Majority
Headnote
' 1. Municipal Contract — Damages for Delay in Completion of Work. Where a contract for a municipal improvement requires the contractor to pay a certain sum a day, as liquidated damages, for each day the completion of the work is delayed beyond a specified date, the municipality will not be allowed to retain from the contractor a substantial sum, under the guise of liquidated damages for delay, when in fact only nominal damages have been sustained.In October, 1884, one Keenan entered into a contract with the defendant to construct a sewer, and began work upon it; but after a short time, for reasons that are of no moment upon this review, he refused to go on under his contract and steps were thereafter regularly and duly-taken, with the result that a contract was entered into between the city and this plaintiff for the construction of the sewer.
The ordinance authorizing the making of the contract, among other things, provided that nothing therein contained should “ be held to create any liability on the part of the city of Albany to pay for the expense of the work and improvement therein authorized to be done, or any part thereof, except to the extent that such expense should be collected by the city of Albany from assessments levied therefor upon the houses and lots, vacant lots and franchises intended to be benefited by such work and improvement, according to law.” The contract contained the following provision: “ Payment for the above-mentioned work is not to be required or to be due until the same shall have been fully completed according to the intent and meaning of the agreement and until the lapse of thirty days after the apportionment and assessment of the expense of the same shall have been approved and,confirmed by the board of contract and apportionment of said city, according to the statute in such case made and provided, and until the same shall have been collected by the chamberlain from said assessments.” The plaintiff contracted to finish the work on or before the 1st day of July, 1886, and gave a bond in the penal sum of 025,000, conditioned for the faithful performance of the contract. He failed to complete the work by
As to the question of liquidated damages, so called, the referee in his report found that the work was substantially completed on time, and that at the end of fourteen days thereafter all the work that the plaintiff was called upon by the contract to do, was done, as it was not his duty to clean the sewer. The Appellate Division put its affirmance of the judgment entered upon such report upon another ground. It held that the evidence repelled the presumption of damages which ordinarily obtains, and, indeed, conclusively established that the city sustained no damages whatever, other than nominal damages, and, hence, that the sum specified in the contract, notwithstanding it is called liquidated damages, is clearly a forfeiture, and its enforcement would have the quality of extortion. The position taken by the learned justice who wrote the opinion of the Appellate Division, that the defendant will not be allowed to retain a substantial sum of money under the guise of liquidated damages, when in fact only nominal damages have been sustained, cannot well be questioned ; but it is insisted that the question was not raised upon the trial; had it been, it is said it cannot be known but that the city would have been able to prove actual damages. It would seem that the question was necessarily up for decision before the referee. . The plaintiff sought to recover of the defendant the sum that it had deducted from the assessment, and which- it claimed the right to deduct on the ground that, under the contract, it was entitled to such sum as liquidated damages; the city’s claim of right to retain that money, or
Upon the motion to dismiss the complaint, the counsel who tried the cause presented as one of his grounds the following: “That the proofs show that the plaintiff forfeited to the defendant the sum of §6,900, sued for by him in this action, fdr the reason that his proof shows that he did not complete all of the work and furnish all of the materials required by the contract in question to be done and furnished by him within the time required by said contract, as extended by the defendant upon the request of the plaintiff.” The motion to dismiss at the close of the case was renewed upon this ground among others. It thus appears that the defendant elected to defend the action as to this item upon the theory that it was entitled to the entire sum of §6,900, without reference to the actual damages sustained by it, because that sum was nominated in the contract; if it could have shown that the city actually sustained damages by reason of the delay for 138 days, it omitted to do it, for, as the record stands, it appears that the city had full and complete use of the sewer during all that period of time.
The learned counsel for the appellantjEurther urges that the defendant acted simply as the agent of the owners of the property liable to be assessed to defray the expense of the work, and was legally responsible only for the payment of the amount collected from the assessment levied for that purpose ;• that if the defendant- refused or neglected to make a proper and sufficient assessment for such purpose, or refused to take the necessary proceedings for the collection thereof, the plaintiff should have proceeded by mandamus and compelled the defendant to take such action ; that no action to recover damages is maintainable against the defendant. ' His brief contains an exhaustive discussion of the question, some phases of which have been considered by the. court in Hunt v. Utica ( 18 N. Y. 442 ); Reilly v. Albany ( 112 N. Y. 30 ); People ex rel. Ready v. Syracuse ( 144 N. Y. 66 ), and Weston v. Syracuse ( 158 N. Y. 274 ). But the counsel who tried the cause seems
The judgment should he affirmed, with costs.
All concur.
Judgment affirmed.
Cases cited
- Hunt v. City of Utica 18 N. Y. 442 p. 635, p. 640
- King v. City of Brooklyn 42 Barb. 627 p. 635
- McCullough v. Mayor of Brooklyn 23 Wend. 458 p. 635, p. 636
- Baker v. City of Utica 19 N. Y. 326 p. 635
- Sherman v. Boyce 15 Johns. 443 p. 635
- People ex rel. Williams v. Haines 49 N. Y. 587 p. 635, p. 636
- Smith v. Brady 17 N. Y. 173 p. 635
- Phelan v. Mayor of New York 119 N. Y. 86 p. 635
- Byron v. Low 109 N. Y. 291 p. 635
- Wasmer v. Delaware, Lackawanna & Western Railroad 80 N. Y. 212 p. 635
- Little v. Banks 85 N. Y. 258 p. 636
- Noyes v. Phillips 60 N. Y. 408 p. 636, p. 637
- Ward v. Hudson River Building Co. 125 N. Y. 230 p. 636
- Tode v. Gross 127 N. Y. 480 p. 636
- Bagley v. Peddie 16 N. Y. 469 p. 636
- Cotheal v. Talmage 9 N. Y. 551 p. 636
- Reilly v. City of Albany 112 N. Y. 30 p. 636, p. 640
- Sage v. City of Brooklyn 89 N. Y. 189 p. 636
- McCormack v. City of Brooklyn 108 N. Y. 49 p. 636
- Donnelly v. City of Brooklyn 121 N. Y. 9 p. 636
- Genet v. City of Brooklyn 99 N. Y. 296 p. 636
- Wright v. Reusens 133 N. Y. 298 p. 636
- Russell v. Allerton 108 N. Y. 288 p. 636
- Nicoll v. Sands 131 N. Y. 19 p. 636
- In re Freel 148 N. Y. 165 p. 636
- Brady v. Mayor 132 N. Y. 415 p. 636
- Weeks v. Little 89 N. Y. 566 p. 636
- Dannat v. Fuller 120 N. Y. 554 p. 636
- Richards v. Edick 17 Barb. 260 p. 636
- Colwell v. Lawrence 38 N. Y. 71 p. 637
- Staples v. Parker 41 Barb. 648 p. 637
- Beale v. Hayes 5 Sandf. 640 p. 637
- Mulholland v. Mayor of New York 113 N. Y. 631 p. 637
- Weston v. City of Syracuse 158 N. Y. 274 p. 640