forth a unit price of $8.56 per 100 pounds and adopted an earlier-Bethlehem price quotation for the job containing a provision that the foregoing unit price was “firm” through December 31,1973 but was thereafter “subject to escalation not to exceed a maximum of $5 per ton per year” from January 1, 1974. The purchase order agreement also recited that delivery dates were “to he negotiated”. When the prime contract between the State and claimant was terminated, claimant and Bethlehem entered into a liquidating agreement under which claimant agreed to prosecute a claim against the State for Bethlehem’s alleged losses from delays caused by the State and in turn Bethlehem agreed to limit claimant’s liability to whatever claimant actually recovered from the State. In July, 1978, the claim in issue was filed, alleging losses not contemplated under the prime contract. The gravamen of the claim was that the State made numerous far-reaching changes in the project and the State’s agents failed to act in an efficient and expeditious manner in coordinating the work of the principal contractors involved, all of which extended the time for claimant’s performance and increased the cost and scope thereof, by reason of which claimant suffered direct and consequential damages. Among the 37 causes of action pleaded, numerous claims were asserted on behalf of subcontractors whose performances allegedly were similarly delayed and made more costly because of the State’s acts and omissions. The claim of Bethlehem was contained in the twentieth cause of action. The State’s motion for summary judgment on Bethlehem’s claim is based on the previously described escalation clause of the latter’s subcontract with claimant. Essentially, the State’s argument is that all of the causes of action set forth in the claim, Bethlehem’s included, are entirely grounded upon delay in performance caused by the State. However, Bethlehem had agreed under the price escalation clause to limit claimant’s additional cost occasioned by delay to a maximum of $5 per ton per year after January 1,1974. Therefore, the State argues, since it has already reimbursed claimant, in conformity with the cost-plus provisions of the prime contract, for its additional cost as determined by the price escalation clause, the State is under no legal obligation to pay for any additional losses of Bethlehem caused by delay. The Court of Claims rejected the foregoing position of the State and denied its motion. The court held that under
Bohl Constr. Co. v Depot Constr. Corp. (
42 AD2d 812 ), clauses in subcontracts for the South Mall project allocating the risk of delay between prime and subcontractors were entirely superseded as to State-caused delays by the Equitable Adjustment Act of 1969 (L1969, ch 328; hereinafter the Act). While there is language in the
Bohl case which lends itself to the Court of Claims interpretation (see
Bohl Constr. Co. v Depot Constr. Corp., supra, p 813 ), we think that
Bohl cannot be read so expansively as to hold that the Act created substantive rights in behalf of subcontractors, independent of contract, to be enforced generally by the courts even when the procedures and remedies under the Act were never invoked. As we held in
Matter of Vermont Marble Co. v Office of Gen. Servs. (
42 AD2d 468 ), the Act was promulgated as an alternative to and for the purposes of avoiding litigation of the myriad of delay-based claims arising out of the construction of the South Mall. Under the Act, an “aggrieved” prime contracting party with the State is permitted to apply to the Office of General Services for an equitable adjustment of its claim that its cost of performance was increased by delays attributable to “an act or omission of the State not expressly or impliedly authorized by the contract” (Public Buildings Law, §
10). In such an event, the Commissioner of General Services may enter into an agreement with the applicant to modify the prime contract accordingly, and payment by the State pursuant to such an agreement may be made upon approval thereof by various named State officials. On its face, the