Majority
Headnote
1. Contracts — Liquidated Damages. Where the language of a provision specifying the amount of damages to be paid in case of the breach of the contract is clear and explicit to that effect, the amount is to be deemed liquidated damages, when the actual damages contemplated at the time the agreement was made are in their nature uncertain and unascertainable with exactness, and may be dependent upon extrinsic considerations and circumstances, and the amount is not, on the face of the contract, out of all proportion to the probable loss.The question presented by this appeal is whether the sum which the plaintiff’s assignor promised to pay the defendants for each day’s delay in completing the building, after expiration of the period stipulated, is in the nature of a penalty or of liquidated damages. This question depends upon the intention of the parties, which is to be gathei’ed from the language used in making the contract, read in the light of the circumstances surrounding them at the time. (Little v. Banks, 85 N. Y. 258 , 266; Kemp v. Knickerbocker Ice Co., 69 N. Y. 45 , 58; Colwell v. Lawrence, 38 N. Y. 71 , 74.) The words of the contract are that the sum of fifty dollars shall be paid by the plaintiff’s assignor to the defendants for each day, after the date named for performance, “ as, fixed, settled and liquidated damages ” which the defendants “ will sustain by reason of the failure * * * to complete said building ” within the time specified.
If this language is given its ordinary meaning the parties have not only defined the sum promised to be paid, as liquidated damages, but have expressly covenanted that it is the amount of damage which the defendants would sustain in consequence of the delay, thus limiting recovery to the sum named, even if the actual damages should greatly exceed it.
The plaintiff, however, contends that the language of the agreement is not conclusive, and that these words should not be given their ordinary meaning, because the per diem payment is so excessive as to shock one’s sense of justice and to
These authorities show that the courts have struggled hard against the apparent intention of the parties, in order to relieve the one in default from an improvident bargain. It is, however, the law of this state, as settled by this court, that where the language used is clear and explicit to that eifect, the amount is to be deemed liquidated damages when the actual damages contemplated at the time the agreement was . made “ are in their nature uncertain and unascertainable with exactness, and.may be dependent upon extrinsic considerations and circumstances, and the amount is not, on the face of. the contract, out of all proportion to the probable loss.” ( Ward v. Hudson River Building Co., 125 N. Y. 230 ; Little v. Banks, 85 N. Y. 258 ; Kemp v. Knickerbocker Ice Co., 69 N. Y. 45 , 57; Clement v. Cash, 21 N. Y. 253 ; Baglie v. Peddie, 5 Sandf. 192 ; S. C., 16 N. Y. 469 ; Dunlop v. Gregory, 10 N. Y. 241 ; Cotheal v. Talmage, 9 N. Y. 551 .)
We thus reach the ultimate question, whether the damages within the contemplation of the parties when they made the contract in question, are so uncertain as to be diffiult of ascertainment, and if so, whether they are so grossly excessive as to be out of all proportion to the probable loss ?
In making said contract the defendants provided for the lease' of a building, to be erected, when there was less than six months’ time within which to complete it, and they needed
Is the sum agreed upon out of all proportion to the probable loss, under the circumstances known to the parties when the agreement was made? Is it so disproportionate that one “ would start at the mere mention of it,” which is the test laid down in Cotheal v. Talmage (supra) ? Of course the parties did not contemplate a long delay in completing the building or neither of them would have entered into the contract at all. We cannot say, as matter of law, that fifty dollars a day for the absolute suspension of a prosperous manufacturing business, for a few days, at the busiest season of the year, accompanied by a temporary removal to other quarters, or a forcible removal to. the street, is so excessive as to shock one’s sense of justice. It. is less in proportion to the actual damages than the amounts sustained in several of the cases cited. Indeed, the actual damages might exceed it and the covenant thus prove a protection to the one in default.
We think the learned trial judge erred in directing a verdict for the plaintiff, and that the judgment below should be reversed and a new trial granted, with costs to abide the event.
All concur.
Judgment reversed, etc.
Cases cited
- Bagley v. Peddie 5 Sandf. 192 p. 50, p. 51, p. 52
- Little v. Banks 85 N. Y. 258 at 266 p. 50, p. 51, p. 52
- Holmes v. Holmes 12 Barb. 137 p. 50
- Smith v. Smith 4 Wend. 468 p. 50
- Clement v. Cash 21 N. Y. 253 p. 50, p. 52
- Cotheal v. Talmage 9 N. Y. 551 p. 50, p. 52
- Dunlop v. Gregory 10 N. Y. 241 p. 50, p. 52
- Ward v. Hudson River Building Co. 125 N. Y. 230 p. 50, p. 51, p. 52
- Pettis v. Bloomer 21 How. Pr. 317 p. 50
- Dodds v. Hakes 114 N. Y. 260 p. 51
- Spencer v. Tilden 5 Cow. 144 p. 51, p. 52
- Beale v. Hayes 5 Sandf. 640 p. 51, p. 52
- Colwell v. Lawrence 38 N. Y. 71 at 74 p. 51
- Williams v. Dakin & Bacon 22 Wend. 201 p. 51
- Kemp v. Knickerbocker Ice Co. 69 N. Y. 45 at 58, at 57 p. 51, p. 52
- Jackson v. Baker 2 Edw. Ch. 471 p. 52
- Niver v. Rossman 18 Barb. 50 p. 52
- Bagley v. Peddie 16 N. Y. 469 p. 52