Judgment, Supreme Court, New York County (Robert F. Doran, J.), entered March 5, 1993, which, after inquest, awarded plaintiff $606,964.45 plus interest at the rate of 1.2% per month from August 11, 1992 and costs, for a sum total of $657,173.20, unanimously reversed, on the law and the facts, without costs or disbursements, and the matter remanded for a recalculation of damages in accordance herewith. Appeals from the orders of the same court and Justice, entered March 3, 1993 and the same court (Edward J. Greenfield, J.), entered May 11, 1993, dismissed as subsumed in the appeal from the judgment.
Plaintiff, a contractor, sues to recover monies allegedly due under a construction contract calling for the construction of 48 luxury homes in Southampton and East Hampton. Construction commenced in July of 1988. Initially, plaintiffs invoices were paid in full. Notwithstanding the failure of defendants, the owners, in or about March 1989 to make timely payments, as required under the contract, plaintiff continued to perform after being advised that payment was forthcoming. Plaintiff ceased any further construction and
Defendants also argue that plaintiff is not entitled to compound interest at the rate of 1 Vi% monthly as reflected in their monthly invoices. As defendants aptly note, the contract does not specifically provide for compound interest. Article 14 provides that interest on payments due and unpaid "shall be at the rate charged to the [contractor by the lending institution [contractor is borrowing from.” Defendants argue that since there was no evidence offered that plaintiff was borrowing to enable it to perform under this contract, its request for compound interest at the rate of 1M>% per month should have been rejected. Defendants also argue that article 14 should not be construed to allow compound interest since the contract was executed almost one year before the enactment of General Obligations Law § 5-527, effective June 1989, which per
Plaintiff’s cross appeal seeking lost profits is without merit. The IAS Court found that plaintiff terminated the contract when defendants ceased to make payments, as billed, thereby triggering the termination provisions of article 14, which, pursuant to section 14.1.2, permitted recovery of payment for work and for proven loss with respect to materials, equipment, tools and construction equipment and machinery, including reasonable overhead, profit and damages "to the extent of the work completed.” Thus, plaintiff was properly denied lost profits since, given the contract’s express terms in the case of termination, such damages were outside the contemplation of the parties. (See, Kenford Co. v County of Erie, 67 NY2d 257 .) We have examined the other contentions and find them to be without merit. Concur—Sullivan, J. P., Wallach, Kupferman, Asch and Tom, JJ.
Cases cited
- Kenford Co. v. County of Erie 67 NY2d 257 p. 440