Cross appeals from a judgment of the Court of Claims which (1) awarded claimant damages for breach of contract occurring in the course of the performance of its contract for construction of a portion of the Cross Bronx Expressway and (2) awarded damages to the State on its counterclaim for the recovery of overpayments made to claimant on account of the latter’s agreement to supply watchman service. The State first contests claimant’s recovery under the first cause of action in its claim, which is for the cost of excavation above a tunnel constructed pursuant to the contract. The excavation was not provided for by the contract but was ordered by the State, and the sole issue is as to the unit price to be allowed, the Court of Claims awarding at the rate of $35 per cubic foot, under item 2X of the contract, as against the State’s contention that compensation should be at $3 per cubic foot, under item 2S, or, alternatively, on the basis of quantum meruit. It is true, as the State asserts, that, under item 2X, excavation between the vertical planes of two designated stations and within the payment lines shown on the plans was to be paid for at the 2X rate; and, further, that the material excavated was not within these lines; and the court so found; but it was also provided that excavation ordered by the engineer beyond the neat lines shown on the plans would be paid for “ under the appropriate Contract items ”. The excavation in issue was above the portals and beyond the payment lines, but it does not necessarily follow, merely because this excavation was not originally contemplated and was not within the tunnel, that the item 2X rate does not apply; and that rate was correctly applied by the Court of Claims on the ground, among others, that, under the contract provisions, item 2X specifically included all the excavation between the east and west faces of the tunnel, the court finding, also, that the work was largely rock excavation similar to that required in the tunneling operation proper “ and required the same type of equipment, blasting, mining labor and removal as did the tunnel rock excavation.” The decision is supported, further, by claimant’s expert’s analysis of the cross
Cases cited
- Cauldwell-Wingate Co. v. State 276 N. Y. 365 p. 795
- William Higgins & Sons, Inc. v. State 20 N Y 2d 425 p. 795
- Wood v. State 12 N Y 2d 25 p. 795