Majority
Headnote
"Where a building contract provides that in case the contractor refuses or neglects to supply a sufficiency of materials or workmen, the owner may finish the work and deduct the expense so incurred from the contract price, and the owner avails himself of this privilege, in determining in an action to recover a balance alleged to be due, as to whether there has been a substantial performance, the contractor is entitled to the benefit of the work so done; the owner may not assert a forfeiture in respect to the deficiency so supplied by him, but is simply entitled to deduct the expense incurred.The acceptance of the order given by the Wadsworths to the plaintiffs upon the defendant was in terms conditional, and payment made dependent upon completion of the building and on the architect’s certificate. And by the contract such certificate was made a condition precedent to the right to any payments upon the work. Flo such certificate was obtained by the Wadsworths or. the plaintiffs in support of the demand for payment of the amount of the order or any portion of it, but upon application made to him FTovember 29, 1887, by one of the plaintiffs for a final certificate on the work, the architect put his refusal in writing of that date as follows:
“ Mr. F. P. Crouch — Replying to your request for final certificate on the Gutmann contract, I regret that there are so many things which are imperfect, that I am prevented from certifying to the satisfactory completion of the work under the contract. JAMES G. CUTLER,
“ Architect.”
The parties to the contract, by it made the architect’s certificate essential evidence of performance and of the right to payment founded upon it, and unless its production was in some manner waived, or its necessity otherwise overcome or obviated, the failure to obtain it constituted a bar to recovery by the plaintiffs. (Smith v. Brady, 17 N. Y. 173 .) In support of his conclusions, the referee found that the contractor Stauchen substantially performed the work on his part, and that on his adjustment with the defendant there was deducted $199.55 for defective mason work, and $1,300 for delay from
The referee further found upon the subject of defects in the carpenter work, that when the Wadsworths stopped work in the latter part of July, 1887, there were defects in their work in the following respects: “ In the bath-rooms, in the hardwood floors, pieced casings on windows in rear of building, defective hand-rail on front stairs, moulding in some portions of the building not properly smoothed before oiling, imperfect painting on the front of the building.” And further, that on the defendant’s three days’ notice provided by the contract and given on July 30, 1887, to the contractor to provide materials and workmen to complete the work, the defendant employed to remedy the defects one Pike, a carpenter, whose work upon the building was “ fixing the doors so they would latch and windows so they would slide, fixing covers on wash trays, fixing back stairs, being defects principally due in part to poor workmanship and in part to settling of the building. That the front of the building was repainted by men employed by Pike, thfe original job having been a poor one showing spots, and in some cases when Pike’s repairing made it necessary, additional coats of oil were put on the building in the interior.” And that the fair value of the labor and materials necessary to remedy and make good- the defective and omitted work covered by the specifications performed by Pike and his painter was $439.29.
The referee then proceeded by his findings to state that the
While the condition of the carpenter work when the Wadsworths left it in July, was such as to indicate defects and omissions, the correction of which would cost $656.29, it may be observed that such defects upon such estimate of the cost to the amount of $439.29 were remedied through the action of the defendant taken pursuant to his right reserved by the contract, to furnish materials and workmen to proceed with the work and charge the expense to the contractor upon the failure of the latter to do it on -three days’ notice to him to that effect. This work having been done by the defendant in the exercise, by his election, of such right, he cannot effectually assert forfeiture in respect to the deficiency so supplied, but the Wadsworths were entitled to the benefit of the work
The amount of damages.for want of strict performance was not such as to necessarily defeat the claim of substantial performance. (Phillip v. Gallant, 62 N. Y. 256 .) The cost of completion of work by remedying defects or supplying omissions in it to meet the requirement of a contract may be so great as to preclude the conclusion of substantial performance.
In Flaherty v. Miner ( 123 N. Y. 382 ), where the damages allowed were upwards of seventeen per cent of the contract price, the court suggested (without deciding) that if it had appeared “ without dispute that such a substantial portion of the work remained undone and objection had been properly taken, it may well be that the plaintiff could not have recovered upon the theory of a substantial performance.” It is suggested that if was not within the province of the architect’s duty to make deductions for defective work, or to determine what less than exact or full completion of the work, according to the contract, was such substantial performance as to permit recovery. That may be true in such sense that the refusal of a certificate may, on his part, have been without purpose to deny to the contractor that which he may have been entitled, and yet it may be determined on trial that the ' certificate was unreasonably withheld. The considerations of good faith on the part of the contractor bearing upon the
In Phillip v. Gallant ( 62 N. Y. 257 ), where the contract price of the work was §865.11 and the damages allowed for defective work was §75, the question of substantial performance was held to be one of fact, and the amount of damages was not treated as inconsistent with the conclusion to that effect. And see Van Clief v. Van Vechten (42 N. Y. S. R. 736).
The rule of substantial performance should not be extended beyond the purpose in view when the relaxation of the strict performance was adopted, which was founded upon equitable considerations in furtherance of justice, and made applicable to cases of honest intention of contractors to fairly perform their contracts, and who shall in the main have done so, with only slight defects or omissions inadvertently and unintentionally caused and appearing in the work. The present is a case not free from difficulty in that respect. Hot less so in the extent of the deficiencies than in the character of some of them. The fact that the windows in the rear of the building were not in align with the doors and were differently cased, were features not in accordance with the specifications, and would seem to have been apparent to observation reasonably diligent. Yet the Wadsworths testify to the effect that they supposed that they had completed the carpentry work according to the contract. The inference was permitted, as the result showed, that they may have placed too much reliance upon the care and skill of their employes. And it does not appear that their attention was by the defendant or his architect called during the progress of the work to those defects in such windows and casings, although payments were from time to time made upon the certificates of the latter to those contractors The referee, however, was by stipulation of the
Dissent
There were some other matters made the subject of controversy, and to which the defendant’s exceptions call attention, but upon careful examination of the record it is found that none of the findings or refusal to find of the referee are wholly unsupported by evidence. Hone of the exceptions seem to have been well taken.
The judgment should be affirmed.
(dissenting). The prevailing opinion goes further than any previous judgment has gone in the direction of holding that the question of “ substantial performance ” is always one of fact.
Generally the question -is one of fact, but so called performance may be so partial or defective that it is the duty of the
The tendency, called equitable, of courts to relieve persons , from the performance of engagements deliberately entered < into, and in legal effect to make for litigants new contracts which they never entered into, and which it cannot be supposed they ever would have entered into, has been and is being carried to a length which cannot be justified in reason.
I think the judgment should be reversed and a new trial granted, with costs to abide the event.
All concur with Bradley, J., except Follett, Oh. J., Yank and Lakdon, JJ., dissenting.
Judgment affirmed.
Cases cited
- Smith v. Brady 17 N. Y. 173 p. 50
- Glacius v. Black 50 N. Y. 145 p. 51
- Murphy v. Buckman 66 N. Y. 297 p. 54
- Nolan v. Whitney 88 N. Y. 648 p. 54
- Phillip v. Gallant 62 N. Y. 256 p. 54
- Flaherty v. Miner 123 N. Y. 382 p. 54