Majority
Headnote
The complaint in an action was for work, labor and services and materials, alleged to have been done and furnished at defendant’s request. The evidence given on the trial showed that such work and materials were done for and furnished to a subcontractor in the construction of certain buildings for defendant, and that the only contract plaintiffs had with the defendant was one by which the latter agreed to withhold a specified amount from the contractor and apply the same in payment of plaintiffs’ claim on completion of the work. Meld, that there was a fatal variance between the pleading and proof, and that a dismissal of complaint was properly ordered.The complaint was for work, labor and services performed and materials furnished at defendant’s request, and the answer, besides generally denying the allegations of the complaint, interposed as a counterclaim a claim for damages alleged to have accrued to defendant out of plaintiffs’ unauthorized filing of a notice of lien claimed pursuant to the provisions of the Mechanic’s Lien Law (Laws 1885, chap. 342). A demurrer to the counterclaim was sustained at Special Term, but on appeal to the General Term of the court below was overruled. Defendant thereupon caused final judgment in his favor to be entered upon the decision of the General Term. Upon appeal to this court that judgment was reversed as unauthorized, the proper judgment upon a decision overruling a demurrer to part of an answer being an interlocutory one. Biershenk v. Stokes, 18 N. Y. Supp. 854 ; 46 N. Y. St. Repr. 179 . Pursuant to the directions in the judgment of this court, an interlocutory judgment overruling the demurrer and granting plaintiffs leave to reply to the counterclaim on payment of costs was thereupon entered at General Term of the court below. With .the conditions of the leave granted them plaintiffs never complied, and no reply to the counterclaim was ever served, so that, at the time when this action was reached for trial in the court below, the counterclaim, assuming it to have been valid as such, stood admitted, except as to the amount of defendant’s alleged damages.
On the trial it appeared unchallenged, and from evidence which plaintiffs had themselves adduced, that the work, labor and services and materials, for which they sought to recover in this action, were performed and furnished by them under a contract, in writing, which they had made therefor with one Owen Cumiskey, a subcontractor of Squire & Whipple, with whom the defendant had contracted for the construction of certain buildings. It further appeared from plaintiffs’ own showing, and from documentary evidence adduced by them,
Observing the rule that the recovery must, in every case, be secundum allegata et probata (Romeyn v. Sickles, 1 Silv. Ct. of App. 594; 108 N. Y. 650 ), it is indisputable that the ruling of the trial court in granting the motion of defendant’s counsel for dismissal of the complaint was correct. The cause of action which appeared from the evidence was widely different from the cause of action alleged in the complaint, and was susceptible of widely different defenses. There was, therefore, not only a variance between the complaint and the proof, and an entire failure of proof, but the cause of action alleged was disproved. Arnold v. Angell, 62 N. Y. 508 .
Nor can appellants, on this appeal, secure a review of the interlocutory judgment of the General Term of the court below which overruled their demurrer to defendant’s counterclaim. Section 3192 of the Code of Civil Procedure provides that section 1294 shall be applicable to appeals from the City Court to this court, and section 1294 confers the right of
The judgment should be affirmed, with costs.
Bookstaver and Pryor, JJ., concur.
Judgment affirmed, with costs.
Cases cited
- Romeyn v. Sickles 108 N. Y. 650 p. 694
- Arnold v. Angell 62 N. Y. 508 p. 694
- Hughes v. Stickney 13 Wend. 280 p. 695
- Reid v. Venderheyden 5 Cow. 719 p. 695
- Hall v. Brooks 89 N. Y. 33 p. 695