Majority
Headnote
Street Improvement—Private Injunction Against Contractor— Expiration op Time por Performance—Extension—Void Assessment.—An injunction at suit of a private person against a contractor to prevent the performance of a contract for a street improvement does not extend the time of performance thereof by operation of law; and where no extension of time was asked for or granted until after the expiration of the time limited for performance, an assessment for work done after such expiration is void and cannot be enforced.This is an action to foreclose the lien of an assessment for curbing and paving a portion of Market street in San Francisco. Plaintiff had judgment, and certain of the defendants moved for a- new trial, and upon the denial of their motion appealed from the order and judgment.
It appears from the complaint, findings, and evidence that the contract to do the work was let by the superintendent of streets, dated January 26, 1896, in which the time
There is no express provision, either in the street law or elsewhere, making the issuance of an injunction at the suit of a third party an excuse for delay in the performance of such a contract. Section 1511 of the Civil Code provides that “the want of performance of an obligation ... or any delay therein, is excused by the following causes, to the extent to which they operate: (1) When such performance ... is prevented or delayed by the act of the creditor, or by the operation of law.” It is under the rule of this section that the delay in this case can be excused, if at all, and this depends upon whether or not the delay caused by the issuance of the injunction is a delay caused by operation of law. A similar question was presented in Klauber v. San Diego St. Car Co., 95 Cal. 353 , [ 30 Pac. 555 ], where it was held that interference by a writ of injunction sued out by a third person will not excuse the performance of a contract, and that such an interference is not a prevention of performance by operation of law. It is there said: “No case has been cited in which it has been held that interference
In the case at bar it is not pretended that any of the defendants, or any officer of the city, took any part in the injunction suit or in any way instigated it. The contractor could have kept his contract alive by obtaining from the board of supervisors an extension of time. So far as the record in this ease shows he took no steps to procure a dissolution of the injunction, but simply waited until the plaintiff in that action dismissed the proceeding. The cases of Hadley v. Clarke, 8 Term Rep. 259, and Baylies v. Fettyplace, 7 Mass. 325 , cited by respondent, are both cases of delay in the performance of contracts by reason of the operation of embargo acts, and are typical cases of prevention of performance by operation of law. Williams v. Pouns, 48 Tex. 141 , and Little v. Price, 1 Md. Ch. 182 , also cited by respondent; are cases where the bringing of the action was enjoined for a time at the suit of the opposite party to the litigation, and it was held that such injunction stayed the running of the statute of limitations, in favor of the party procuring the injunction, not because thq bringing of the suits was prevented by operation of law, but by the act of the party defendant. On the other hand, in Wilkinson v. First Nat. Fire Ins. Co., 72 N. Y. 499 , [ 28 Am. Rep. 166 ], it was held that an injunction issued at the suit of a third person was not a prevention by act of law, and did not suspend the running.of the time limited in the contract
For the' reasons above set forth, we are of the opinion that the issuance of an injunction at the suit of a third party was not a prevention of performance by operation of law, and therefore the time for performing the contract had expired before the extensions thereof pleaded and found, and all subsequent proceedings thereunder were void. (Kelso v. Cole, 121 Cal. 121 , [ 53 Pac. 353 ], and other cases cited supra.) In view of the conclusion we have reached on the main point involved in this case, it is unnecessary to discuss other points made by appellants.
The judgment and order are reversed.
Harrison, P. J., and Cooper, J., concurred.
Cases cited
- Turney v. Dougherty 53 Cal. 619 p. 535
- Beveridge v. Livingstone 54 Cal. 54 p. 535
- Mappa v. Council of Los Angeles 61 Cal. 309 p. 535
- Palmer v. Burnham 120 Cal. 364 p. 535
- Kelso v. Cole 121 Cal. 121 p. 535, p. 537
- Klauber v. San Diego St.-Car Co. 95 Cal. 353 p. 535
- Sample v. Fresno Flume & Irrigation Co. 129 Cal. 222 p. 536
- Rogers v. Druffel 46 Cal. 654 p. 536
- Wilkinson v. First National Fire Insurance Co. of Worcester 72 N. Y. 499 p. 536
- Hadley v. Dague 130 Cal. 207 p. 537