p. 33FEDERAL POWER COMMISSION v. TEXACOINC. ET AL.
CERTIORARI TO THE UNITED STATES COURT OF APPEALS FOR
THE TENTH CIRCUIT.
No. 386. Argued March 25, 1964.—Decided April 20, 1964.
1. A Court of Appeals granted review of a Federal Power Commis-
sion (FPC) order concerning a contract performed in its circuit
involving natural gas produced there by two respondent natural
gas companies incorporated outside the circuit, the principal place
of business of one (A) being within the circuit; that of the other
(B) being without. Respondents proceeded under § 19 (b) of the
Natural Gas Act, which provides for review in the court of appeals
wherein the aggrieved natural gas company “is located or has its
principal place of business.” Held: The Court of Appeals erred
in failing to dismiss the petition of respondent B for lack of venue,
since the term “is located” in § 19 (b) means more than having
physical presence in a place and refers in the case of a corporation
to the State of its incorporation. Pp. 37-39.
2. Pursuant to § 16 of the Natural Gas Act and § 4 of the Adminis-
trative Procedure Act, the FPC after a hearing given to interested
parties, including respondents, at which they were allowed to sub-
mit their views in writing, issued regulations providing for the sum-
mary rejection of contracts with pricing provisions other than those
specified in the regulations as being “permissible.” Under § 7 of
the Natural Gas Act, which includes a provision for an FPC
hearing, respondents each submitted an application for a certifi-
cate of public convenience and necessity to supply natural gas
to a pipeline. Since the applications disclosed price clauses im-
permissible under its regulations, the FPC rejected the applications
without a hearing. Its order on review was set aside by the Court
of Appeals. Held:
(a) The “hearing” satisfied the requirements of § 4 of the Admin-
istrative Procedure Act. P. 39.
(b) The requirement for a hearing under § 7 does not preclude
the FPC from specifying statutory standards through the rule-
making process and barring at the outset those like respondent A
whose applications neither meet those standards nor show why in
the public interest the rule should be waived. United States v.
Storer Broadcasting Co., 351 U. S. 192, followed. Pp. 39-41.
p. 34(c) The present regulations pass on the merits neither of any
rate structure nor of a certificate of public convenience and ne-
cessity; they merely prescribe qualifications for applicants. P. 42.
(d) The FPC need not proceed on a case-by-case basis where its
policy outlaws all indefinite price-changing provisions. P. 44.
(e) A plenary adversary-type hearing under § 7 of the Natural
Gas Act and § 5 of the Administrative Procedure Act would have
been necessary had there been an adjudication on the merits as to
whether respondent A could qualify for a certificate of public con-
venience and necessity. But the only determination made—after
the adequate rule-making hearing under § 4 (b) of the Administra-
tive Procedure Act—was not one on the merits but only that
respondent A’s application was not in proper form because of the
impermissible price-changing provisions in the contract upon which
the application depended. Pp. 44-45.
317 F. 2d 796, reversed.
Howard E. Wahrenbrock argued the cause for peti-
tioner. With him on the brief were Solicitor General
Cox, Ralph S. Spritzer, Richard A. Solomon, Josephine H.
Klein and Peter H. Schiff.
Alfred C. DeCrane, Jr. argued the cause for respondent
Texaco Inc. With him on the brief was Paul F. Schlicher.
Carroll L. Gilliam argued the cause for respondent Pan
American Petroleum Corp. With him on the brief were
W. W. Heard, Wm. H. Emerson and William J. Grove.
J. Calvin Simpson and John T. Murphy filed a brief
for the State of California and the Public Utilities Com-
mission of California, as amici curiae, urging reversal.
Mr . Justi ce Douglas delivered the opinion of the
Court.
The Federal Power Commission in its regulation of
independent producers 1 of natural gas has required them 1
p. 35to file their contracts as rate schedules. This was done
by regulations which evolved as a result of a series of
rule-making proceedings.2 The pertinent regulations
presently provide that only certain pricing provisions in
the contracts of independent producers are “permis-
sible,” 3 any other being “inoperative and of no effect at
law.” 4 The regulations go on to say that any contract
executed on or after April 2, 1962, containing price-
changing provisions other than the “permissible” ones,
“shall be rejected” so far as producer rates are concerned,5
that a producer’s application for a certificate of public
convenience and necessity under § 7 of the Natural Gas
Act “shall be rejected” if any contract submitted in sup-
port of it contains any of the forbidden provisions,6 and
that, so far as pipeline certificates are concerned, any pro-
ducer contract executed after that date which has that
2 See Order No. 174-B, 13 F. P. C. 1576, 18 CFR § 157.25; Order
No. 232, 25 F. P. C. 379, 26 Fed. Reg. 1983, as amended by Order No.
232A, 25 F. P. C. 609, 26 Fed. Reg. 2850; Order No. 242, 27 F. P. C.
339, 27 Fed. Reg. 1356; Reg. § 154.91 et seq., as amended, 18 CFR
(Cum. Supp. 1963) § 154.91 et seq.
3 Section 154.93 defines the “permissible” provisions:
“(a) Provisions that change a price in order to reimburse the seller
for all or any part of the changes in production, severance, or gather-
ing taxes levied upon the seller;
“(b) Provisions that change a price to a specific amount at a
definite date; and
“(c) Provisions that, once in five-year contract periods during
which there is no provision for a change in price to a specific amount
(paragraph (b) of this section), change a price at a definite date
by a price-redetermination based upon and not higher than a producer
rate or producer rates which are subject to the jurisdiction of the
Commission, are not in issue in suspension or certificate proceedings,
and, are in the area of the price in question . . . .”
4 Ibid. For a discussion of escalation clauses see Pure Oil Co..
25 F. P.
p. 36infirmity “will be given no consideration in determining
adequacy” of a pipeline company’s gas supply.7
These regulations were adopted pursuant to the pro-
visions of § 4 of the Administrative Procedure Act, 60
Stat. 238, 5 U. S. C. §
1003. General notice of the pro-
posed rule making was published in the Federal Register
as required by § 4 (a) of that Act. The Commission also
gave interested parties a “hearing” under § 4 (b).8 No oral
argument was had but an opportunity was afforded for all
interested parties to submit their views in writing; and
the two respondents in this case—Texaco and Pan Ameri-
can—along with others, did so.
Later, each respondent submitted an application for a
certificate of public convenience and necessity under § 7
of the Natural Gas Act, to supply natural gas to a pipeline
company. Section 7 provides, with exceptions not pres-
ently material, that the Commission “shall set” such an
application “for hearing.” Since, however, the applica-
tions disclosed price clauses that are not “permissible”
under the regulations,9 the Commission without a hearing
p. 37rejected the applications. 28 F. P. C. 551; 29 F. P. C. 378.
Petitions for review were filed with the Court of Appeals,
which set aside the orders of the Commission. 317 F. 2d
796. It held that while the regulations are valid as a
statement of Commission policy, they cannot be used to
deprive an applicant of the statutory hearing granted
those who seek certificates of public convenience and
necessity. The two cases are here in one petition for
certiorari which we granted because of an apparent con-
flict between that decision and Superior Oil Co. v. Fed-
eral Power Comm’n, 322 F. 2d 601, decided by the Court
of Appeals for the Ninth Circuit. 375 U. S. 902.
A preliminary question, which concerns Texaco Inc.,
alone, is whether venue to review these orders of the
Commission was properly in the Tenth Circuit. The
governing provision is § 19 (b) of the Natural Gas Act
which provides:
“Any party to a proceeding under this Act
aggrieved by an order issued by the Commission in
such proceeding may obtain a review of such order
in the court of appeals of the United States for
any circuit wherein the natural-gas company to
which the order relates is located or has its principal
place of business, or in the United States Court of
Appeals for the District of Columbia . . . .”
The term “is located” would have an ambivalent mean-
ing if venue lay only in “any circuit” where the natural
gas company “is located.” But in the context of § 19 (b)
“any circuit” covers either the place where the company
future, e. g., the passage of 5, 10, or 15 years, increased taxation
on the production, severance, gathering, transportation, sale, or deliv-
ery of gas or as a result of renegotiations undertaken six months prior
to the beginning of the third (1974) and fourth (1979) of the four
five-year periods into which the contract term was divided.
p. 39corporated. See 9 Fletcher, Cyclopedia Corporations
( 1931 ), § 4385. That theme runs through the cases. See,
e. g.,
Shaw v. Quincy Mining Co., 145 U. S. 444, 449-450.
We conclude that, although “located” sometimes is used
as indicating a place of business (Mercantile Nat. Bank v.
Langdeau,
371 U. S. 555), in the setting of this Act “is
located” and “resides” are equated and that “is located”
refers in the case of Texaco to its State of incorporation.
There is symmetry in that construction as the choice,
so far as circuits are concerned, is then left between that
State, the “principal place of business” (with no penum-
bra of other places of business, as here), or the District of
Columbia where the Commission sits.
Texaco is a Delaware corporation and there is no claim
that its principal place of business is within the Tenth
Circuit. The Court of Appeals therefore erred in failing
to dismiss its petition for lack of venue. There is, how-
ever, another respondent, Pan American, whose principal
place of business is within the Tenth Circuit. We there-
fore proceed to the merits of its application.
The main issue in the case is whether the “hearing”
granted under § 4 (b) of the Administrative Procedure Act
is adequate, so far as the price clauses are concerned, for
purposes of § 7 of the Natural Gas Act. We think the
Court of Appeals erred, that the present case is governed
by the principle of
United States v. Storer Broadcasting
Co., 351 U. S. 192, and that the statutory requirement for
a hearing under § 7 does not preclude the Commission
from particularizing statutory standards through the rule-
making process and barring at the threshold those who
neither measure up to them nor show reasons why in the
public interest the rule should be waived.
In Storer the Federal Communications Commission,
pursuant to its general rule-making authority, limited
p. 40permissible multiple ownership for radio and television
stations. Storer, which had seven radio stations and five
television stations, was under that rule automatically dis-
qualified for further licensing. To surmount that barrier
it argued that the Act required a license to issue where
the public interest would be served and that before an
application could be denied, a hearing must be held. We
said:
“We read the Act and Regulations as providing a
‘full hearing’ for applicants who have reached the
existing limit of stations, upon their presentation of
applications conforming to Rules 1.361 (c) and 1.702,
that set out adequate reasons why the Rules should
be waived or amended. The Act, considered as a
whole, requires no more. We agree with the con-
tention of the Commission that a full hearing, such
as is required by § 309 (b) . . . would not be neces-
sary on all such applications. As the Commission
has promulgated its Rules after extensive adminis-
trative hearings, it is necessary for the accompanying
papers to set forth reasons, sufficient if true, to jus-
tify a change or waiver of the Rules. We do not
think Congress intended the Commission to waste
time on applications that do not state a valid basis
for a hearing. If any applicant is aggrieved by a
refusal, the way for review is open.”
351 U. S., at
205.
In the present case, as in Storer, there is a procedure
provided in the regulations whereby an applicant can ask
for a waiver of the rule complained of.11 Facts might con-
p. 41ceivably be alleged sufficient on their face to provide a
basis for waiver of the price-clause rules and for a hearing
on the matter. Cf. Atlantic Refining Co., 28 F. P. C.
469; 29 F. P. C. 384. But no such attempt was made
here by Pan American, the only respondent to which the
present point has any immediate applicability.
The rule-making authority here, as in Storer, is ample
to provide the conditions for applications under § 4 or § 7.
Section 16 of the Natural Gas Act gives the Commission
power to prescribe such regulations “as it may find neces-
sary or appropriate to carry out the provisions of this
Act.” We deal here with a procedural aspect of a rate
question and with a certificate question that is important
in effectuating the aim of the Act to protect the consumer
interest. Federal Power Comm’n v. Hope Natural Gas
Co.,
320 U. S. 591, 610. In a rate case under § 5 (a) of the
Act the Commission can pass on existing contracts affect-
ing rates, can find that particular contracts are “unjust,
unreasonable, unduly discriminatory, or preferential” and
thereupon has power to determine the “just and reason-
able” rate or contract and “fix the same.” And see
United
Gas Pipe Line Co. v. Mobile Gas Service Corp., 350
U. S. 332, 341. And where, as here, applications for cer-
tificates are made under § 7 of the Act, the Commission
under § 7 (e) is required to control the terms and condi-
tions under which natural gas companies, such as respond-
ent, may initiate sales at wholesale of natural gas in
statutory provision or other authority therefor. If a rate filing is
accompanied by a request for waiver pursuant to this section the
thirty-day notice period provided in section 4 (d) of the Natural
Gas Act and section 205 (d) of the Federal Power Act shall begin
to run if and when the Commission grants the request. Such petition
shall set forth the purpose of, and the facts claimed to constitute
the grounds requiring, such rule, amendment, waiver, or repeal, and
shall conform to the requirements of §§ 1.15 and 1.16. Petitions for
the issuance or amendment of a rule shall incorporate the proposed
rule or amendment.”
p. 42commerce. Atlantic Refining Co. v. Public Service
Comm’n,
360 U. S. 378, 389.
Pan American does not disagree on that score; it
insists that those changes and adjustments can be made
only after an adversary hearing. To that there are two
answers. The present regulations do not pass on the
merits of any rate structure nor on the merits of a cer-
tificate of public convenience and necessity; they merely
prescribe qualifications for applicants. Those qualifica-
tions are in the category of conditions that relate to the
ability of applicants to serve the consumer interest in this
regulated field. They are kin to the kind of capital struc-
ture that an applicant has and to his ability by reason of
the rate structure to serve the public interest. It must be
remembered that under this Act rate increases are ini-
tiated by the natural gas company, the Commission hav-
ing the burden by reason of § 4 (e) of the Act to initiate
a hearing on their legality with only a limited power to
suspend new rates. See United Gas Pipe Line Co. v.
Mobile Gas Service Corp., supra. Natural gas com-
panies that seek to enter the field with prearranged
escalator clauses and the like have a built-in device for
ready manipulation of rates upward. Protection of the
consumer interests against that device may be best
achieved if it is given at the very threshold of the enter-
prise. At least the Commission may so conclude; 12 and
p. 43the legislative history makes clear that its authority
reaches that far. H. R. Rep. No. 1290, 77th Cong., 1st
Sess., pp. 2-3, states:
. . The bill when enacted will have the effect
of giving the Commission an opportunity to scru-
tinize the financial set-up, the adequacy of the gas
reserves, the feasibility and adequacy of the proposed
services, and the characteristics of the rate structure
in connection with the proposed construction or
extension at a time when such vital matters can
condition which requires correction if regulatory objectives embraced
by the statute are to be achieved. See American Trucking Associa-
tions v. United States,
344 U. S. 298. In our view, the rule we adopt
fully meets this test.
“We held in the Pure Oil case [see note 4, supra] that indefinite es-
calation clauses are contrary to the public interest and restated this
conclusion in Order No. 232A. Increases in producer prices, triggered
by indefinite escalation clauses, have resulted in a flood of almost
simultaneous filings. These filings bear no apparent relationship to
the economic requirements of the producers who file them. The
Natural Gas Act contemplates that prices, to be just and reasonable,
be related to economic needs. The elimination of indefinite escalation
provisions does not, of course, cut off other avenues by which a
producer may make provision for filing for increased rates.
“Filings under indefinite escalation clauses have created a significant
portion of the administrative burdens under which this Commission
is laboring today. The Natural Gas Act contemplates that rate
increases shall be sought when there is economic justification, but
not that there shall be a chain reaction in a wide area whenever one
producer in the area negotiates a contract at a new price level. The
Act requires the Commission to give precedence to the hearing and
decision of rate increases, but the complexity of indefinite price
clauses requires it to spend an undue amount of time in their inter-
pretation and application at the expense of making a prompt deter-
mination of the rate issues involved. Accordingly, in protecting the
public against waves of increases which have no defensible basis, we
also serve the need—which we believe we should take into account—
of making the tasks of regulation more manageable.” 27 F. P.
p. 44readily be modified as the public interest may de-
mand. . . .” (Italics added.)
And see S. Rep. No. 948, 77th Cong., 2d Sess., pp. 1-2.
To require the Commission to proceed only on a case-
by-case basis would require it, so long as its policy out-
lawed indefinite price-changing provisions, to repeat in
hearing after hearing its conclusions that condemn all of
them. There would be a vast proliferation of hearings,
for as a result of
Phillips Petroleum Co. v. Wisconsin,
347 U. S. 672, there are thousands of individual producers
seeking applications. See Wisconsin v. Federal Power
Comm’n,
373 U. S. 294, 300. We see no reason why under
this statutory scheme the processes of regulation need be
so prolonged 13 and so crippled.
Pan American finally argues that the “hearing” ac-
corded it under § 4 (b) of the Administrative Procedure
Act14 did not comply with that Act nor with the Natural
Gas Act. It points out that § 7 of the Natural Gas Act
requires a hearing and that § 5 of the Administrative Pro-
cedure Act provides, with exceptions not relevant here,
that a full-fledged adversary-type of hearing be held in
“every case of adjudication required by statute to be
determined on the record after opportunity for an agency
hearing. . . .” “Adjudication” is defined in § 2 (d) of
the Administrative Procedure Act as “agency process
for the formulation of an order”; “order” is defined
as “the whole or any part of the final disposition . . .
of any agency in any matter other than rule making but
13 In one recent case seven years elapsed between the date of the
new rate filing and the close of the review proceedings. Shell Oil Co.,
18 F. P. C. 617, 19 F. P. C. 74, set aside sub nom,. Shell Oil Co. v.
Federal Power Comm’n,
263 F. 2d 223, rev’d sub nom.
Texas Gas
Transmission Corp. v. Shell Oil Co., 363 U. S. 263; on remand, aff’d
sub nom. Shell Oil Co. v. Federal Power Comm’n,
292 F. 2d 149,
cert, denied,
368 U. S. 915.
p. 45including licensing.” And “licensing” is defined as
“agency process respecting the . . . denial ... of a
license.” § 2 (e). What the Commission did in these
cases, however, is not an “adjudication,” not “an order,”
not “licensing” within the meaning of § 2. Whether Pan
American can qualify for a certificate of public conven-
ience and necessity has never been reached. It has only
been held that its application is not in proper form
because of the pricing provisions in the contracts it
tenders. No decisions on the merits have been reached.
The only hearing to which Pan American so far has been
entitled was given when the regulations in question were
adopted pursuant to § 4 (b) of the Administrative
Procedure Act.
Reversed.
Mr . Justic e Stewart , dissenting in part.
I agree with Part I of the Court’s opinion, holding that
the petition of Texaco Inc. should have been dismissed
for lack of venue. I cannot agree, however, that a gas
producer’s application for a certificate of public con-
venience and necessity can be rejected without the full
adjudicative hearing to which § 7 of the Act entitles him.
My reasons are substantially those expressed in Judge
Breitenstein’s opinion for the Court of Appeals. 317 F.
2d 796, 804-807.