Majority
Headnote
A non-performance of a condition in the charter of a turnpike company, in respect to the mode of constructing and maintaining the road, is in itself a. misuser that will forfeit the franchise of the corporation.[After stating the facts.] — Assuming the facts found by the jury to be legally ascertained, it follows from them that the judge at the circuit properly directed a verdict for the plaintiffs. When the facts are undisputed or .settled, then the proper verdict is purely a question of law, and the direction of the court, if in accordance with the law on the facts assumed, is not the subject of.exception.
Section 32 of the general act, under which the defendants were incorporated, directs how the road to be made by a company incorporated under it, to make a turnpike road, shall be constructed
The first and second questions submitted to the jury are in the identical language of section 32 of the act, which contains the directions for the manner in which the road shall be constructed, omitting the requirement that the road shall be at
The court properly submitted to the jury the question whether or not the defendants had constructed their road in compliance with the requirements of the statute. It was no error in the judge to read from the statute, to enlighten the jury as to their requirements, and no question was made, that there had been a substantial compliance therewith. If the defendants had desired to bring that question up for consideration, they should have requested the judge to charge the jury that a substantial compliance with the requirements of the act was all the law required of them, and- that if the jury found there was a substantial compliance, then they were to find that the road had been constructed in the manner called for by the statute. If such requests had been made and refused, it is clear, upon the authorities cited, such refusal would have been error. The jury having found that the road had not been constructed in the manner required by the statute, it follows clearly that the plaintiffs were entitled to a verdict in their favor, and it also follows that the judgment was correct; unless there was some error committed in the admission or rejection of evidence, or in the charge made to the jury; or unless the inspectors’’ certificates which were set up as proving that the defendants had made and completed their road, according to the true intent and meaning of the statute, are conclusive evidence that it was so made and completed. These positions will be considered m the order above stated.
First. It is now urged that the admission of the two judgment rolls against the Whitehall and Waterford Turnpike Company were erroneously admitted. It is not seen how the fact of the recovery of these judgments, and that they remained unsatisfied and unpaid, was at all material or pertinent to any inquiry involved in the trial of this action. The history or proceedings of that company had no legitimate or
Second. It is not perceived that any error was committed in the charge. The questions submitted were in the discretion of the court, and seem to be proper and legitimate, to the proper issues to be determined. The facts covered by the questions propounded to the jury, were'vital to the plaintiff’s right to recover, and were distinctly embraced within the pleadings. The first request to charge was clearly immaterial and improper, and the court properly directed the attention of the jury to the language of the statute as to the mode and manner of the construction of the road. The requirements of the statute, in these particulars, was vital to the inquiry whether the defendants had complied with them; and the second request to the court, to instruct the jury that the statute does not require the road to be maintained with a hard and even surface during the whole year, regardless of rains and bad weather in the spring, was clearly unwarranted. The statute does not make any such exception, and there is nothing in it to warrant any such discrimination. The court would have been justified in a refusal to make it. But it is beyond all controversy that the defendants were inexcusable for a noncompliance with the requirements of the act in the construction of their road, and the question was properly one of fact, to be determined by the jury, whether the defendants had kept their road in repair, according to the spirit and intent of the statute. This was placing this inquiry before the jury in a most favorable aspect for the defendants, and excludes the idea that the court instructed or intimated to the jury, that a literal compliance with the terms of the statute was to be
The further charge, that the fair construction of the language of section 32 of the statute, “ or such other material as may be found on the line thereof,” meant such other hard or durable material as stone or gravel, and could not be supposed to be satisfied with a poorer material than the natural roadbed, would seem to be an obvious inference front the language of the statute. It certainly contemplates that the bed of the road is to be made of stone, gravel, or some such other material as may be found on the line thereof, and the face thereof was to be made of stone or gravel, so as to form a hard and even surface. The exception goes to hoth branches of the proposition stated, that this language meant such other hard or durable material as stone or gravel, and could not be supposed to be satisfied with a poorer material than 'the natural roadbed. Whatever doubt there may bo as to thé correctness of the first proposition, there can be none as to that of the las^ namely, that the statute would not be satisfied with a poorer material than the natural road-bed. The legislature evidently contemplated that the bed of the road was id be made of stone or gravel, or such other material of á like nature as might be found on the line of the road. This clearly contemplated that something was to be added to the natural condition of the road-bed better than it, and therefore the court properly told the jury that this provision was not satisfied by the addition of something poorer than the natural road-béd.
The other part of the charge excepted to was proper. If the defendants had neglected to bed and construct iheir road, at any part of it, substantially as required by Lhb ‘statute, this
There can be no doubt that the word “ arch,” as used in the statute, required that the center of the bed of the road should be rounded up or be highest at the center, and the court was clearly right in so charging. It is difficult to see how the arch of the road could be made or constructed without the center being higher than the sides. The arch must necessarily form a segment of a circle, and the central point of the arch must be the highest point in the segment of a straight line drawn from the two extn-mes of the segment. It is an impossibility that the road-bed could properly be an arch without its central point being the highest, assuming, as we must, from the language used, that the legislature intended what they said, that the arch of the road should be eighteen feet wide. It is apparent from this language, that they did not intend that the bed of the road should be level or concave. In the former event, we know that the water falling in it, must necessarily remain there, until wasted by evaporation or by sinking into the ground; in the latter, it must settle or run down to the center of the road, there to remain until dispelled in one or the other of the modes suggested. This certainly was not the intent of the legislature. They proposed that the bed of the road should be arched so that it might easily shed water, and thus, as far as possible, remain dry and in good condition for traveling. I see nothing, therefore, objectionable in the charge.
The proper judgment has been rendered upon the facts found by the jury, and the judgment should be affirmed, with costs.
The objections and the exceptions taken at the trial were very numerous, but the following only have been discussed.
1. The road of the defendants runs over the bed of a turnpike, formerly belonging to an incorporated company called the President and Directors of the Waterford & Whitehall Turnpike. Evidence was admitted, against the objection and exception of the defendants, showing that this old corporation was insolvent, had not repaired the road, taken toll, or done any business for twelve or fifteen years; that the directors were all dead hut three, and that there was ah entire abandonment of the road and a dissolution of that company.
2. The defendants’ counsel objected to the admission of evidence showing the condition of the road from the time that the defendants began to take toll from passengers down to the commencement of the action, and, his objections being overruled, he excepted.
The evidence was clearly within the issue. The complaint states the duty of the defendants to construct and keep in good repair the said road, twenty-two feet wide, bedded with stone, gravel, sound wood, or other hard substance, well compacted, and of sufficient depth to secure a solid foundation, and to face it with gravel or broken stone, not less than nine inches in depth, in such a manner as to sucure a firm and even surface, rising in the middle by a gradual arch, with ditches on each side; and that the defendants were bound to erect and maintain good and sufficient bridges over all the streams which were passed by the road, and to keep the bridges and the road in good condition, and the surface of the road smooth and even, as pounded or broken stones, slate, gravel or other hard material would admit. It is then averred that the defendants never constructed the road or bridges as required as aforesaid; that they have not for the last ten years kept and maintained the road in the condition required by law, but have willfully neglected to make, mend and repair the road, and have allowed it to remain out of repair, unsafe and dangerous to pass with loaded teams, and have willfully neglected to keep the surface
It is entirely clear that this issue called for the very evidence which was admitted under the inquiry objected to.
The averment of greater width than the act required was immaterial. The evidence ivas still admissible, although a forfeiture could not he adjudged for the want of sufficient width, if found to be as wide as the statute called for.
It was also urged that the complaint was not specific, and that the certificates of the inspectors of turnpike-roads, of the completion of the road in conformity with, the law, was conclusive upon the plaintiffs as to the construction. The evidence covered only the facts specified in the averment of breaches in the complaint. The complaint is specific as to the duty of the defendants, and also in respect to their willful neglect, in certain specified particulars, to comply with the law which prescribed the defendants’ duty.
The certificates had not been introduced when the plaintiffs’ evidence was given in respect to the construction; hut if it had been, the evidence was still admissible. The certificates were presumptive evidence only for the defendants of the proper construction of the road to entitle them to begin to receive tolls. Nor was any avermént required in the complaint in respect to the falsity of the certificates. If they were false it could not be anticipated by the plaintiffs, that the defendants, who knew better than anybody else how the fact was, would offer them as evidence. It would have been a mere pleading of evidence to have referred to the certificates in the complain t, and to have there alleged their falsity. The certificates had nothing to do with the issue to he framed by the pleadings.
3. The interrogatories finally submitted to the jury do not embrace anything respecting the sufficiency of the bridges, nor as to their width. The inquiries relate to the road only. The jury could not, therefore, have found against the defendants, on
4. The judge was requested to charge that the defendants were not required to use extraordinary and enormous expenses m constructing the road. The judge declined so to do, but read the provision of the statute directing how the road should be constructed, and charged that the defendants were bound to comply with the statute. The defendants excepted to the refusal, and also to the direction given.
The request was too broad. No evidence had been offered to show what would be ordinary or common expense, or that the road could not be constructed within such limits; nor that any extraordinary or enormous expenses would be incurred m conforming to the requisition of the statute which was read to the jury. There was no error in directing the jury that.the statute must be complied with.
Every argument for supposing that the jury could be unfavorably influenced by these remarks of the judge, was removed by the next paragraph ot the charge, as shown by the case. They were there instructed that the defendants were not required to maintain the road with a hard and even surface, regardless of rains and bad weather in the spring; and the jury were then directed that the defendants must comply with the statute in building the road, and that they must decide from the evidence whether the road had been kept in repair according to the spirit and intent of the statute.
5. There is no request or exception on the subject of the neglect of the defendants being willful or malicious. The evidence renders it apparent that the defendants knew the condition of their road. It cannot be supposed that the road could have been so out of repair as to be nearly impassable by teams, m the spring and fall, in many places, for several years, without the defendants being chargeable with such knowledge as must constitute willful and malicious negligence. Negligence wilh knowledge is intentional, and includes the willful and malicious omissions oí duty mentioned in the statute. L. 1854, p. 1G7, c. 87.
6. It is said that the court submitted to the jury the construction of the statute m relation to the manner of bedding P the road.
The judge said, as it appears from a paragraph of the case, that “ if the jury came to the conclusion that the statute requires that thé bedding of the road must be- made otherwise than by merely drawing gravel on the top, then they will find that the road was not properly bedded.”
In that connection he proceeds to instruct the jury further in respect to the bedding, that the fair construction of the statute meant such other hard or durable material as stone or gravel, and could not be supposed to be satisfied with a softer or poorer material. 2 S. S. 5 ed. pp. 481, 499. The defendant's- excepted to each paragraph separately; but-the latter direction modifies and explains the former, and.left the jury no opportunity for exercising their own discretion as to -the interpretation of the statute.
If, however, the judge left the construction of the statute to the jury, it was the more favorable for the defendants, inasmuch as the proper interpretation.required, the-judge to, inform the jury that the statute required a bedding of some hard or durable material, and could not be satisfied by putting a facing over the natural soil, or a bedding of clay, as was done in many places. The defendants might have had a more favorable construction from the jury than the court could give them... But I think no such subject was left to them..
7. The defendants, however, insist that the statute permits the use of the ordinary soil for bedding the road. 2 B. S. 5 ed. p. 499, § 98.
It is provided by the statute that the-road “ shall be bedded with stone, gravel or such other material as may by found on the line thereof.” It is in evidence that there was stone and gravel in great abundance within a short distance of the worst and most impassable parts of the road. ■ There was no occasion to inquire what “ other material,” which might be foiind on the line of the road, was referred to by the statute. There was an abundance of stone and gravel along the line of this road, but the natural soil, without any bedding, was proven to- be its condition in several places. If there had been no stone or
The defendants also object because the court directed the jury to render a general verdict; for the plaintiffs, after having found specially in answer to certain interrogatories propounded under the direction of the court.
A general verdict appears not to be necessary or required by the Code of Procedure (§§ 260, 261). The court may in all cases instruct the jury, if they render a general verdict, to find upon particular questions of fact in writing (§ 261). Where the special finding of facts shall be inconsistent with the general verdict, the former shall control the latter, and the court shall give judgment accordingly (§ 262).
The court can now treat the case as if no general verdict had been rendered. The general verdict, being immaterial, may be disregarded. The judgment was to be rendered by the court, as the law applicable to the facts, as found, required. Such would be the result, under the foregoing provisions of the Code, which way soever the general verdict had been rendered by the jury. United States Trust Co. v. Harris, 2 Bosw. 75 . The facts found established a forfeiture from which the defendants can be relieved only by the legislature. Without regard to the
These were all the questions discussed on this appeal, and I now reach the conclusion that the' judgment below should be ■affirmed, with costs.
All the judges concurred, except Porter, J., who did not vote.
Judgment affirmed, with costs,
Cases cited
- Forrest v. Forrest 25 N. Y. 501 at 511 p. 583, p. 584, p. 587
- Wadsworth v. Allcott 6 N. Y. 64 p. 584
- People v. Fishkill & Beekman Plank Road Co. 27 Barb. 445 p. 584, p. 585
- Huntington v. Conkey 33 Barb. 218 at 227 p. 584, p. 587, p. 591
- People ex rel. Bishop v. Kingston & Middletown Turnpike Road Co. 23 Wend. 193 p. 584, p. 585
- City Bank of Brooklyn v. Dearborn 20 N. Y. 244 at 246 p. 587
- Worrall v. Parmelee 1 N. Y. 519 p. 591
- United States Trust Co. v. Harris 2 Bosw. 75 p. 595