Majority
Headnote
Contract — state — provision, in contract for construction of portion of Barge canal, for additions and changes in plans and specifications — when refusal by contractor to comply with alteration order constitutes breach of contract — practical construction put upon contract by parties — when claim against state properly dismissed.On the 3d of April, 1905, the Ferguson Contracting Company entered into a contract with
The contract provided generally for excavating, constructing supports for the sides of the canal, and the construction of two locks, Nos. 2 and 3, with side walls and floors of concrete. The amount of estimated work, with the prices stipulated in the contract, plans and specifications made a part of it, including alteration orders 1 to 7, both inclusive, amounted to $946,105.76. The amount of work, excluding alteration order No. 7, was $906,896.26. Alteration order No. 7 added work amounting to $74,848.90, and decreased work amounting to $35,639.49, so that there was an actual increase in the work, by reason of this order, of $39,209.50. The contractor entered upon and continued performance of the work as called for until the 27th of April, 1909, when it refused to proceed further.
Section 7 of the contract provided as follows: “It is mutually agreed that the state reserves the right, until the final completion and acceptance of the work, to make such additions to or changes in the plans and specifications covering the work as may be necessary, and the contract shall not be invalidated thereby, and no claim shall be made by the contractor for any loss of profits because of any such change or by reason of any variation between the quantities of the approximate estimate and the quantities of the work as done.”
Thereafter, acting under the provision of the contract quoted, the state, from time to time, made certain alterations which are designated in the record as alteration orders Nos. 1 to 7, both inclusive. The contractor acquiesced in all of the alterations except No. 7, ■ and performed the work called for without objection, at the
Therefore, the state, acting under the power given to it by section 7 of chapter 147 of the Laws of 1903, and by section 12 of the contract under consideration, in the form and manner provided therein, canceled the contract and directed the remaining part of the work under it to be readvertised and relet in accordance with the provisions of the statute. A new contract was then entered into for the completion of the work. After the new contract was let, the claim in question, amounting to upwards of $400,000, was presented against the state, on the ground that it, by alteration order No. 7, had broken the contract.
The claimant, in the claim filed, alleged, in substance, that alteration order No. 7 constituted a radical change in the plans and specifications of the work remaining to be done under contract No. 2, thereby departing radically from the general character and type of the work as originally contemplated; that the claimant refused to recognize such radically proposed alterations as binding,
In 1910 a trial was had as to the validity of the claim thus presented. The Court of Claims dismissed the claim. It found that alteration order No. 7 contained no item for which a unit price was not stipulated in the contract, and no work of a different kind from that called for by it. It also found, to which no exception was taken, as follows:
“ 9. Alteration No. 7 did not change the nature of the work called for by the contract or substantially change the cost of the work.
“10. The claimant refused to accept said alterations and refused to enter into an agreement therefor, on the ground that they constituted a fundamental change in the contract, and amounted to a breach of the contract by the State.
“11. The claimant refused to continue the work under the contract after the submission of said Alteration Order No. 7, treating the order as a breach of the contract by the State, and thereby was guilty of a breach of its contract.”
And as conclusion of law:
“ 1. Alteration Order No. 7 did not change the nature or substantially affect the cost of the contract and was not a fundamental change of the contract.”
These findings were unanimously affirmed by the Appellate Division.
The question presented by the appeal is whether the state had the right to make alteration order No. 7 and require the contractor to do the extra work called for thereby, at the unit prices specified in the contract. I
The construction thus put upon the contract is supported by the practical construction the parties themselves placed upon it in the six prior alteration orders. The contract fixed unit prices for each class of work called for in these alteration orders, including order No. 7.
Under the terms of the contract, as well as the construction placed upon it by the parties themselves, the work specified in alteration order No. 7 had to be performed by the claimant at the unit price specified, and when it refused to perform the work and furnish the materials called for, it broke the contract and the state was justified in doing what it did.
The judgment ' of the Appellate Division should, therefore, be. affirmed, with costs.
Hogan, Pound and Crane, JJ., concur; His cock, Ch. J., Cardozo and Andrews, JJ., dissent.
Judgment affirmed.
Cases cited
- Sun Printing & Publishing Ass'n v. Remington Paper & Power Co. 235 N. Y. 338 p. 187
- Barrow Steamship Co. v. Mexican Central Railway Co. 134 N. Y. 15 p. 187
- Myers v. Smith 48 Barb. 614 p. 187
- Clark v. Mayor of New York 4 N. Y. 338 p. 187
- Kinser Construction Co. v. State 204 N. Y. 381 p. 187, p. 191
- People ex rel. Graves v. Sohmer 207 N. Y. 450 p. 187