Majority
In an action, inter aha, to foreclose a mechanic’s lien, the defendant Astoria Pines Holding Co., LLC, appeals, as limited by its brief, from so much of an order of the Supreme Court, Queens County (Taylor, J.), dated February 23, 2001, as denied its motion for summary judgment dismissing the complaint insofar as asserted against it.
The plaintiff GCDM Ironworks, Inc., doing business as GC Ironworks (hereinafter GCI), commenced this action, inter alia, to foreclose a mechanic’s lien filed against property owned by the appellant, Astoria Pines Holding Co., LLC. The appellant moved, inter alia, for summary judgment dismissing the complaint insofar as asserted against it on the ground that it did not consent to the work allegedly performed by GCI. The Supreme Court denied the motion, finding the existence of a triable issue of fact as to whether the appellant consented to the work. This was error.
The relevant portion of Lien Law § 3 provides that a contractor “who performs labor or furnishes materials for the improvement of real property with the consent or at the request of the owner thereof, or of his agent, contractor or subcontractor * * * shall have a lien for the principal and interest, of the value, or the agreed price, of such labor * * * or materials upon the real property improved.” Consent of the owner is the sine qua non, and if no consent is shown, there is no right to a lien (see, Delany & Co. v Duvoli, 278 NY 328 , 331; 76 NY Jur 2d, Mechanics’ Liens § 38; 16 Carmody-Wait 2d, Mechanics’ Liens § 97:49, at 99). The consent required by this section is not mere acquiescence and benefit, but some affirmative act or course of conduct establishing confirmation (see, Valsen Constr. Corp. v Long Is. Racquet & Health Club, 228 AD2d 668 , 669; Tri-North Bldrs. v Di Donna, 217 AD2d 886 ; see also, Delany & Co. v Duvoli, supra; Brigham v Duany, 241 NY 435 , 440; Beaudet v Saleh, 149 AD2d 772 , 773; Mock, Inc. v 118 E. 25th St. Realty Co., 87 AD2d 756 ; Harner v Schecter, 105 AD2d 932 ; M & B Plumbing & Heating Co. v Cammarota, 103 AD2d 879 ).
“Where the circumstances are such that an owner may be said to have consented so far as the contractor is concerned, the owner is deemed also to have consented to the furnishing of labor and materials to the contractor with the latter’s consent” (Rure Assoc. v DiNardi Constr. Corp., 917 F2d 1332 , 1336; see, Wheeler v Scofield, 67 NY 311 , 314; 16 Carmody-Wait 2d, Mechanics’ Liens § 97:49, at 99; 76 NY Jur 2d, Mechanics’ Liens § 38). The subcontractor has the burden of establishing that there was money due and owing to the general contractor from the owner based on a primary contract (see, Falco Constr. Corp. v P & F Trucking, 158 AD2d 510 ; Brainard v County of Kings, 155 NY 538 , 543-544; see also, Rure Assoc. v DiNardi Constr. Corp., supra at 1335).
In view of this determination, we need not reach the appellant’s remaining contentions. Goldstein, J.P., McGinity, Luciano and Crane, JJ., concur.
Cases cited
- P. Delany & Co. v. Duvou 278 NY 328 at 331 p. 496
- Valsen Construction Corp. v. Long Island Racquet & Health Club, Inc. 228 AD2d 668 at 669 p. 496
- Tri-North Builders, Inc. v. Di Donna 217 AD2d 886 p. 496
- Brigham v. Duany 241 NY 435 at 440 p. 496
- Beaudet v. Saleh 149 AD2d 772 at 773 p. 496
- Harner v. Schecter 105 AD2d 932 p. 496
- M & B Plumbing & Heating Co. v. Cammarota 103 AD2d 879 p. 496
- Wheeler v. Scofield 67 NY 311 at 314 p. 496
- Falco Construction Corp. v. P & F Trucking, Inc. 158 AD2d 510 p. 496
- Brainard v. County of Kings 155 NY 538 at 543-544 p. 496
- Zuckerman v. City of New York 49 NY2d 557 at 562 p. 497
- Winegrad v. New York University Medical Center 64 NY2d 851 at 853 p. 497