Majority
Headnote
Judgment of the supreme court in this case as reported in 12 Wendell, 344, affirmed. The Chancellor, in the prevailing opinion delivered by him, places the affirmance upon the ground, that by a previous decision of the supreme court, acquiesced in by the defendants below,the original contract entered into by these parties must be considered as rescinded, and that therefore the plaintiff below is not limited in his claims to the compensation specified in the contract, but entitled to recover for the work done by him under a quantum meruit. It seems, that but for considering the contract rescinded, the Chancellor would have held that the plaintiff was not entitled to recover for hard pan, a price greater than that fixed by the contract for excavation generally, and that the estimate of the engineer, as to the amount the plaintiff was entitled to recover would have been conclusive.The following opinions were delivered
This case comes before us upon a writ of error to the supreme court, to review its decision upon a report of referees, incorporated in the record in the form of a case or special report. It appears from this record of the judgment of the supreme court, that the parties went down to trial at the circuit, where a stipulation was entered into by
The substance of that decision, so far as I can understand it from the reported decisions of Mr. Justice Marcy, 4 Wendell, 288, is, that the special agreement under which Dubois commenced his work upon the canal, was rescinded by the acts, or rather by the omission of the agents of the canal company, so as to authorize the plaintiff to recover compensation for his services under the common counts, upon a quantum meruit; but that in ascertaining the amount which the plaintiff was justly entitled to for his services, the prices fixed upon by the ' parties themselves, in the rescinded contract, ought to be resorted to, and should conclude the parties, so far as the work had been done in the manner and within the time specified in the contract, and as contemplated by the parties at the time of entering into such special agreement. And where the work was different from that originally contemplated by the parties, or was done at a later period and under circumstances more unfavorable to the plaintiff than was thus contemplated, he was entitled to recover an extra allowance therefor ; in other words, that the terms of the contract were not binding upon the plaintiff, except so far that the prices fixed upon the labor by the parties themselves, were to be considered as the real value of those parts of the work which were done at the time and in the manner originally contemplated by the parties.
It is insisted however, by the counsel for the canal company, that by the written contract between the parties, the engineer was to determine the value of all extra work, and that his decision therefore, as to the value of the hard pan excavation, was conclusive upon the plaintiff. The terms of the contract, as to the powers of the engineer not only to estimate the number of yards of excavation and of embankment, and the value of extra work caused by an alteration of the line of
The conclusion at which I have arrived in this cause is, that the judgment of the supreme court is not erroneous, and that it should be affirmed.
In this cáse questions of law and facj- are so mingled, that it is not easy to get at distinct legal propositions, such as alone are fit for examination and decision by this court. In tracing the whole course of this controTerg^ frotn jtg commencement to the last judgment of the supreme court, one will scarcely fail of being satisfied that the plaintiffs in error have cause to complain that they have not been protected in their legal rights, and yet there is some difficulty in fixing on the precise point at which they have been manifestly violated.
On examining the original agreement between the parties, I cannot doubt that it was the peculiar design of the company, and the expressed understanding of the contractor Dubois, that every question of controversy which could grow out of the contract, should be definitely settled by the engineer to be appointed by the company to' superintend and inspect the work. There was a prospective submission,, which it is competent and not uncommon for parties to make; and though in this case the arbiter was not named, there was such a description of him as rendered the submission as practicable and effectual as if he had been designated by name. It is scarcely necessary to refer to authorities to sustain a position so in accordance with common sense and convenience, as that parties may, as to all such matters, make the law for their own contract; and that an award in pursuance of such a form of submission is conclusive, although made without the subsequent intervention of the parties, or either of them. The case of the United States v. Robinson, 9 Peters, 327, is full to this point.
The supreme court, however, construes this provision of the contract in a more limited sense, confining the submission to questions of extra work arising from alterations of the line of the canal, and to computations of the quantity of the work for which specific prices is provided. This construction is placed on the ground that “ the enumeration of one species of extra work is an exclusion of all others.” Assuming, as for this, purpose I shall, that the hard pan excavation was extra work, it appears to me that this is not the legal interpretation of the instrument. Its provision is, that the engineer “ shall esti
But it is claimed that a previous decision of the supreme court in this same suit, 4 Wendell, 285, acquiesced in by the parties, established new rights between them in respect to the present subject of controversy, so that if the plaintiff below would have been bound by the decision of the engineer as to the amount and value of this hard pan excavation, that decision has provided for him a different and more liberal rule for his compensation. It is unnecessary to examine how far an interlocutory decision can have such an effect; for the one in question, as far as I can understand it, does not establish any
It thus is evident that the supreme court did not propose to establish a new rule of compensation in regard to any portion of the work, but merely to provide for the party a mode of obtaining an indemnity for the additional expense he had been put to, by the defendants’ delay to authorize him to complete the canal across the highway. Beyond this they must have contemplated that his compensation should be regulated by the terms of the contract. The case, as it came then before the court, did not warrant or receive as broad a decision as was afterwards made in Koon v. Greenman, 7 Wendell, 123 ; for there was nothing to show that the plaintiff had, as in that
The supreme court, in its opinion under review, assumes that “ the contract makes no specific provision for hard pan excavation.” This remark is correct, if by it there is only meant that hard pan excavation is not specifically enumerated in the contract, in contradistinction to excavation generally ; and, in this view, it would be equally correct to say that the contract makes no specific provision for sand excavation, gravel excavation, or clay excavation. But if the supreme court means, as the conclusion drawn from the proposition seems to indicate, that hard pan excavation was a description of work which Dubois by the contract was not bound to perform, then the proposition is entirely erroneous. The obligátion assumed is in these words: “ The said Isaac Dubois doth covenant and agree to construct, in a good, substantial and workmanlike manner,[all that part of the Delaware and Hudson canal which is included in section twelve of the line of the canal,” &c.; and afterwards it was specified of what dimensions, form and finish this part of the canal should be constructed, and then follows the covenant on the part of the company for compensation, which was “ at the rate of nine cents per cubic yard for excavation, and forty cents per cubic yard for rock in ledge, or fragments measuring one cubic yard, and thirty cents per cubic yard for slope wall, and eleven cents per cubic yard for embankment,” &c. By the terms of the contract, then, it is as plain as words can make it, that Du
Viewing, then, this extra allowance for hard pan in the favorable light to the contractor, of an authorized modification of the contract by the engineer, it can by no construction be carried further than the engineer agreed to carry it—that is,
I differ also from the supreme court on the other point— that the bill of particulars furnished by the plaintiff did not limit his right of recovery for the hard pan excavation, to a less amount than was awarded by the referees. Though a bill of particulars need not be as special in its form as a count upon a special contract, yet as the object of it is to give the adverse party a further knowledge of the claims made against him, than can be obtained from the pleading, it.is just and proper, when it is furnished, that the party should be bound by it. The charge for hard pan excavation was thus stated in the bill:
To 12,000 yards of hard pan excavation, $3600
To other hard pan, 3600
On one side it is insisted that the above specification is equivalent to a charge of thirty cents per yard for the hard pan ; while the other insists that it amounts only, to a charge of $7200 for an undefined quantity, and that so long as the recovery for hard pan did not exceed the whole sum charged
Upon the question being put, Shall this judgment be reversed ? the members of the court voted as follows :—
In the affirmative—Senators Beardsley, Jones, MacDonalld, M’Dowell, Tracy—5.
In the negative—The President of the Senate, the Chancellor, and Senators Armstrong, Beckwith, Cropsey, Downing, Edwards, Fisk, Gansevoort, Griffin, Halsey, Lacey, Lansing, Loomis, Maison, Willes—16.
Whereupon the judgment of the supreme court was affirmed.