Majority
Headnote
New York city — board of education a corporation separate and distinct from city — section 149 of charter, providing for adjustment of claims against city, and section 261, prohibiting prosecution of claim until thirty days after presentation to comptroller, do not apply to claims against board of education — power of audit rested in board of education — when action of board of education effective as audit of claim — when clause in contract permitting extension of time for completion of work may not be invoked to defeat claim for damage to contractor by reason of “delay ” arising from fault of others — arrangement for completion of work not a new contract — agreement to pay additional expense occasioned by delay not grant of extra compensation within prohibition of Constitution.October 25th, 1915, relator entered into a contract with the board of education of the city of New York, through its committee on buildings, for the installation of a heating and ventilating apparatus in Evander Childs High School, borough of The Bronx, New York city, the same to be completed within one hundred twenty days.
Due to defaults of contractors having in charge the construction of the building, relator was prevented from proceeding with the work under its contract within the time prescribed therein, and for a period of upwards of two years subsequent thereto. About June, 1918, the relator still deprived of opportunity to complete its contract, appreciating that the continued defaults on
July 3d, 1918, the vice-president of the board of education addressed a communication to the attorney for relator in which he stated that no disposition existed on the part of the board of education to treat the situation other than with a spirit of fairness to relator, but in so doing it was essential that the board should act with caution so as to preserve its rights against the sureties of defaulting construction contractors, further that he was prepared to submit a resolution to the board of education reciting the facts and complications that had arisen, providing for a continuation of the work by the relator under the terms of the then contract until completion, that the board of education acknowledged that the relator would have a claim for extra expenses incidental to the carrying out of the contract, the amount of which was not definable at that time, “ said extra expenses arise because of certain delays and the enhanced prices of labor and materials due to present day extraordinary conditions;” that' upon completion of the work to be performed under the existing contract the board of education will entertain a claim in detail and settle the same either (1) by agreement, (2) by arbitration, or (3) by judicial decision on agreed state of facts,. “ íf you will assent I will offer the requisite resolution.”
Upon receipt of such communication relator indorsed upon the same its acceptance of the terms proposed and
Relator thereupon resumed work under its contract and fully completed the same in May, 1920, notwithstanding additional delay caused by defaults of construction contractors, and thereupon employed two several certified public accountants to make an exami
The statement prepared by the accountants fixed the total direct cost to relator $105,480.69, plus overhead of $18,986.52, or a total of $124,467.21, and added thereto as a profit for doing the work ten per cent, amounting to $12,446.72, making in the aggregate $136,913.93.
In June following, the board of education requested and relator furnished to it affidavits of the public accountants who had made the examination and audit for relator. Such affidavits made reference to the statement already made and further stated that the rates and charges for labor and materials agreed with the rates and charges appearing on the payrolls, records and books of account of relator; that the rates charged for labor were the rates actually paid; that the prices charged for materials were the prices actually paid for the same; that no interest charges had been made for money used; that the profits and overhead expenses were reasonable. The affidavits were supported by an affidavit of the president of relator.
The claim was referred to the auditor of the board of education who made further inquiry as to correctness of the same. On July 12th one of the accountants made a further report to such auditor in which was contained a detailed statement of the wages paid by relator to various classes of mechanics during the various years from the time the work commenced in October, 1915, to the completion of the same in 1920. Accompanying the statement there was furnished the auditor of the board of education a detailed statement of rates of
On July 22d, 1920, the auditor of the board of education submitted a report to the president of the board, in which he recited at length all the foregoing facts in detail and submitted all documents relating thereto, and stated that from the evidence which the bureau had secured, it seemed that the total direct cost plus overhead was $124,467.21, and plus 10% for profit, $136,913.93, and
“ The bureau is -without any evidence which we can use to offset or deny the claim nor does it appear that it was the original intention of the Board of Education to do other than meet the situation in a fair and reasonable way.”
He suggested the settlement of the claim was a matter for determination by the board, either by allowance in full or by some method of compromise which might be agreed upon and acceptable to all parties concerned, and whatever sum. or allowance the board deemed proper to make he believed it would be necessary to submit to the board of estimate and apportionment a special estimate under subdivision 8, section 877, Education Law (Cons. Laws, ch. 16), to meet same.
July 30th, 1920, a resolution was adopted by the board of education wherein it requested the board of estimate and apportionment to “ appropriate the sum of $62,143.93, such appropriation or so much thereof as may be required to be used for the purpose of making payment to the Wells & Newton Company of New York of the amount found to be due and resulting from work performed at the Evander Childs High School, Borough of The Bronx, in accordance with the terms and stipulations contained in preambles and resolutions adopted by the Board of Education on July 3rd, 1918, the said preamble and resolutions continuing in performance a
The amount of $62,143.93 stated in the resolution was the difference between the sum of $136,913.93, herein-before referred to, and $74,770, theretofore paid to relator.
August 6th, 1920, when the board of estimate and apportionment considered the estimate and resolution of the board of education it had before it all documents relating to the facts, all affidavits, statements, computations, reports of the auditor of the board of education and of all proceedings had. On that day the board of estimate and apportionment appropriated, subject to the approval of the board of aldermen, the sum of $62,143.93, and after such approval authorized the comptroller to issue special revenue bonds, the proceeds to the amount of the par value or as much thereof as shall be required to be used to pay whatever claim may be found in favor of the Wells & Newton Company under the provisions of law relating to the audit .and payment of salaries and other claims by the department of finance. The resolution was unanimously adopted.
August 17th, the board of aldermen by a resolution of like tenor concurred in the resolution adopted by the board of estimate and apportionment. Such resolution of the board was approved by the mayor.
August 24th, 1920, a document entitled “ Payment Voucher and final certificate ” and then described as “Payment Voucher to Wells & Newton Company of New York, Avenue B and 17th Street, New York City, August 20, 1920. For work performed at the Evander Childs High School, Borough of Bronx as per the following resolution adopted by the Board of Education July 30th, 1920” (then followed a copy of the resolution) and followed by the figures $62,143.93, representing the amount of the voucher, was issued. Accompanying the
The certificate together with all documents therein referred to was filed in the office.of the comptroller on the same day, August 24th, 1920. Despite frequent requests made of the comptroller to draw a warrant for the payment of the account, no warrant was drawn. No objection was urged by the comptroller to the drawing of a warrant or legal reason urged for delay in issuance of the same. Upwards of four months having elapsed without action by the comptroller or heed given to the requests of relator this proceeding was instituted.
The application of relator for a writ of mandamus was granted at Special Term. The order of the Special Term was reversed by the Appellate Division and the writ denied as matter of law and not in the exercise of discretion. Relator appealed to this court.
Preliminary to a consideration of the argument of respondent in support of the decision of the Appellate Division adverse to the right of the relator to maintain this proceeding, attention should be called to the relations between the board of education and the city of New
In so far as material to be considered in the instant case, the board of education was by the Education Law clothed with power to purchase sites for and construct school buildings; to purchase apparatus, equipment and supplies necessary for the management of the schools; to provide such regulations and by-laws as may be necessary to make effectual the provisions of the Education Law; and the transaction of its business affairs and for the general management, operation, control, maintainance and discipline of the schools and other interests under its charge or direction; to perform such other duties and possess such other powers as may be required to administer the affairs placed under its control and management; to execute all powers vested in it and to promote the best interests of the schools and other activities committed to its care.
The powers conferred upon the board of education to administer the public educational system within the confines of the city of New York were exclusive. The grant of the same to the board of education negatives authority in the municipality to exercise like powers. As between the two corporate bodies the relation of principal and agent does not exist. (Titusville Iron Co. v. City of New York, 207 N. Y. 203 .) With the stated conclusions in mind, we pass to a consideration of certain objections to the granting of the relief prayed for by relator made by respondent and upon which stress was laid in the opinion of the Appellate Division.
The Appellate Division held the omission fatal; that the city of New York was a party to the proceeding and the real party in interest; that the act of the official required to be performed by the order of the Special Term directly affects the city; that the provision of the charter was a most salutary one providing the city’s chief financial officer with an opportunity of investigating all claims sought to be enforced against the city, giving him reasonable time for his investigation, and thus preventing imposition and fraud. I am in accord with the opinion of the Appellate Division in so far as it defines the general purpose to be attained by the section of the charter quoted. I am at. variance with the conclusion that the provision is applicable to the instant case.
The board of education alone was authorized to erect the school building, contract for the erection thereof and for the heating and ventilating apparatus therein. The contracts entered into were not contracts of the city but of the body corporate designated by the state for such purpose. Three several contractors for the erection of the school building defaulted. The right to recover damages against them severally for breach of contract was vested in the board of education, not in the city. Had the board of education breached its contract, action
In Gunnison v. Board of Education ( 176 N. Y. 11 , 17) we said: “ The only relation that the city has to the subject. of public education is as the custodian and depositary of school funds, and its only duty with respect to that fund is to keep it safely and disburse the same according to the instructions of the board of education. The city as trustee has title to the money, but it is under the care, control and administration of the board of education.”
The conclusion reached as to the applicability of section 261 applies equally to section 149 of the charter, relied upon by respondent, which latter section confers upon the comptroller power “ to settle and adjust all claims in favor of or against the corporation (the city) and all accounts in which the corporation (the- city) is concerned as debtor or creditor.”
A consideration of the statutory method to be adopted for providing means to carry on the system of public education in the city of New York, the custody of the fund and disposition to be made of the same is of importance.
Subdivision 7 of section 877 of the Education Law, as amended (Laws of 1917, chap. 786) in substance requires the board of education to file an estimate of moneys to be expended by it for school purposes, giving in detail items for salaries, maintenance, purchase of real property, erection of buildings, etc. If such estimate does not exceed four and nine-tenths mills on every dollar of assessed valuation of real and personal property in the
The money appropriated for school purposes is required to be held in two funds: A general fund for the payment of salaries of all employees in the supervising and teaching staff including the superintendent and associates, lecturers, etc. A special fund to embrace all moneys not comprised in the general fund. Then follows: “ The Board of Education shall administer all moneys appropriated or available for educational purposes in the city, subject to the provisions of law relating to the audit and payment of salaries and other claims by the department of finance.”
Subdivision 8 provides: “ A board of education may, to meet emergencies which may arise, submit a special estimate in which items for extraordinary expenses may be submitted to meet such emergencies. Such estimate shall contain a complete statement of the purposes for which the items are requested and the necessity therefor. The same method of procedure shall be followed in submitting such estimate and such estimate shall be subject to the same consideration and action as is required in the submission, consideration and action upon the regular annual estimate submitted by a board of education.”
Section 880 of the Education Law provides that all funds collected or received from any source for school purposes shall be paid into the treasury of the city and
The language quoted from subdivision 7, “ The board of education shall administer all moneys appropriated or available for educational purposes in the city, subject to the provisions of law relating to the audit and payment of salaries and other claims by the department of finance,” must be read in connection with section 880.of the Education Law which provides that school funds shall be disbursed only by the board of education, and clothes that body with power of audit.
The power vested in the board of education to administer the school fund is a grant of authority to that body to fix salaries of all employees of the board. Such salaries when fixed by the board are presumably embodied in the estimate filed with the board of estimate and apportionment. Upon receipt of a requisition from the board of education the comptroller is authorized to ascertain whether or not the requisition made upon him embraces charges against the education fund as disclosed in the record in his department relating to the board of education. If such requisition be found correct there
The Appellate Division attached importance to the fact that the board of estimate and apportionment and the board" of aldermen in . the resolutions respectively adopted, appropriated the sum of $62,143.93, “ or so much thereof as may be required,” and held that thereby the amount due to relator was left undetermined and also concluded that the action of the board of education was not effective as an audit of the claim of relator and such claim had never been audited. A consideration of the following facts leads me to a contrary conclusion. The resolution adopted by the board of education together with the voluminous report of the auditor of that body were transmitted to the board of estimate and apportionment on July 31, 1920. On August sixth the board
The board of education in the resolution adopted by it, after a complete examination of the claim of relator and of the numerous reports, computations and affidavits submitted to it, together with the report of the auditor of the board fixed the sum of $62,143.93 as the amount to be used for the purpose of making payment to the Wells & Newton Company of the amount found to be due, etc., and in support of and justifying the request for that sum it transmitted the report of its auditor embracing numerous facts upon which the board had acted. When the special estimate was presented to the board of estimate and apportionment under subdivision 8, section 877, Education Law, that board was empowered to exercise the authority conferred upon it in a consideration of the annual estimate filed with it by the board of education. The appropriation asked for being in excess of the four and nine-tenths mills appropriation to which the board of education was absolutely entitled, under
The respondent asserts that by reason of clause J ■ in the contract between the board of education and relator the latter may not assert a claim thereunder. The. clause so far as material provides:
a * * * if the work be delayed by any act or omission of the city * * * or any act or omission of any contractor to perform his work for the city, the committee on buildings or whoever is directed by this contract to make the certificate in reference to time, shall then extend the time for the completion of the
work for such period as the engineer in charge shall certify that the work has been delayed. No allowance whatever as damages or otherwise shall be claimed by or made to the contractor because of any such delays. * * * ”
Counsel for appellant asserts in his brief and the statement is not controverted by respondent that clause J as set out in the affidavit of respondent is incomplete. The contract, a voluminous document, was presented upon the argument but does not appear in the record. We may assume that counsel for appellant is correct in his statement that the clause in question confers power upon the committee on buildings to suspend the work only “ for the public interest.” Such limitation of power would certainly be reasonable.
We are asked to determine that under clause J of the contract the committee on buildings of the board of education, by reason of defaults of construction contractors, was authorized to extend the time of relator to complete its contract (not by reason of act or solicitation on the part of relator who was ready and willing to complete its contract within the time prescribed therein, one hundred twenty days from -October 25, 1915, but because of defaults of other contractors with the board of education), said extension covering a period of three years during which time relator would continue bound by the terms of its contract, while the board of education would not be liable to relator for any damage caused it by such delay, neither would relator be permitted to make a claim for loss occasioned by reason of delay. If the board of education possessed arbitrary power to suspend the Work of relator as it did for a period of three years, it could exercise the same power and continue the extensions for a period of ten years without liability on the part of the board for the loss sustained however serious by relator.
It is inconceivable that the relator or the board of
Counsel for respondent argues that the arrangement made between the board of education and relator whereby the latter agreed to resume work and complete its contract, operated as a new contract between the parties which could not be entered into without bids therefor, or if not a new contract and is to be construed as a modification of the existing contract the same was violative of article 3, section 28, of the Constitution of the-state. The Appellate Division in its opinion considered the two propositions adversely to the respondent and in such conclusion I concur. The board of education had
I recommend that the order of the Appellate Division be reversed and the order of the Special Term be reinstated, with costs to appellant in this court and the Appellate Division.
His cock, Ch. J., Cardozo, Pound, McLaughlin, Crane and Andrews, JJ., concur.
Ordered accordingly.
Cases cited
- Gunnison v. Board of Education 176 N. Y. 11 at 17 p. 126, p. 127, p. 137
- In re Freel 148 N. Y. 165 p. 127
- People ex rel. Rodgers v. Coler 166 N. Y. 1 p. 127
- Snyder v. City of New York 74 App. Div. 421 p. 127
- Titusville Iron Co. v. City of New York 207 N. Y. 203 p. 127, p. 135
- Smith v. Board of Education 208 N. Y. 84 p. 127
- Hirshfield v. Cook 227 N. Y. 297 p. 127
- Ackley v. Board of Education 174 App. Div. 44 p. 127
- Industrial & General Trust, Ltd. v. Tod 180 N. Y. 215 p. 127
- Russell v. Allerton 108 N. Y. 288 p. 127
- Gage v. City of New York 110 App. Div. 403 p. 127
- Horgan v. Mayor of New York 160 N. Y. 516 p. 127
- Simon v. Etgen 213 N. Y. 589 p. 127
- Johnson v. City of New York 231 N. Y. 564 p. 127, p. 144
- Mechanics' Bank v. City of New York 164 App. Div. 128 p. 127
- Genovese v. Third Avenue Railroad 13 App. Div. 412 p. 128
- Booth v. Cleveland Rolling Mill Co. 74 N. Y. 15 p. 128
- Mansfield v. New York Central & Hudson River Railroad 102 N. Y. 205 p. 128
- People ex rel. McMackin v. Board of Police 107 N. Y. 235 p. 128
- People ex rel. McCabe v. Matthies 179 N. Y. 242 p. 128
- Smith v. City of New York 88 App. Div. 606 p. 128