Majority
Headnote
.The year within which, under the provisions of the Revised Statutes (1 R. S. 236, § 49), a claimant for damages for premises that shall have been appropriated to the use of a canal is required to file his claim or be forever barred from recovering compensation does not begin to run, as to lands permanently appropriated, until the quantity taken has been determined by the officers of the state and its boundary lines described on the maps they are authorized to make and file, or marked on the ground by monuments in such a manner that the owner has the means of ascertaining the quantity and boundaries.Prior to February 8,1878, the date of the appointment of the first superintendent of public works, the board of canal commissioners had the general care and superintendence of the- canals of this state, with power to appropriate, permanently or temporarily, lands necessary for their construction or maintenance. (Canst, art. 5, § 3, as amended in 1876; 1 B. S. 220, §§ 9, 16.)
The construction of the new Oneida Lake canal was authorized by chapter 934 of the Laws of 1867, pursuant to which it was afterwards built, and in the course of its construction
The record which "we are called on to review is a very unsatisfactory one. The statute regulating the practice of the Board of Claims provides: “ Upon the hearing of all claims before the board, the rule of evidence now prevailing in the courts of record of this state shall be observed, and the practice upon sucli hearing of claims and taking appeals from the final order or award made therein shall conform, as near as may be, to the practice now prevailing in the Supreme Court of this state, upon the trial of actions and upon appeal.” (Chap. 205, Laws 1883, § 11, as amended by chap. 60, Laws 1884.) Under this statute decisions of the Board of Claims should be in writing, signed by all or a majority of the commissioners, and separately stating the facts found and the conclusions of law, pursuant to the practice in the Supreme Court, as prescribed by sections 1010 and 1022 of the Code of Civil Procedure. Again, the eighth section of chapter 205 of the Laws of 1883, provides: “ § 8. On the termination of ahearingbefore the board of claims, the commissioners, or any two of them, shall make and assign (sign) the award of the board, which shall contain the names of the persons interested, the names of the attorneys, if any, who appeared for the claimant, or by whom the claim was made, the amount allowed the claimant, if any, and if it be a case where the state seeks to appropriate or has appropriated lands for public use, a description by metes and bounds
The final order or award contains no description of the lands appropriated, nor does it show what facts were deemed to be established by the evidence, nor is it signed by any of the commissioners, and this court is compelled to decide this appeal by an examination of the evidence, which is far from giving a satisfactory account of the proceedings taken by the state, when taken, or how much land the state claims to have appropriated, either permanently or temporarily.
It appears that October 23, 1867, it was resolved by the contracting board to build a new canal on a line laid down on the map theretofore prepared and then exhibited by the state engineer and surveyor, and December 18, 1867, the construction of the canal was let. The lines showing the permanent location of the land taken for its construction were partly established and marked on the ground by stakes in 1868, but this work was not completed until 1870. It does not appear when, if ever, the lines were established on the claimant’s farm. The work of constructing the canal was begun in Hay, .1868; was continued until October or December of that year, when it was suspended; was recommenced in June, 1874, and continued until January, 1875, when it was susj)ended for a time; was afterwards resumed, and was in progress at the time of the hearing of this claim by the board of canal appraisers in September, 1877.
We think the year within which the claimant was, by the forty-ninth section of article first, title nine, chapter nine of the first part of the Revised Statutes (1 R. S. 226, § 49), required to file his claim or be forever barred from recovering compensation, does not begin to run, as to lands permanently appropriated, until the qiiantity lias been determined by the officers of the state and its boundary lines described on maps
The award should be reversed and a rehearing granted before the Board of Claims, with costs to abide the event.
All concur.
Award reversed and rehearing granted.
Cases cited
- Carpenter v. City of Cohoes 81 N. Y. 21 p. 191
- Rexford v. Knight 15 Barb. 627 p. 191
- Corkings v. State 99 N. Y. 491 at 492, at 499 p. 191, p. 195
- Mark v. State 97 N. Y. 572 p. 192
- In re the Claim of Chaphe 117 N. Y. 511 p. 192
- Lewis v. State 96 N. Y. 71 p. 192
- Gahn v. Niemcewicz 11 N. Y. 312 p. 192
- Turrell v. Norman 19 Barb. 263 p. 192
- Birdsall v. Cary 66 How. Pr. 358 p. 192
- Broeck v. Sherrill 71 N. Y. 276 p. 192