Majority — Caedozo J.
delivered the opinion of the Court.
We are to. determine the measure of damages upon a bond conditioned against loss through the failure to complete a building at the time and in the manner called for by the building contract.
On December 16, 1930, the borrower made default under the mortgage, abandoning the work with the building then unfinished. At that time the petitioner’s advances under the building loan agreement were $6,575,-000, the full amount promised, less $75,000 retained by agreement. On December 18, 1930, petitioner through its nominee brought suit in the state court for the foreclosure of the mortgage. On January 6, 1931, it went into possession with the mortgagor’s consent. On January 19, 1931, there was a judgment of foreclosure, followed by a sale on March 17, 1931, at which the mortgagee was the buyer, the bid of $6,000,000 being applied upon the mortgage.- A-deficiency judgment of $716,215.02 was entered the next month.
Petitioner in' possession of the building went on with the unfinished work, bringing it to completion in October, 1931. An action on the bond was. then begun against the sureties. The trial court gave judgment for damages in the sum of $798,416.81, made up of three classes of items:
Limiting our review accordingly, we think the extent of the recovery upon the new trial that will be necessary has been too narrowly confined.
The petitioner should be placed in the same position it would have occupied if the building had been completed on December 16, 1930. Trainor Co. v. Aetna Casualty & Surety Co., supra, at pp. 54, 55 ; Kidd v. McCormick, 83 N. Y. 391 , 398; Province Securities Corp. v. Maryland Casualty Co., 269 Mass, 75 , 94; 168 N.
The petitioner might have relied upon the testimony of experts as to the total depreciation and as to the weight of the component factors. It chose a different method. To show the loss sustained from finishing the work, it proved the actual cost, as by the express provisions of the bond it was at liberty to do. Cf. Comey v.
A question is raised as to the form of the complaint. The respondents insist that its allegations are insufficient to permit proof of loss of rents in addition to the cost. We read the pleading otherwise. In the circumstances of this case, loss of rents is to be reckoned as general, not special, damage. Sedgwick, Damages, 9th ed., § 1261; Griffin v. Colver, supra; Cassidy v. Le Fevre, supra; Ruff v. Rinaldo, supra; Jutte v. Hughes, 67 N. Y. 267 , 271. It is one of the factors contributing to and measuring the diminished worth of the security. Damages when general are recoverable under a pleading that does not
Another trial will permit the petitioner to show more accurately than it has done upon the record now before us that the building was continuously untenantable until the completion of the work and that the time taken for completion did not outrun the bounds of reason.
What was ruled by the Court of Appeals in respect of the scope of the recovery for omissions and substitutions was not specified as error in the petition for the writ, and., will be' assumed to be correct. Zellerbach Paper Co. v. Helvering, 293 U. S. 172 , 182; Helvering v. Taylor, 293 U. S. 507 , 511; Clark v. Williard, 294 U. S. 211 , 216.
The judgment is modified by a direction that the measure of damages upon a new trial shall be that defined in this opinion, and as thus modified affirmed.
Modified and affirmed.
Cases cited
- 7 F. Supp. 392 7 F. Supp. 392 p. 205
- Trainor Co. v. Aetna Casualty & Surety Co. 290 U. S. 47 p. 205, p. 206
- Freedman's Saving & Trust Co. v. Shepherd 127 U. S. 494 p. 206
- W. B. Worthen Co. v. Kavanaugh 295 U. S. 56 p. 206
- New York & Colorado Mining Syndicate & Co. v. Fraser 130 U. S. 611 at 623 p. 207
- Zellerbach Paper Co. v. Helvering 293 U. S. 172 p. 208
- Helvering v. Taylor 293 U. S. 507 p. 208
- Clark v. Williard 294 U. S. 211 p. 208