Majority — WAYNE J.
Syllabus
Where there was a special contract to build a house by a certain day, which was not fulfilled, owing to various circumstances, and the.contractor brought a suit setting forth the special contract and averring performance, it was erroneous in the court to instruct the jury to find for the plaintiff, as the work was not finished by the appointed day, though it was completed after the time with the. knowledge and approbation of the defendant.delivered the opinion of the court.
This record shows that the-plaintiff and the defendant entered into a building contract, under • seal, with specifications annexed, on the 22d'April, 1851. It was agreed between them, that Jones, the plaintiff, should do in a good, substantial, and workmanlike manner, the houses, buildings, and work of every sort and kind' described in a schedule annexed to the contract, of which ic was apart; that he should procure and supply all the materials, implements, and fixtures, requisite for executing the work in all its parts and details; and that the stores fronting on Market Space, .and the warehouse on Seventh street, should be finished and ready for use and occupation, and be delivered over to the defendant, on the first day of October after the date of the contract, and all .the rest of the work on the first day of December afterward. The defendant agreed, upon her part, to pay the plaintiff for the performance of the work, and for the materials furnished, twenty-four thousand dollars by instalments:. five thousand dollars on the first day of July, 1851; five thousand dollars on the first day of Oetobér following; it being expressed in their contract, that the stores and warehouse were then to be delivered to t,<,e defendant ready for use and occupation; -and that the residue of the twenty-four thousand dollars was to be paid to the plaintiff on the first day of January, 1860, with interest upon four thousand of it from the first day of May, 1851, and with interest on ten thousand dollars from the first day of December, 1851. We do not deem it necessary to -notice the other covenants of the contract, as they have no bearing upon the ease as we shall treat it.
The defendant filed three pleas to the first count of the amended declaration: 1st, that she was not indebted as was alleged; 2d, that the plaintiff had not performed the special agreement; and 3d, that he had not performed the condition precedent of the contract, to complete the building, which he had agreed to do by the first day of October, 1851. . To the rest of the count the defendant demurred. Ás the verdict of the jury and the judgment réndered for-the plaintiff are upon the first amended count, contrary to instructions asked of the court by the defendant, we shall not notice the subsequent pleadings and proceedings in the ease, and will confine ourselves to what we consider to have been the legal rights ofithe parties under the original declaration and the first amended count. The evidence shows that the three stores and the warehouse were not finished,.'hy the 1st of October, 1851. It is also proved' that
Also, if the defendant did not, at any time whatever, execute and finish, ready for use and occupation, and deliver in that state and condition to the defendant, the stores and warehouse, but had delivered them over to the defendant in a state wholly unsafe and unfit for use, and untenantable, &e., ho., and that the defendant had been obliged, to reconstruct the walls, and to refix the buildings, so as to fit them, for use and occupation, at her own cost and charges, then that the defendant may recoup or deduct the same against the plaintiff’s claim for the said instalment of five thousand dollars claimed in the suit, or the value of the work done by the plaintiff upon the stores and warehouse; but that, in all events, the plaintiff' could only recover nominal damages.
These instructions the court refused to give, without the-following qualifications :
“ If the jury shall find from the. evidence that the plaintiff, Jones, has executed the work according to the specifications forming a .part of the contract, in a skilful, diligent, and careful and workmanlike manner, and that his performance of- it was with the knowledge and approbation of the defendant, then they should find for the plaintiff the said sum of five thousand dollars, with interest from the date of the delivery of the stores and warehouse to the defendant.”
The defendant excepted to the refusal of the instructions as they had been prayed for, and to the qualifications of them as they were given to the jury..
There is error in this instruction. The count and the plea of the defendant, and the instruction asked, raised the construction of the special contract, whether or not the right of the plaintiff to recover the second instalment did. not depend upon the completion of the stores and warehouse by the 1st of October, 1851; whether that was not a condition precedent, or a case , in which the parties had agreed — one to deliver the buildings finished, according to the special
The plaintiff' undertook to furnish the materials and to construct the buildings, according to specifications. Part of them were to be finished, and to be delivered to the defendant, on the 1st of October, 1851, and the residue on the 1st December afterwards. For the whole, the defendant was to pay $24,000 — ■ $5,000 on the 1st of July, 1851; $5,000 on the 1st of October, 1851, if the stores and warehouse were then finished for use and occupation, and delivered over on that day to the defendant ; and if that was done, then the balance of the $24,000 was to be paid on the 1st of January, 1860, with the interest, as mentioned in the special contract.
The words of the contract for payment are, “ in consideration of the covenants, and their due performance.” Such words import a condition. It is difficult at all times to distinguish whether contracts are dependent or independent; but there are rules collected from judicial decisions, by which it may be determined. We have tested the correctness of them by an examination of several authorities. '
“ When the agreements go to the whole of the consideration on both sides, the promises are dependent, and one of them is a condition precedent to the other.” Such is the case with-the special contract with which we are now dealing. ‘‘If the agreements go to a part only of the consideration on both sides, the promises are so far independent. If money is to be paid on a day certain, in consideration of a thing to be performed at an earlier day, the performance of that thing is a condition precedent to the payment; and if money is io be paid by instalments, some before a thing shall be done and some when it is
The first instalment was to be paid on an appointed day, in consideration of the work to be begun; and the second instalment was to be paid on a subsequent day, if the work should then be finished and delivered over to the defendant, ready and fit for us.e and occupation. Before that day it could not have been demanded; on that day, the work having been performed, it might have been. The evidence shows that the work had not been done on the 1st of October, 1851, and was not finished until the 1st of December.
The plaintiff' avers in his first amended count that he had, >n his part, complied with his undertaking in the special contract. The issue upon it is, that he had not done so, and he gave no proof to sustain the averment.
The evidence entitled the defendant to a verdict on that count; but the court, without regard to the time fixed upon for the work to be finished, instructed the jury, that if the work had been done according to the specifications forming a part of the contract, in a . skilful and workmanlike manner, or if his execution of it was with the knowledge and approbation of the defendant, then they were to find for the plaintiff the sum of five thousand dollars, with interest from the date of the delivery of the stores and warehouse. It must be obvious that this instruction makes between the parties a different contract from that into which they had entered, and one different from that the plaintiff had declared upon.
We do not consider that the plaintiff’s right to recover upon that declaration was in any way affected by the extra work which was done upon the requisition of the defendant, or by the increase of materials which he furnished for that purpose; or that the sinking of the foundation of the buildings excused him from finishing the work by the time specified; or that the acceptance of the buildings by the defendant as they had been constructed by the plaintiff was any release of the plaintiff from his undertaking to finish them in the time specified in the contract. But after that time had passed, the plaintiff continued, with the knowledge and permission of the defendant, and also with the knowledge of her superintending architect, to do the work specified in the contract, and also to do the extra work, and -to furnish the materials necessary for both. And when the work was done by the plaintiff, however imperfectly that may have been, the defendant accepted it.
The law in such a ease implies, that the work done and the materials furnished were to be paid for. The general rule of law is, that while a special contract remains open — that is, unperformed — the party whose part of it has not been done cannot sue in indebitatus assumpsit to recover a compensation for what he has done, until the whole shall be completed. This principle is affirmed and acted upon in Cutter v. Powell, 6 Term Reports, 320; also in Hulle o. Heightman, 2 East., 245, and in several other cases.
But the exception's from that rule are in cases in which something has been done under a special contract, but not in strict accordance with that contract. In such a case, the party cannot recover the remuneration stipulated for in the contract, because he has not done that which -was to-be the consideration of it. Still, if the other,party has derived any benefit from the-labor done, it would be unjust to allow him to retain
Such is the law now in England and in the United States, notwithstanding many cases are to be found in the reports of both countries at variance with it. It was recognised by this court to be the existing rule in the case of Slater v. Emerson, 19 Howard, 224 , 239.
The difference between the rule now and in earlier times, it is" believed, has caused much of the difficulty in the establishment of the present. rule. Formerly it was held, that whenever anything was done under a special contract not in conformity with it, the party for whom it was done was obliged to pay the stipulated price; but that he might resort to a cross-action, to izidemnify hiznself for the deficiency izz the consideration. Blair v. Davis, 1794, cited in 7 East., 470. See Smith’s L. Cases, in the notes following the case of Cutter and Powell, 2d voh, for a full description, historical and chronological, of the rule as it now prevails and as it formerly was.
The rule as it now exists has been recently dismissed and affirmed in the Queen’s Beneh, in the case of Munroe v. Phelps and Bell, 8 Ellis and Blackburn, 739; 92 English Common Law.
It has been the rule in the courts of New York for more than thirty years. In the ease of Jewell et al. v. Schroepnell, 4 Cowan, 564, it was decided, that if there be a special contract under seal to do work, and it be not done pursuant to the agreement, whether in-point of time or izz other z-espeets, the party who did the work may recover, upon the common counts in assuznpsit, for wozk and labor dozze. If, whezz the time arrives for performance, the party goes on to conzplete the woz’k, with the knowledge of his employer, it was evidence of a promise to pay for the work. So if the employer does not object.
This rule prevails, also, in Massachusetts, in Pennsylvania, and in several of the other States. Also in Alabama, as may
In the trial of such an action, where the defence is not presented as a matter of set-off, arising on an independent contract, but for the purpose of reducing the plaintiff’s damages, because he had not complied with his cross obligations arising on the same contract, the defendant may be allowed a recoupment from.the damages claimed by the plaintiff for such loss as she shall have sustained' from the negligence of the plaintiff". Such evidence is allowed to prevent circuity of action, and to prevent further litigation upon the same matter. It may be well to say, that the court allowed a recoupment in Green and Biddle, 8 Wheat., 1 , to a disseizor, who was a bona fide occupant of land, for the improvement made by him upon it, against the plaintiff’s damages. But such recoupment cannot be claimed unless the. defendant shall file a definite statement of his claims, with notice of it to the plain till’ sufficiently in time before the trial term of the case to enable the latter to meet the matter with proof on his side.
We have pursued the case In hand further than may have been necessary; but it was thought best to do so, as the points now here ruled have not before been expressly under the consideration of this court.
The judgment given in the court below is reversed; and we shall order that the case shall be remanded to it, with directions for its trial again, pursuant to our rulings in this opinion.