that the suit brought within a year was in time. Certiorari was granted to resolve an alleged conflict between this decision and that in Consolidated Indemnity & Insurance Co. v. W. A. Smoot & Co., 57 F. (2d) 995 ; compare Lambert Lumber Co. v. Jones Engineering & Construction Co., 47 F. (2d) 74 .
' The Budget and Accounting Act set up the General Accounting Office under the direction of the Comptroller General of the United States. Section 304, 31 U.S.C.A., . § 44, transferred to it the powers and duties of the Comptroller of the Treasury and of the six Auditors of the Treasury Department, and authorized the heads and disbursing officers of executive departments to apply for the decision of the General Accounting Office upon any question involving a payment to be made by them, which de
1 The history, procedure and function of the Accounting Office of the Treasury before 1921 and of the General Accounting Office are discussed in detail in Smith, The General Accounting Office (Institute for Government Research, Service Monograph No. 46); Willoughby, The Legal Status and Functions of the General Accounting Office (Institute for Government Research, Studies in Administration). The settlement and adjustment of claims against the government receive particular treatment in Willoughby, c. IV.
In the light of this history we cannot say that Congress, merely by transferring the function previously performed by the Treasury to the General Accounting Office, intended to disturb this construction of the statute or to make final administrative determinations in the executive departments any the less final settlements within the meaning of the Heard Act than they had been before. Consolidated Indemnity & Insurance Co. v. W. A. Smoot & Co., supra.
It is true, as respondent points out, that the question thus raised is different from that involved in the earlier cases, where payment preceded audit by the accounting office, and from that in the Peeler case. The contract in the Peeler case was under the administrative control of the Treasury Department and when that case arose and was decided the power to settle contracts, now lodged with the Comptroller General, was in the Treasury Department. Thus the question presented there was not whose was the authority to make the final settlement, but' at what stage the decision of the department, authorized to make it, became final. Here the question is whether the decision of the Comptroller General supplanted that of the Department of the Interior, which concededly would have been a final settlement if there had. been no action by the Comptroller General before payment. This question must be resolved in view of the purpose sought to be accomplished by the Heard Act and of the administrative procedure for the settlement, auditing and payment of claims against the government.
The Heard Act relates only to. bonds given as surety for those entering into contracts for the construction of public buildings or works. It serves the dual purpose of securing to the United States the protection of a surety
The policy of the statute to afford protection to the interests of laborers and material men would not be effected unless they were allowed to bring suit with reasonable promptness after the United States has determined that it will have no claim on the bond and unless the date of final settlement which fixes the time within which suit is permitted could be ascertained with reasonable certainty and finality. A determination, made and recorded in accordance with established administrative practice by the administrative officer or department having the contract in charge, that the contract has been completed and that the final payment is due, fulfills these requirements. See Illinois Surety Co. v. United States to the use of Peeler, supra. Such was the determination made here by the Interior Department, which alone was in possession of the- knowledge. and data necessary to prompt decision. The Department, in' forwarding the claim, made every determination prerequisite to payment. See Illinois Surety Co. v. United States to the use of Peeler, supra; Mandel v. United States, supra. It declared that the contract had been completely performed; it stated the balance due after deducting the stipulated amount for liquidated damages for delay; it déclared that the claim had received, administrative examination and
No such consequences either to the government or to subcontractors can result from treating the departmental settlement as the final one within the .meaning of the Heard Act. There is no more occasion for delaying suit on. the bond because of the contingency that the departmental determination may not be approved by the Comptroller General in his auditing of the accounts, than because of the contingency that any administrative determination may not be approved by the courts. See Illinois Surety Co. v. United States to the use of Peeler, supra, 221 ; Consolidated Indemnity & Ins. Co. v. W. A. Smoot Co., supra, 997.
A different question would be presented if the department concerned declined to settle the claim and referred it to the General Accounting Office for settlement. See Lambert Lumber Co. v. Jones Engineering &. Const. Co., supra.
Reversed.