Majority
Headnote
Where the parties to a contract stipulate for a payment in liquidation of damages by a party in default, if the damages are in their nature uncertain and incapable of exact ascertainment, and may be dependent upon extrinsic considerations and circumstances, and the amount is not, on the face of the contract, out of all proportion to the probable loss, it will be treated as liquidated damages.The appellant seeks to excuse the failure to perform his agreement and to be legally absolved from the pecuniary loss consequent thereupon, by invoking the application of an equitable rule which relieves from a penalty and from forfeiture, whenever performance has been rendered impossible by the act of God; by which expression he characterizes the storms and atmospheric disturbances, in the state of New York and elsewhere, which set in about March 12, 1888, and were popularly described as “ The Blizzard.” We do not think,, however, that this is a case for equitable relief, or for any such application of the rule referred to. By the original contracts, of the parties, default in completion of the houses, which were the subject-matter of their making, subjected the contractor to. the liability to respond to the owner, in a stim measured by the number of days of default and agreed upon between them to be in liquidation of all damages. When the default occurred the new contract, which followed, did not excuse the plaintiff,, or waive -his default, but, qn the contrary, was an agreement between the parties fixing what the amount of the sum due by way of liquidated damages would be upon a certain date, and stipulating that it should be due and owing them, if the contractor’s work still remained unfinished. The last agreement, has no further bearing upon this matter than to evidence the fact that the continuing default of the contractor was not excused, and that if he chose to litigate the question of an excuse by act of God, which his lawyer advanced, he was at liberty to do so. It was simply an agreement in settlement of the controversies which had arisen, but which left out of them for subsequent litigation the one question of what is there called the penalty. Whether the sum agreed between parties to be paid, in the event of a breach of some agreement is termed by them a “ penalty,” or “ liquidated damages,” is not controlling upon the question of construction. Their use of such words is not always conclusive as to their legal meaning..
In Lowe v. Peers (4 Burr. 2228, 2229), Lord Mansfield, and in Kemble v. Farren (6 Bing. 141), Tindal, C. J., discuss the subject. In Dakin v. Williams ( 17 Wend. 447 and 22 id. 201), Nelson, Ch. J., in the first report, and Chancellor Walworth, in the second, review the question in the light of the English and New Yorlc cases. (See also Hosmer v. True, 19 Barb. 106 ; Lampman v. Cochran, 16 N. Y. 275 ; Clement v. Cash, 21 id. 253; Little v. Banks, 85 id. 258.)
The result of an examination of cases is to confirm the idea-that it is difficult, if it is even possible, to lay down a general rule applicable to all the cases which arise, where parties have-undertaken to provide against a loss consequent upon a breach of an agreement. We may, at most, say that where they have-stipulated for a payment in liquidation of damages, which are-in their’ nature uncertain and unascertainable with exactness,, and may be dependent upon extrinsic considerations and circumstances, and the amount is not, on the face of the contract, out of all proportion to the probable loss, it will be treated as-liquidated damages.
In this case, in the last agreement, of March thirtieth, upon-which the plaintiff seems to rest, the use of the word “penalty”'
Hone of the features of a penal obligation are present, and the plaintiff should be held to his agreement. The damages were liquidated and the contract made no provision against the result of an interference with its performance, by the intervention of occurrences unforeseen and beyond the plaintiff’s ■control. Having contracted absolutely to complete the houses ■on or before a certain date, unforeseen contingencies, no matter ■of what nature, are not available to plaintiff as a defense to the ■exaction of damages. (Harmony v. Bingham, 12 N. Y. 99 ; Tompkins v. Dudley, 25 id. 275; Wheeler v. Ins. Co., 82 id. 543.)
The order reversing the judgment at Special Term and ordering a new trial should be affirmed, and, under the stipulation, judgment absolute is ordered for the respondent.
All concrn*.
Order affirmed and judgment absolute ordered for the; defendant on stipulation.
Cases cited
- Porter v. Smith 107 N. Y. 531 p. 233
- Fleischmann v. Stern 90 N. Y. 110 at 114 p. 233
- Tayloe v. T. & S. Sandiford 7 Wheat. 13 p. 233
- Colwell v. Lawrence 38 N. Y. 71 p. 233
- Spalding v. Rosa 71 N. Y. 40 p. 233
- Hyland v. Paul 33 Barb. 241 p. 233
- Merritt v. Earle 29 N. Y. 115 at 116, 117 p. 233
- Hubbell v. Von Schoening 49 N. Y. 326 at 331 p. 233
- Bagley v. Peddie 16 N. Y. 469 p. 233
- Hosmer v. True 19 Barb. 106 p. 235
- Lampman v. Cochran 16 N. Y. 275 p. 235
- Harmony v. Bingham 12 N. Y. 99 p. 236