← Historical versions

Versions of s. 108(2)

N-7 — National Energy Board Act · 2 versions

Historical text comes from the Justice Laws point-in-time corpus and is unofficial — not the official version.

  1. 2013-07-03 to present available View Source
    The pipelineBoard ofmay, by order, on application, grant a company may, if leave isto firstconstruct obtaineda from the appropriate authority, be carried across any utility and forpipeline that purpose may be constructedpasses on, over, along or under a utility. It may require from the applicant any suchplans, utility.profiles and other information that it considers necessary to deal with the application.
    Full text

    The Board may, by order, on application, grant a company leave to construct a pipeline that passes on, over, along or under a utility. It may require from the applicant any plans, profiles and other information that it considers necessary to deal with the application.

  2. 2002-12-31 to present View Source

    The pipeline of a company may, if leave is first obtained from the appropriate authority, be carried across any utility and for that purpose may be constructed on, along or under any such utility.