Majority
Headnote
Contracts—Sale of Marble—Former Decision—Law of Case.—In this action to recover on a contract for furnishing marble for the repair of a. building, it is held that the decision on the former appeal ( 163 Cal. 227 ) that the contract price was to be determined by the amount of the marble set and measured in the building, and not by the amount actually furnished by the contractor, is the law of the case.The action was brought to recover the sum of $6,170.61 claimed as a balance due on a contract for marble shipped from Colton, California, to be used in the Monadnock Building in San Francisco, and the verdict and judgment were for plaintiff in the sum of five thousand and seventy dollars, and interest. The parties to said contract were W. A. Perrin, a manufacturer of marble, and Herbert E. Law, the owner of said building, and the plaintiff is the assignee of said Perrin.
We may state appellant’s first contention in his own language: “Law concedes that Perrin’s figures are correct as to the amount of marble placed on the cars at Colton and shipped to San Francisco, as he has no means of disputing plaintiff’s evidence in this behalf or questioning the accuracy of the various statements sent to him from time to time relating to shipments. Law also concedes and admits that plaintiff’s statement as to the amount of money paid by him is correct. Law contends, however, that he is not responsible for the total amount of marble shipped, but that the limit of his liability is made to depend upon the quantity of marble actually set in place in his building at the unit prices fixed in the contract.” It is insisted that there is no substantial conflict in the evidence but that it shows that “the contract value of the marble set in the building was $33,908.45; also that $31,315.40 was paid on the contract value of the marble set in the building since the fire. The uneontradicted and undisputed evidence was that $7,404.35 worth of marble was saved from the disaster, upon which a balance of $2,738.78 was owing and upon which there had necessarily been paid $4,665.57. This would show that the sum of $35,980.97 was the full amount paid upon all the marble set in the building, or $2,070.52 in excess of the contract price.” Indeed, it is admitted that the vital point in the controversy is involved in the amount of marble saved from the fire that is now in the building. Respondent denies that marble of the value of $7,404.35 was saved but claims that it was only of the value of $1,124.35, admitting, how
In said opinion it was declared by the supreme court: “Appellant, however, contends and it is without dispute that the contract price for all the marble actually set in the building and measured therein upon its completion amounted to the sum of $33,908.45; that it is equally without dispute that $7,404.35 of this amount was marble saved from the disaster; that deducting this latter sum from the former there is left $26,504.10 as the contract price of the marble shipped after the disaster and actually set in the building. . . . Also appellant still further argues and shows that immediately after the disaster there was a balance unpaid upon the marble shipped of $2,738.78; that there was marble saved to the value of $7,404.35. Deducting from this the sum of $2,738.78, which was owing, $4,665.57 had been paid upon the marble saved from the disaster and placed in the building. Upon the shipment of marble made after the disaster there has admittedly been paid $31,315.40, making a total payment for the marble actually set in the building of $35,980.97.” Of course, that decision befiame and is the law of the case (Brett v. S.
There is no doubt that the only direct evidence based upon actual knowledge was in favor of appellant’s contention. The record warrants the following statement by appellant: “Shortly after the disaster and when it was the desire of Law to find out how much marble was uninjured and intact, he instructed his superintendent to have the marble throughout the Monadnock Building examined and measured. Two young men were employed to do this work. They were Morris Helger and the younger Perrin. After the marble in the building had been examined and measured by these men a statement thereof was made by each of them. The statements were identical. . . . This statement was prepared at a time when everything was fresh in his mind and was approved by the elder Perrin, the subcontractor for the setting of the marble in place in the building. This statement was presented to the elder Perrin, who indorsed it by attaching his signature thereto. Upon its face it gave evidence of careful preparation. At the time it ivas made out it was the desire of Law to collect all the insurance money owing to him on account of damaged marble—that is, marble that had been injured by flame and smoke, or which had been loosened from the walls of the building to such an extent that it would have to be reset. There was no motive at that time for making the estimate of damaged marble less than it was. No dispute had arisen between Perrin and Law, nor had there been any difficulty of any kind between plaintiff and defendant. There was no motive for making the amount of marble saved greater than it really was. The motive, if any, must have been the other way. Years after this estimate was made young Perrin is placed upon the witness-stand and says that the measurements that he made in May, 1906, a statement
As to whether there was any such credible evidence, counsel are in hopeless conflict.
The other important contentions of appellant relate to the action of the court in giving and refusing certain instructions. It is claimed that the court erred in refusing the following instruction requested by appellant: “If you believe from the evidence in this case that the defendant and one W. A. Perrin entered into a contract, whereby said Perrin was to manufacture polished marble for use in a building belonging to the defendant in this city and that defendant was to pay for such quantity of marble at the prices mentioned in the contract as was set in said building; and if you also find that defendant has fully paid for all the marble set in said building at the contract price set forth in said contract, then I charge you that plaintiff is not entitled to recover and your verdict should be in favor of defendant.” It is said by appellant that “the foregoing instruction covers all the law there is in the case as regards the rights of either plaintiff or defendant, for if Law has actually paid for all the marble set in place in the building, plaintiff cannot recover anything
In the Inman case, the contract having been for the purchase of a certain number of redwood ties, it was held that “though defendant could not be compelled to accept any ties in excess of the maximum stated in the written contract, j^et when an excess was delivered and accepted by the defendant, the court was justified in holding that all of the extra ties were delivered under the contract at the contract price and that defendant assumed the corresponding obligation to pay
We can see no practical objection to such principle and, conceding that evidence was admitted without objection that defendant received and appropriated to another use additional marble to that used in said building, said marble being furnished under the same contract, the jury would be warranted in holding the defendant liable for it at the contract price. However, after plaintiff was compelled, by the decision of the supreme court, to change his theory of the liability of defendant, it would have been better practice for him to amend his complaint so as to include by appropriate averments this additional marble. This- would have been more in accordance with the accepted rules of good pleading and practice. From the statement of respondent it is apparent that his complaint was framed upon the theory of an express contract and he sought to recover additionally upon a quantum valebat or conversion. In the absence of objection, though, as already indicated, it would be without prejudice and not unreasonable to hold that the cause was tried upon the theory that the issue was properly presented and therefore the point as to variance could not thereafter be urged.
We think, however, that plaintiff’s contention as to defendant’s liability for the surplus marble is untenable. This view of plaintiff, erroneous as we conceive it, was adopted by the trial court and embodied in the instructions to the jury. There was, it is true, a few hundred dollars ’ worth of marble sold by defendant under agreement with plaintiff, but we understand there is no serious controversy as to that small amount and it may be eliminated from consideration. Law’s contract did not make him liable for the surplus. His agreement was to pay for whatever amount of material was incorporated in the building. The surplus marble that was shipped from Colton was at the risk of the plaintiff. Defendant was not responsible for all that was received at the building. If he had appropriated the surplus his liability would have attached, but there is no evidence that he appropriated more than was- actually used, except the small amount before stated. As already stated, he could not know how much even to accept for the building until the marble wa§ set io place,
The court instructed the jury as follows: “Ton are instructed as a matter of law that the title to the marble shipped under the contract in evidence and under the plans and specifications connected therewith, passed to the defendant Law when placed aboard the cars, f. o. b. Colton, California, and that the marble so shipped thereupon became the property of said Law, subject to the right of said La\V to return to plaintiff, or plaintiff’s assignor, any surplus over that he required for the building, according to the plans and specifications, -if any such there be.” We agree with appellant that this instruction was calculated to mislead the jury and to induce them to hold Law liable for all the marble that was shipped from Colton. As suggested, the parts of a contract must be construed together to arrive at the intention of the parties. So construed, it seems plain that Law did not become the owner of the marble until it was incorporated in the building. If he became the owner "when it was placed on the cars at Colton he was liable for it and would have no right to return any portion of it unless there was an agreement to that effect. But there was no agreement about the return
The jury were directed as follows: “You are instructed that if you find from the evidence that there was any surplus marble shipped to defendant by the plaintiff, or by plaintiff’s assignor, and received and accepted by defendant, that it was the duty of defendant to account for such surplus marble to plaintiff or plaintiff’s assignor.”
The term “accepted” was not defined and was likely to be misconstrued by the jury. “Accepted” is often used in the sense of “received.” That is one of the definitions of the word. Ordinarily it signifies “to receive with favor or approbation.” No doubt, all the marble received in good condition was accepted in that sense, but the additional element of use in .the building was necessary to bind appellant under the contract. From the phraseology used in the instruction we think the jury would quite naturally conclude that Law was liable for all the acceptable marble received at the building and therefore it should not have been given.
The court also, in its oral instructions, gave the following: ‘ ‘ According to the view which I take of the law and as I have stated in one of the instructions, any marble shipped from Colton, which accorded with the terms and conditions of the contract of the parties, as to size, dimensions and the like, and which was to be shipped in good condition free on board the cars at Colton, thereupon and thereby became the property of the defendant, Law.”
From this instruction we think the jury would almost necessarily conclude that the amount of such marble shipped from Colton was the test of defendant’s liability under the contract instead of the amount set in the building.
If such instruction had been given it is quite likely that a different verdict would have been rendered.
It is apparent from an examination of the record that much confusion would have been avoided and less likelihood of error fostered if plaintiff had amended his complaint so as to show separately how much he claimed for the marble set in the building under the original contract and how much for the surplus appropriated otherwise by defendant. If the ease is to be tried again it is to be hoped that such amendment will be made in order that the issues may be regularly framed.
We think the judgment and order should be reversed and it is so ordered.
Chipman, P. J., and Hart, J., concurred.
A petition to have the cause heard in the supreme court, after judgment in the district court of appeal, was denied by the supreme court on September 16, 1915.
Cases cited
- Fleming v. Law 163 Cal. 227 p. 110, p. 113
- Inman v. L. E. White Lumber Co. 14 Cal. App. 551 p. 117
- Bedell v. Kowalsky 99 Cal. 236 p. 117
- Levino v. Moore Co. 97 App. Div. 109 p. 117