Majority
Plaintiff Wilson sued defendants Keefe[1] to recover for extras performed under a building construction
1 Mrs. Keefe seems to be a nominal party and the husband will be indicated by use of the word “defendant” unless otherwise indicated.
Re Plaintiff’s Appeal
The work was done under a written contract of March 19, 1953, wherein plaintiff Wilson agreed to construct for defendant a residence upon “Lot 34 on Lago Vista Dr., Beverly Hills, Calif.” for an agreed sum of $32,200. Paragraph 8 covers the matter of omissions and extras: “Should the Owner at any time during the progress of the work request any modification, alterations or deviations in, additions to, or omissions from, this contract or the plans or specifications, he shall be at liberty to do so, and the same shall in no way affect or make void this contract; but the amount thereof shall be added to or deducted from the amount of the contract price aforesaid, as the case may be, by a fair and reasonable valuation, based upon the actual cost of labor and materials plus 10% profit to the Contractor. . . . The rule of practice to be observed in fulfillment of this paragraph shall be that upon the demand of either the Owner or the Contractor, the character and valuation of any or all changes, omissions or extra work shall be agreed upon and fixed in writing, signed by the Owner and the Contractor, prior to execution. . . . Provided however that the Contractor is not deemed to have waived his right to compensation for extra work if the same is not provided for in writing.” The court found upon adequate evidence that plaintiff at defendant’s request supplied extra labor and material having reasonable value of $906.82; that neither party ever demanded or requested that the character or value of changes, omissions or extra work should be agreed upon and fixed in writing signed by the parties prior to execution of the work. From this it was concluded that “plaintiff is precluded from recovery of said sum for the reason that paragraph 8 of said building contract was not complied with by the parties in that neither party requested that same be reduced to writing and that same was not so reduced to writing.”
In this conclusion the court erred. There were omissions amounting to $1,358.94, which were credited to the owner by the contractor without the support of any writing. The extras were done upon the request and with full knowledge of the
True, the specifications say: “The owner may order extra work or make changes by altering, adding to or deducting from the work, the contract sum being adjusted accordingly as agreed to by the owner and contractor before the change is commenced.” It will be noted that this language is merely a partial duplication of the provisions of paragraph 8 of the contract. In view of the specific nature of the concluding language of that paragraph it must be held that the specifications yield to the contract and that the last sentence of paragraph 8 governs the specification as well as the contract itself. (See Am.Jur. § 11, at page 12; Moreing v. Weber, 3 Cal.App. 14 , 20 [ 84 P. 220 ]; Valley Const. Co. v. City of Calistoga, 72 Cal.App.2d 839 , 841 [ 165 P.2d 521 ].)
It follows that, upon the evidence now before us, plaintiff is entitled to recover for said extras.
Defendants’ Appeal
The contract provides that the dwelling be constructed upon the designated Lot 34. The street is a winding, mountainous road, with no sidewalks, but apparently the curbs had been installed. When completed the house “did
The contract, in addition to providing that the building be constructed on Lot 34, requires that it be completed “in strict conformance with plans and specifications for the same signed by the parties hereto;” also, “in strict compliance with all laws, ordinances, rules and regulations of competent public authority. ’ ’ Paragraph 7 thereof says: ‘1 The plans and specifications are intended to supplement each other, so that any works exhibited in either and not mentioned in the other are to be executed the same as if they were mentioned and set forth in both.”
The agreement makes no mention of an architect or of any superintendence of the work. This is also true of the specifications. They were prepared by one Colleen Crist, who is trained in draftsmanship but not licensed as an architect. The fact that she had no license was known to the contracting parties and plays no part in the solution of this case. The specifications provide: “The owner shall supply all information as to lot lines, deed restrictions, property line agreements [sic], easements, or any other right effecting [sic] this building. The drawings were completed with the information supplied, and changes resulting from misinformation shall be paid for on a fair and reasonable basis. ’ ’ Neither of said documents (contract or specifications) mentions Miss Crist or purports to confer any authority on her, except that the specifications do say: ‘ ‘ The building is to be framed, braced, spiked and pinned in a sound manner and to be true and plumb. Consult with Miss Crist in regard to any framing which involves construction different from that indicated on various details or which is not detailed in the drawings.”
The court having found with plaintiff on this phase of the case, all testimony and all inferences favorable to respondent must be accepted in this court. (Nichols v. Mitchell, 32 Cal.2d 598 , 600 [ 197 P.2d 550 ].) We proceed upon that basis.
Defendant says he furnished to plaintiff all plans, contour maps and surveyor’s maps which he had received when he purchased the lot; this the plaintiff denies, saying he was
The arrangement between the owner and Miss Crist is not in evidence; it does not appear whether the same was oral or written; Miss Crist was not called as a witness. Her conduct was such, and known to defendant to be such, that it raised a fair inference of agency, express or implied, actual or ostensible, with respect to the matters above discussed and continuing throughout the construction period. We cannot say that the evidence does not warrant the finding that the building “was placed in such position according to the plans pre
2 The plans themselves' seem to have been before the trial court, but they were never formally received in evidence and are not among the exhibits transmitted to this court.
The portion of the judgment which denies plaintiff recovery on his first amended complaint is reversed; the portion which denies defendants recovery upon their amended cross-complaint is affirmed.
Moore, P. J., and Fox, J., concurred.
Cases cited
- Frank T. Hickey, Inc. v. Los Angeles Jewish Community Council 128 Cal.App.2d 676 at 682-683 p. 181
- Wyman v. Hooker 2 Cal.App. 36 at 41 p. 181
- Bavin & Burch Co. v. Bard 81 Cal.App. 722 at 727-728 p. 181
- Miller v. Brown 136 Cal.App.2d 763 at 775 p. 181
- Roberts v. Security Trust & Savings Bank 196 Cal. 557 at 570 p. 181
- Moreing v. Weber 3 Cal.App. 14 at 20 p. 181
- Valley Construction Co. v. City of Calistoga 72 Cal.App.2d 839 at 841 p. 181
- Nichols v. Mitchell 32 Cal.2d 598 at 600 p. 182