    InSubject thisto subsection (4), no company shall construct a pipeline that passes on, over, along or under a utility unless a certificate has been issued, or an order has been made under section and58, sectionsin 110respect of the pipeline, and 111,
    Full text

    Subject to subsection (4), no company shall construct a pipeline that passes on, over, along or under a utility unless a certificate has been issued, or an order has been made under section 58, in respect of the pipeline, and

  2. 2002-12-31 to present View Source

    In this section and sections 110 and 111,