Majority
Headnote
Municipal contract — claim for extra work — provisions of contract examined and held that common council reserved power to control and reject claims for extra work even though such work be ordered by city engineer.Plaintiff’s assignors made a contract with the defendant to furnish labor and materials necessary for the construction of a sewage disposal plant for the sum of $135,825. The work was completed and in this action brought to recover compensation the trial judge directed a verdict for the sum of $30,093.01, which was indisputably due on said contract. Plaintiff complains because it was not also permitted to have the jury pass upon a further demand for $22,324.33 alleged to be due for extra, or as counsel prefers to designate it, additional work and material. Its claim in respect of this further alleged balance is that defendant’s engineer in charge of the work during the prosecution thereof ordered certain changes to be made in the specifications which increased the cost of work and materials in the sum of $29,236.64, and that against this aggregate increase there were ordered deductions from contract
Aside from establishing the value of -the additional work and material claimed to have been thus furnished, the burden rested upon plaintiff to prove in the face of defendant’s denial thereof, first, that there was incorporated in the contract a clause permitting alterations in contract specifications during the progress of the work; second, that this clause permitted the engineer in charge of the work to order the changes, or, in lieu of the last, third, that the common council of defendant ratified the alterations after they were made. The clause thus involved reads as follows: “ If, during the progress of the work, any minor changes or alterations in details, quantities or methods of the work may be decided upon by the engineer, such changes, if duly authorized, will be carried into effect by the contractor, the cost of the work to be added to or deducted from the contract price, as the case may be. ”
As has Tpeen indicated, there is at the very outset a dispute whether this clause was ever incorporated in the contract. An examination of the rather voluminous evidence, however, leads us to believe that a jury would have had a right to say that it was thus incorporated, and that conclusion brings us to a consideration of its meaning, the principal question being whether under its terms defendant’s engineer in charge of the work was authorized to order alterations in the performance of the contract, as was in fact done, or whether it was necessary that such alterations should be authorized by defendant’s common council.
An examination of the clause simply by itself leads us to think that it was not thereby intended to empower the engineer to authorize changes. Its provision is, “ If, during the progress of the work, any minor changes or alterations * * * may be decided upon by the engi
But it is appreciated that this reasoning is not conclusive and that an argument may be made leading to an opposite conclusion, and, therefore, in addition to the consideration of the language of the clause itself, there will be applied to its interpretation certain arguments arising from its general purpose and scope and from other provisions in the contract and which do quite conclusively demonstrate I believe that the provision should not be construed as asked by plaintiff.
This clause was put in the contract solely for the benefit of the municipality and not for the advantage of the contractor. It was placed there for the purpose of enabling
We are all well aware that it is the constant effort of municipalities to so frame their contracts that they shall not be subjected to demands for extra work and material based upon orders given by some subordinate official in charge of or connected with the work. The contract before us is no exception to this rule, for it contains a clause that “bio claim for extra work shall be considered
If plaintiff’s interpretation of the clause which we have been considering is correct the provision last quoted has been entirely nullified for the engineer in charge has been enabled to order extra work amounting to $29,000. Of course if the defendant which prepared the contract has deliberately or carelessly nullified the clause prohibiting claims for extra work on orders given simply by the engineer, by a subsequent clause allowing him to order such work under the form of alterations, it ought to suffer the consequences. But in accordance with perfectly familiar principles of interpretation we ought not to give such a construction to the contract if it can fairly be avoided. On the other hand, it is our duty to assume that the contract was prepared with care and intelligence and to adopt a construction which will give such meaning to each provision as will be in harmony with that of the other one. This result is readily and reasonably accomplished by interpreting the words “ when duly authorized,” ambiguous perhaps when standing alone in the clause relating to alterations, as requiring authority from the common council. We then have a contract which is consistent throughout and which secures to the municipality the protection and advantages which we must assume were intended. It has the privilege of making alterations if the engineer decides them to be desirable. But by reserving to the council the power to authorize these changes after they have been recommended by the engineer it retains its control of claims for extra work and preserves the specific prohibition in the extra work clause against the creation of such claims by orders of the engineer in charge of the work.
Although we thus conclude that the contract required that extra work must be authorized in advance by the common council, it is assumed that the common council might offset the omissions thus to do by ratifying the alterations after the work had been performed, and it is urged by the plaintiff that this was done in this case. An examination of the record, however, fails to disclose any evidence which in our judgment would have permitted the jury to say that the common council, with that full knowledge necessary to a ratification, approved the changes in the contract’and the performance of the extra work for which the plaintiff now seeks compensation. In the final resolution adopted by that body it did make an allowance of a certain amount on account of these items, but this was plainly done for the purpose of compromise and settlement and did not amount to a ratification.
I think the judgment appealed from should be affirmed, with costs.
Chase, Cardozo and Seabury, JJ., concur; Willard Bartlett, Ch. J., Collin and Hogan, JJ., dissent.
Judgment affirmed.
Cases cited
- Gillet v. Bank of America 160 N. Y. 549 p. 511
- Imperial Shale Brick Co. v. Jewett 169 N. Y. 143 p. 511
- Halpin v. Insurance Co. of North America 120 N. Y. 73 p. 511
- Borough Construction Co. v. City of New York 200 N. Y. 149 p. 511
- Woodruff v. Rochester & Pittsburgh Railroad 108 N. Y. 39 p. 511
- Bradley & Currier Co. v. Pacheteau 175 N. Y. 492 p. 511
- Langley v. Rouss 185 N. Y. 201 p. 511