Majority
Headnote
Where, after a breach of a contract by one party, the other is permitted to perform the same in part and receives the contract-price for such part performance, this is not a waiver or a release on the part of the latter of his right to damages for the breach. He may refuse further performance or perform as far as he is permitted and then claim his damages.There is no contention on the part of the state-that the award in this case is excessive, provided it is free from the objections which it makes thereto. Its claim is that, there was no liability whatever on its part for any of the-damages embraced in the award. It will conduce to perspicuity and brevity to consider the various objections under-separate heads.
(1.) The furnishing contract required the contractors to-furnish the stone of the quality known as hard sandstone for the exterior facings of the walls of the asylum buildings, and the cutting contract required them to cut such stone. The* contracts contain no description of the buildings, and there is. nothing in either of them specifying that the whole exterior-facings of the walls were to be of sandstone, and hence it is. contended that there was no breach of the contracts in the-construction of the walls of some of the buildings of brick with sandstone trimmings. But it is fairly to be inferred from the language of the furnishing contract that the facings, of the walls were to be of sandstone. The contractors were to furnish all such stone required and necessary for the construction of the buildings. The stone was to come from quarries in Orleans county, and the contractors agreed to lease*
(2.) In answer to the claim for damages on account of the change from stone facings to brick with stone trimmings, it is said by the learned counsel for the state that such change was authorized by the contracts, and that it was not, therefore, a breach thereof. It is not pretended that there is anything in the terms of the furnishing contract authorizing such a change. According to that contract the contractors were bound to furnish and the state was bound to take from them all the sandstone required for the completion of the buildings according to the plans and specifications. But the cutting
But if we should suppose that the rule could have operation and that this clause must be taken as controlling the construction of both contracts, as it certainly must be taken as controlling the construction of the contract in which it was inserted, yet we are of opinion that it cannot have the effect claimed for it and that it did not authorize the change made. What change did the state reserve the right to make ? It certainly had no right to omit entirely the construction of all or any of the buildings. The asylum buildings referred to in the contracts were the central or administration building, the five connecting wards on each side and the out-buildings. These were all to be built. The size and height of them were fixed and the material to be put in the walls was determined. The general character of the buildings could not be changed so that the buildings would not be the same contracted for; if it could be, then a public letting in such a case would not be a useful and might be an idle ceremony. Under such a reservation could a building planned for five stories be reduced to two ? Could a stone building let to a stone mason be changed to wood or brick? Could the five connecting wards be reduced to two or three or four ? We are clear that authority for such extensive changes could not be found in such language. If the state could change to brick walls with sandstone trimmings, then it could change to walls made wholly of brick, and thus there would be no stone to cut and the cutting contract would be entirely nullified. It is difficult, probably impossible, to draw in advance a precise line between what is authorized by such a reservation and what is
The construction we have thus given is fortified rather than weakened by construing both,contracts together, as the learned counsel for the state claims. they should be. Under the first contract the contractors were required to own or purchase quarries and lease them or give the control of them to the state, and thus they were required to make considerable investments for the purpose of being able to furnish the stone. Can it be supposed, under such circumstances, that the parties intended by. the reservation in the second contract to authorize at the will of the state any change that might substantially destroy the furnishing contract? Would buildings with a few superficial feet of sandstone facings be the building in reference to which the competitive bidding was invited and the contracts were let ? We think not, and that the contracts were broken by change from sandstone to brick; > .
(3.) After the resolution of May 25, 1876, under which the change from sandstone to brick with sandstone trimmings was made, the contractors furnished and cut the sandstone for the trimmings and received pay therefor in full under the contracts, and.therefore the state contends that they practically construed the contracts as authorizing the change and that their conduct constituted a waiver of any claim for damages by reason of such change, If the contractors had in any way induced the change or if they had taken any advantage therefrom, or if their conduct had thereafter imposed any loss upon the state there might have been some reason for the contention now made. But it does not appear that they knew that the change was contemplated until it was irrevocably accomplished, and if they had known it they could not have prevented it. They furnished and cut the stone for the trimmings under their contracts, and this they had the right to do. They could perform their contracts so far as they were able, without
But here there was not silent acquiescence in the change. The contractors did not in any way assent thereto, and the finding that they protested against the same has some support in the evidence. A finding that they condoned a serious violation of their rights and effectually released and waived a large claim of damages should have something substantial to rest upon.
(4.) The plan of the out-buildings was also changed from. sandstone facings to brick with sandstone trimmings, and they were built upon the changed plan. There does not appear to have been any formal resolution making this change. But it was nevertheless made by the representatives of the state at the same time with the change in wards O, D and E, and as part of the same scheme for the completion of the asylum
(5.) The largest portion of the award made to the claimant, is founded upon the omission of the state to construct the five female wards. The refusal of the state to build them, and to allow the contractors to furnish and cut the stone for them constituted a breach of the contracts which made it hable for damages. The contractors in no way assented to this breach.. They were ready, willing and able to perform the contracts on their part. It is true that no time is specified in the contracts for the construction or completion of the buildings. The contractors were bound in terms to furnish and deliver the stone from time to time as rapidly as they might be required for the construction of the buildings, and the state was bound to make them monthly payments; and by the cutting contract they were bound “ to commence the work immediately and prosecute the same diligently to its completion.” At the time, the contracts were let the state had inaugurated a scheme for the immediate construction of the asylum buildings and had appropriated money for that purpose, and it was evidently the expectation of all parties that the work of construction would at once be commenced and carried to completion without unnecessary delay. The contractors were clearly bound to commence performance on their part and to continue to final-performance, and it would be quite unreasonable to hold that while they were at all times bound to be ready and able to perform, the state was at liberty at any time for an indefinite period to arrest and abandon performance which might again be resumed at its pleasure. We think after entering into these contracts and commencing the work, the state was bound to go on with the construction of the buildings without unnecessary delay, and to carry the enterprise to completion within a.
The state was bound by its contracts just as an individual would have been bound. It might violate them, but could not repudiate or destroy the obligation of them. It was bound through its legislature to make the necessary appropriation of money for them, and to do whatever was necessary for performance on its part. The contractors did not, in entering into the contracts, take the chances that the legislature would pass the acts requisite for performance on the part of the state; but they had the right to expect and demand performance on the part of the state as if it were an individual. Now, what did the state do ? After the central building, the five male wards and the out-buildings were completed, and while the contractors were there with their material ready to continue performance on their part, the managers representing the state, by resolution, on the 5th day of November, 1811, ordered them to remove all their stone from the asylum grounds within ten days. The stone referred to, or at least some of them, may be presumed to have been delivered there for the performance of their contracts. The order was peremptory to remove all their stone, and thereafter they were not permitted to furnish or cut any more stone, and the five female wards have never been constructed, and the legislature has never appropriated any money for their construction. We think the contractors had the right to regard the contracts as broken as to the female wards, and they were not bound to make any offer or tender of performance. The resolution of the managers was equivalent to a positive command to cease further performance on their part. It is clear that an offer of performance on their part after that would have been fruitless, as the managers, without a legislative appropriation, were powerless to perform.
W e are, therefore, of opinion that the award is not open to-any of the assaults made upon it on behalf of the state, and. that its appeal should fail.
(6.) After the Board of Claims had determined that the ■contractors would have made as profits from the performance of the two contracts the sum of $105,200.42, computed as .stated in the findings of facts, they deducted from that sum .$30,200.42, and awarded the sum of $75,000 as the aggregate profits which would have accrued to the contractors from the ■performance of the two contracts. The larger sum was reached by taking the difference between the contract-prices .and the estimated cost of the stone and cutting, and was the result of a mathematical calculation based upon data furnished by the witnesses. The general statement of the rule of damages in such cases is the difference between the contract-price and the cost of performance, and in the case of contracts requiring for their performance a few acts and a brief period ■of time the rule is not difficult of application and will gener.ally produce results sufficiently certain for the purposes of justice. But in the case of contracts requiring for their performance many acts and a series of years, the application of ■the rule is attended with more uncertainty and the question -of damages becomes a complex problem not so easily solved. In such cases accidents and contingencies may and usually will .intervene to vary results. Here the Board of Claims were dealing with contracts which would take several years for their performance. The contractors were required to take the stone from quarries in Orleans county and transport them about 100 miles, to the asylum grounds in Buffalo, and then «cut them ready for the buildings. ■ Capital, machinery and implements had to be supplied and kept for the performance, and during the five years there would be many contingencies and accidents to vary results and probably to detract from profits. In the estimation of damages for the breach of such contracts all these matters ought to be considered. In fixing the gross sum, however, we must assume that they were not ■allowed their proper influence. So, too, in estimating profits from the performance of such contracts requiring the labor,
(7.) The claimant contends that the Board of Claims erred in not allowing him interest upon the amount found due from the date of filing his petition against the state. If this had been a common law action against an individual to recover damages for breach of contracts under precisely the same conditions, we are of opinion that interest could not legally have been allowed to the plaintiff, even from the commencement of the action. The claim is in every sense unliquidated. There was no possible way for the state to adjust the same- and ascertain the amount which it was liable to pay, and hence within the decision of White v. Miller ( 71 N. Y. 118 , 78 id.
We have therefore come to the conclusion upon the whole ■case that neither appeal should prevail, and the award should be affirmed without costs to either party.
All concur, except Danforth. J., dissenting, and Gray, J., who dissents as to interest.
Award affirmed.
Cases cited
- McMaster v. State 103 N. Y. 547 p. 544
- Clark v. Mayor of New York 4 N. Y. 338 p. 546, p. 555
- Fallon v. Lawler 102 N. Y. 228 p. 546
- United States v. Speed 8 Wall. 77 p. 546, p. 557
- McCollum v. Seward 62 N. Y. 316 p. 546
- Wilson v. Randall 67 N. Y. 338 p. 547, p. 550
- Swain v. Seamens 9 Wall. 254 p. 547
- Allen v. Robinson 2 Barb. 341 p. 547
- Lawson v. Hogan 93 N. Y. 39 p. 547
- People ex rel. Reilly v. Johnson 38 N. Y. 63 p. 547
- Sweet v. Tuttle 14 N. Y. 465 p. 548
- Reynolds v. Garner 66 Barb. 310 p. 548
- Jackson v. Andrews 98 N. Y. 672 p. 548
- President, Directors & Co. of Rensselaer Glass Factory v. Reid 5 Cow. 587 p. 548
- Day v. New York Central Railroad 89 N. Y. 616 p. 548
- Lewis v. State 96 N. Y. 71 p. 548
- United States v. Smith 94 U. S. 214 p. 555
- White v. Miller 71 N. Y. 118 p. 557