Majority
This action was instituted to foreclose a materialman’s lien and to recover on a statutory bond given by the contractors. The appeal is taken on the judgment-roll alone. It appears from the findings that the defendants Longshore, as owners, entered into a contract with the defendants Thompson and Stowell, as contractors, for the erection of a building on the owners’ lot in the city of Redondo
The trial court entered judgment for plaintiff against the contractors for the amount due for the materials furnished, together with interest and costs, but denied it the right to foreclose its lien. It also denied plaintiff judgment against the surety on the contractors’ bond. From the adverse portions of the judgment plaintiff has appealed.
■The trial court found, and the appellant concedes, that the building was completed and occupied by the owners on September 21, 1923. As the owners failed to file their notice of completion within ten days thereafter it was incumbent upon all persons to file their claims of lien within ninety days after actual completion of the building. (Code Civ. Proc., see. 1187; Schwartz & Gottlieb v. Marcuse, 175 Cal. 401 , 415 [ 165 Pac. 1015 ]; Bird v. American Surety Co., 175 Cal. 625 , 631 [ 166 Pac. 1009 ]; Robison v. Mitchel, 159 Cal. 581 , 585 [ 114 Pac. 984 ]; Simons Brick Co. v. Hetzel, 72 Cal. App. 1 , 9 [ 236 Pac. 357 ]; Emigh-Winchell Hdw. Co. v. Pylman, 38 Cal. App. 508 , 509 [ 176 Pac. 722 ].) This the appellant failed to do, for it deferred such action until December 27, 1923, ninety-seven days after actual completion. It has, therefore, no valid lien.
Even if it be assumed, without deciding, that the owners by reason of their tardy filing of the notice of completion are estopped to deny that the building was completed on November 15, 1923, as recited in such tardy notice of completion, it would avail the appellant nothing for its claim of lien would not, even then, have been filed within thirty days after such completion as required by section 1187. A
The trial court held that plaintiff was not entitled to judgment against defendant McWhinnie as surety on the contractors’ bond “for the reason that said instrument is not a good, sufficient and valid bond.” An examination of the bond appearing in the findings discloses that it was not properly drawn in that the name of one of the owners of the property appears in the body of the instrument as “surety” whereas the signature of defendant McWhinnie appears at the end thereof where it is usual and customary for a surety or obligor to sign his name. In our opinion the
Dissent
For the foregoing reasons the judgment is affirmed except in so far as it purports to deny relief to the appellant as against the defendant McWhinnie. In this latter respect the judgment is reversed with directions to the court below to enter judgment for the plaintiff as against the defendant McWhinnie. The appellant to recover costs against the respondent McWhinnie and the respondents Longshore to recover costs against the appellant.
Seawell, J., Langdon, J., and Richards, J., concurred.
I concur in the conclusion of the foregoipg opinion concerning the sufficiency of the bond as against the defendant McWhinnie, but I dissent from that portion of the opinion which holds that the plaintiff’s claim of lien was not filed within time. It is undisputed that the claim of lien was filed within thirty days after the filing of the notice of completion by the owners. But it is held that because the owners did not file the notice of completion within ten days after the date of completion, as such date is now asserted by them (but contrary to the completion date inserted in the notice of completion), therefore the filing of said notice of completion could not be deemed an equivalent of completion as provided in section 1187 of the Code of Civil Procedure. Ordinarily no one is in as good a position to know when a building is completed as the owner. At least he is in a better position to know than lien claimants. Being in that position, he is bound so to direct his course of action as not to mislead lien claimants with reference to the time when claims of liens must be filed. If the owner occupies the premises and there is a cessation of •labor, as in the present case, the lien claimants are put upon notice that they must file their liens within ninety days, if no notice of completion is filed within that time. But if, as here, within said ninety days, the owner files of record a verified notice of completion, lien claimants should be entitled to rely on the record of such filing as indicating the statutory equivalent of completion and the owner should be estopped to deny the verity and effect of his affirmative step in so filing his notice of completion. Otherwise his action might, and in this case undoubtedly did, operate to the prejudice of the lien claimant. In other words, the owner should not be permitted to rely on his own disregard of the statute in failing to file the notice of completion within the statutory time when such disregard of the statute has resulted in misleading the lien claimant. That an estoppel will lie against an owner when he makes inconsistent claims as to the date of completion has been decided in the case of Hubbard v. Lee, 10 Cal. App. 477 [ 102 Pac. 528 ], relied upon by the plaintiff. The oral representations of the owner in that case were of no greater force, in my opinion, than the solemn act of the owners in this case in
Curtis, J., and Preston, J., concurred.
Cases cited
- Schwarz & Gottlieb, Inc. v. Marcuse 175 Cal. 401 at 415 p. 356
- Bird v. American Surety Co. of New York 175 Cal. 625 at 631 p. 356
- Robison v. Mitchel 159 Cal. 581 at 585 p. 356
- Simons Brick Co. v. Hetzel 72 Cal. App. 1 at 9 p. 356
- Emigh-Winchell Hardware Co. v. Pylman 38 Cal. App. 508 at 509 p. 356
- P. A. Buell & Co. v. Brown 131 Cal. 158 at 162 p. 357
- Hubbard v. Lee 10 Cal. App. 477 at 482 p. 357, p. 358
- Hubbard v. Lee 6 Cal. App. 602 p. 357
- Kurtz v. Forquer 94 Cal. 91 at 93, 94 p. 358
- Hughes Manufacturing & Lumber Co. v. Hathaway 174 Cal. 44 p. 360