Majority
Headnote
Municipal corporations — sewer assessment — when property owner cannot contest validity of assessment on ground that contracts require compliance with Eight-Hour Labor Law — failure of owner to show damage. .The defendant, acting under the provisions of its charter (Laws of 1895, chap. 635, tit. 7, as amd.), has constructed certain sewers in the streets, highways and public places of the city of Yonkers, and has levied assessments upon the property supposed to he benefited by such'improvements. The plaintiff has property adjacent to some of these sewers, which were evidently constructed to- con
The principal objection urged to the assessments as a whole is the fact that the various contracts under which the three separate sewers were constructed contain provisions by which the contractors agree to abide by the provisions of chapter 567 of the Laws of 1899 (amdg. Labor Law [Laws of 1897, chap. 415], § 3[1] ), which provides for the employment of laborers for .only eight hours per day. and the payment of not less than the prevailing rate of wages in the locality. It is conceded that these provisions of the statute are unconstitutional and of no force and effect, and it is the contention of the plaintiff, supported by the judgment, that the presence of this provision in the various contracts has had the effect of increasing the cost of these sewers, and thus to take the property of the plaintiff, without due process of law, by compelling him to pay more than the legitimate cost of the public improvement. It is not to be doubted that a municipal corporation, acting as, the agent of the owners of property benefited by a public improvement, is restricted in its agency to the- terms of the statute vunder which the work is undertaken, and that there is an implied limitation that the abutting or benefited property shall not be called upon to pay more than the legitimate cost of such public improvement within reasonable bounds, but where the plaintiff has stood by and watched the improvement being made, without raising any objections, he is bound, in' appealing to a court of equity, to establish affirmatively the fact that he has been wronged by the assessment as a condition of relief. The evidence in this case, it seems to us, fails to meet this equitable requirement.' It is true that there was some testimony by witnesses called as experts to the effect that a contract per-, formed under the letter of these various agreements would increase the labor cost fifteen to twenty-five per cent, but there is no evidence that the contracts were performed under such limitations, and the presumption is that the contractors knew the law and that they
* This statute was also amended by chapter 298 of the Laws of 1900.— [Rep.
It is also urged by the plaintiff, and supported by the judgment, that the assessment resulting from the North Broadway sewer proceeding and from the Robert avenue and Palisade avenue proceeding are void because the plaintiff’s land is not benefited thereby, several sewers having been in each instance united in one proceeding and the property benefited by one of such sewers being in no sense benefited by the other. It appears from the evidence in this case that the sewers, constructed in Robert avenue and Palisade avenue were done under one proceeding.- The sewer is in the form of a “ T,” the stem of the “ T ” being in Palisade avenue, while the top of the “ T ” extends east and west along Robert avenue. The plaintiff’s property lies north of Robert avenue on the slope of the southerly hill forming the valley where the north and south branches of the sewer connect with the Palisade avenue stem. The work was all embraced in a single contract; there is no evidence of any fraud or bad faith on the part of the common council in fixing the assessment district, and the assessors in apportioning the cost of the improvement according to the benefits to the property within the assessment district procured the. contractor to furnish an itemized estimate of the cost of constructing the portion of the sewer which passed near the plaintiff’s premises, and the assessment of benefits appears to have been made, not upon the cost of the entire “ T ” sewer, but upon that portion which may be presumed to be of benefit to the plaintiff’s premises. This was likewise true of another of the sewers in a general way, and we are of opinion that it does
The suggestion that the defendant had failed to accept certain conveyances of rights of way, or that there was defect in the proceedings vitiating the assessment because of the fact that at the time of the commencement of this action the defendant had a mere. license to construct the sewer under the tracks of the New York Central and Hudson Biver railroad, is hardly worthy of serious consideration. It is always presumed that a beneficial grant is accepted, and the fact that the defendant procured these grants and then constructed the sewer through the premises described in such grants is conclusive that the right vested in the defendant. In the matter of crossing the railroad it appears that the matter has since been entirely cleared up by a grant from the railroad company, and there is no ground for equitable relief in this technical defect.
We have examined all of the matters urged by the plaintiff, but we are unable to agree- with the conclusion reached by the learned court at Special Term. The proceedings of a jurisdictional character appear to have been complied with in a manner which is not open to criticism, and the details appear to have been worked out with mor,e than usual regard for the rights of those who are to pay for the improvement. Mere formal defects, in nowise working an injury to one who has stood by and seen a public improvement constructed, are not proper grounds for setting aside an assessment, which must result in throwing the burden either upon the contractor or upon the community at large, and we are of opinion that the
Concurrence
The judgment appealed from should be reversed, with costs to abide the final award of costs.'
Miller, J., dissented on the ground that the finding that the illegal provisions of the estimates and contracts increased the cost of the work is abundantly supported by the evidence. The successful bidder admitted that it entered into his estimates.
Judgment reversed and new trial granted, costs to abide the final award of costs.
Cases cited
- People ex rel. North v. Featherstonhaugh 172 N. Y. 112 at 126 p. 310
- Knowles v. City of New York 176 N. Y. 430 at 440 p. 311
- Gilmore v. City of Utica 131 N. Y. 26 at 34 p. 312