← Historical versions

Versions of s. 6(2.4)(b)

N-7 — National Energy Board Act · 2 versions

Historical text comes from the Justice Laws point-in-time corpus and is unofficial — not the official version.

  1. 2016-06-19 to present available View Source
    the Board is bound by every decision made by the Board in relation to the application before the taking of the measure unless the Board elects to review, vary or rescind it.
    Full text

    the Board is bound by every decision made by the Board in relation to the application before the taking of the measure unless the Board elects to review, vary or rescind it.

  2. 2012-07-06 to present View Source

    the Board is bound by every decision made by the Board in relation to the application before the taking of the measure unless the Board elects to review, vary or rescind it.