Majority
Headnote
New York, City of — Construction of Paving Contract—General Covenant to Maintain and Repair Qualified by a Specifica- ' tion. A provision in a contract for paving certain streets in the city of New York which provided for the execution of the work in accordance with specifications therein referred to, requiring the contractor to “maintain the said work in good condition to the satisfaction of the commissioner of public works * * * for the period of fifteen years from the final completion and acceptance thereof; all the said work to be done in the manner and under the conditions hereinafter specified,” and that the entire work will be completed “ to the satisfaction of the commissioner of public works, and in substantial accordance with said specifications,” should be read in connection with a specification providing “that if, at any time during the period of fifteen years from the date of the acceptance by said commissioner of the whole work under this agreement, the said work, or any part or parts thereof, or any depression, bunches or cracks shall, in the opinion of the commissioner, require repairs, and the said commissioner shall notify” the contractor “to make the repairs so required by a written notice served on the contractor, either personally or by leaving said notice at his residence or with his agent in charge of the work,” the contractor “shall immediately commence and complete the same to the satisfaction of the said commissioner; ” and when so read requires the contractor to make only such repairs as he should be required to make pursuant to the written notice served upon him in the manner specified.The single question presented by this appeal arises upon the construction of the “ maintenance ” clause of the contract upon which this action is brought. On the 26th of December, 1890, the Matt Taylor Paving Company entered into a contract with the defendant to pave with asphalt the carriageways of Sixty-sixth and Sixty-seventh streets from Lexington avemie' to Third avenue in the borough of Manhattan, city of Mew York. The contract provided for the payment by the defendant to said contractor of 70 per cent of the contract price within 30 days after the completion of the work and the acceptance of the same by the commissioner of public works .and the balance thereof as follows: “ Three per cent of the whole amount of money accruing to the said party of the second part (the contractor) on the expiration of the .sixth year, and a like further sum'of three per cent upon the expiration of each succeeding year thereafter until the whole, or as much as remains due upon said contract price shall be paid, should the party of this second ■partperform the work stipulated under section 13a of this agreement.” The installment of 70 per cent of the contract price, which became due upon the completion of the work and the acceptance thereof by the commissioner of public works, has been paid ; several installments of three per cent have also been paid, and 15 per cent still remains unpaid. This action was brought by the plaintiff, as receiver of the said contracting company, to recover the amount unpaid.
The contract, after providing for the execution of the work in a good and substantial manner in accordance with the specifications therein referred to, requires the contractor to “ maintain the said work in good condition to the satisfaction of the commissioner of public works * * "x" for the ¡period of fifteen years from the final completion and acceptance thereof; all the said work to be done in the manner and under the con
Specification 22 of the contract provides that the party of the second part “ shall not be entitled to demand or receive payment for any portion of the aforesaid work or matei’ials until the same shall be fully completed in the manner set forth in this agreement, and such completion shall be duly
The complaint alleges the full performance of the contract. The answer denies this allegation of the complaint and sets forth, as a separate and distinct defense, the provisions of the contract above quoted. The answer further alleges that at various times-during the years from 1894 to 1901 inclusive the said work became out of repair and required that repairs should be made thereto; that at various times during said years the contractor was notified in writing to make such repairs; that he neglected and refused to make the same, and that said commissioner of public works caused said repairs 'to be made by other parties. At the trial the plaintiff, after making the formal proofs relating to his appointment as receiver, his qualification as such and his authority to sue, offered in evidence the contract referred to, the certificate of the defendant’s engineer showing the completion of the work in accordance with the terms of the contract, and then rested. Thereupon defendant’s counsel moved to dismiss the complaint on the ground that the facts proven do not constitute a cause of action against the city. This motion was granted and plaintiff excepted.
This decision of the trial court and the affirmance by the Appellate Division of the judgment entered thereon are based on the ground that under the provisions of the contract “it was the duty of the contractor to maintain the pavement in good condition without any notice from the commissioner, and it was also his duty to make the repairs specified in section 13a upon notice from the commissioner,” and that plaintiff could not establish a cause of action without showing affirmatively that he had maintained said pavement in good order for a period of fifteen years after its acceptance by the defendant. Although the question presented is a narrow one, we are inclined to differ from the learned courts below in the
When the plaintiff rested he had made out a prima facie case. The burden of proof was not shifted to the defendant, but the plaintiff had proven all that was essential unless, and until, the defendant introduced some evidence which required the plaintiff to prove more. We are of opinion, therefore, that it was error to dismiss the complaint.
The judgment should be reversed and a new trial granted, with costs to abide the event.
Parker, Ch. J., Gray, Bartlett, Haight and Cullen, JJ., concur : O’Brien, J., absent.
Judgment reversed, etc.
Cases cited
- Graves v. Deterling 120 N. Y. 447 p. 475
- MacKnight Flintic Stone Co. v. Mayor of New York 160 N. Y. 72 p. 475
- Gilliam v. Brown 116 Cal. 454 p. 475
- Dady v. O'Rourke 172 N. Y. 447 p. 475, p. 480
- Holmes v. Hubbard 60 N. Y. 183 p. 475
- Norton v. New Amsterdam Gas Co. 69 App. Div. 10 p. 475
- New England Iron Co. v. Gilbert (Metropolitan) Elevated Railroad 91 N. Y. 153 p. 475
- Manke v. People 74 N. Y. 415 p. 475
- Wells v. Alexandre 130 N. Y. 642 p. 475
- People ex rel. North v. Featherstonhaugh 172 N. Y. 112 p. 475
- French v. Barber Asphalt Paving Co. 181 U. S. 324 p. 475