Majority
Headnote
Contract — analysis and construction of contract for constructing part of barge canal — changes in plans required by unforeseen conditions rendering completion of work under original plans impossible — when contractor cannot recover profits lost by such changes.This appeal comes to us on the findings made by the Court of Claims and unanimously affirmed by the Appellate Division, so that the facts are settled beyond our power of review. The main question presented for decision is whether the facts thus, finally resolved sustain the conclusions of law found by the trial court. That question depends on the meaning of the seventh clause of the contract, when read in connection with the context and construed in the light of the circumstances surrounding the parties when they entered into the agreement. It will be convenient for any one who reads this opinion to have that clause directly before him as he considers our views upon the subject and, hence, we quote it again as follows : “7. It is mutually agreed that the State reserves the right until the final completion and acceptance of the work, to make such additions to or deductions from such work or changes in the plans and
This clause permits the state not only to make such additions to or deductions from the work, but also to make such changes in the plans and specifications covering the work as may at any time be necessary, without rendering the contract invalid or subjecting the state to claims for loss of profits by the contractor. (Clark v. Mayor, etc., of N. Y., 4 N. Y. 338 ; Kingsley v. City of Brooklyn, 18 N. Y. 200 .) No limitation other than necessity is placed upon the right to make additions, deductions and changes in the work, plans and specifications. Necessity is the sole basis and standard for the protection of both parties. On the one hand, it protects the contractor from arbitrary, capricious or unreasonable action by public officers, and on- the other it protects the state from unforeseen conditions, which would render the work as originally planned impossible of performance. The necessity need not be absolute, but it must be reasonable, for the law writes the word “reasonably” before the word “ necessary ” in the contract as unavoidably within the contemplation of the parties, when the extent of the work is considered. (Jerome v. Boss, 1 Johns. Ch. 315 , 340.) Reasonable necessity did not require that it.should be absolutely or physically impossible to build the lock on the old location, for, assuming that it was an engineering possibility, if the expense involved was so enormous as to make it impracticable, performance was impossible within the meaning of the contract.
The surrounding circumstances show that the word, “ necessary” was used to fulfill a purpose of the highest importance to the state. The contractor agreed that it had satisfied itself by its own investigation and research
The state was engaged in a work of such magnitude as to be without precedent in its own history or in the history of any other state. Nearly a century before it had built the Erie canal at a cost of about $1,000,000 with capacity to carry boats of seventy-five tons burden. Years later it had enlarged the canal so that it could carry boats of over two hundred tons, but at last it was about to construct a great waterway to carry boats of more than three thousand tons and at an expense of more than $100,000,000. It extended from Lake Erie to the Hudson river with one branch from Three River Point to Lake Ontario, another from the Hudson river at Waterford to .Lake Champlain and a third to connect with the Seneca and Cayuga lakes, making a total of more than four hundred and fifty miles.
In laying out a line of canal engineers have less lati
It is obvious that in a work of this magnitude the highest engineering skill, even when exercised with the utmost care, could not learn in advance all the physical conditions to be met with during the progress of the work. Those to whom the mammoth undertaking was intrusted, even with the aid of the most expert engineers, could not find in all places throughout the long line of operations what nature had-placed beneath the surface of the earth in the form of obstacles to construction which could not be overcome. Alterations and changes, many slight and some substantial, would almost inevitably be required at various points in a work of such extent. Common prudence on the part of those in charge would compel them to make provision for such contingencies as could not be foreseen with ordinary care and prudence. This was the object of the clause in question, which should be so construed as to effect its important purpose. Bidders were bound to take notice that the state reserved the right to make additions and deductions In the work and changes in the plans and specifications covering the work, with no right on their part to claim damages for loss of profits on account thereof. Minor changes were certain and of slight importance. Radical changes might or might not be made, depending upon necessity, and the bidder ran his risk and doubtless increased his bid on account of the risk. In this case the result is harsh in its effect, not owing to absolute loss for which the judgment provides, but to the loss of profits that might have been made. This evil is less serious than to force the state to pay
We have examined the authorities cited by the learned counsel for the claimant, but find none when carefully read which decide anything in conflict with the views here expressed, whatever may have been said as the personal view of the judge writing the opinion. It is one thing to build a single structure like the dam across the Hudson river near Palmer’s Falls and quite another to create a body of water extending across the state upon which barges can carry the commerce of the great lakes in loads of more than 3,000 tons each. (National Contracting Co. v. Hudson River Water Power Co., 192 N. Y. 209 .)
The case cited, which is the chief reliance of the appellant, involved a contract, not with the state, but between private parties, to build a single dam, while the contract in question covers hut a small part of a great work. There was no provision for a change in case of necessity, although there was power to make alterations without liability for anticipated profits. A change from a masonry dam with no earth called for, to a dam essentially of earth with comparatively little masonry, mads
McMaster v. State of New York ( 108 N. Y. 542 ) is also relied upon by the claimant, but there was no necessity for the change of plans in that case and the change made was arbitrary, radical and subversive of the thing to be done. There was no reason for it except that the new construction would be cheaper.
An authority much more analogous to the case in hand, both in its facts and in the principle involved, lends strong support to the conclusion we have reached. (Kingsley v. City of Brooklyn, 78 N. Y. 200 , 208.)
The appellant claims that the state guaranteed its plan, but assuming, without deciding, that this is true, the trouble was not with the plan but with the earth, which refused the support relied upon by both parties, the one as much as the other. When the earth gave way and there was no adequate support for the structure to be built upon it, a contingency arose which authorized the state to exercise its reserved power. It was the same in effect as if an earthquake had utterly destroyed the foundation on which the lock was to rest. The defect was caused by nature, not by man.
According to the facts'Tound by the trial court and unanimously approved by the Appellate Division there was no breach of contract by the state, and the claimant was not entitled to prospective profits nor to a judgment
More might be said; but, in view of the careful opinions written in both of the courts below, I regard further discussion as unnecessary. I recommend that the judgment appealed from be affirmed, with costs.
Cullen, Oh. J., G-bay, Haight, Willabd Baetlett, Hiscock and Chase, JJ., concur.
Judgment affirmed.
Cases cited
- Clark v. Mayor of New York 4 N. Y. 338 p. 389, p. 391
- Warren Chemical & Manufacturing Co. v. Holbrook 118 N. Y. 586 p. 389
- Byron v. Low 109 N. Y. 291 p. 389
- Gearty v. Mayor of New York 171 N. Y. 61 p. 389
- Danolds v. State 89 N. Y. 36 p. 389
- McMaster v. State 108 N. Y. 542 p. 389, p. 396
- Gage v. City of New York 110 App. Div. 403 p. 389
- National Contracting Co. v. Hudson River Water Power Co. 192 N. Y. 209 p. 389, p. 395
- Gillet v. Bank of America 160 N. Y. 549 p. 389
- Tompkins v. Dudley 25 N. Y. 272 p. 389
- Wheeler v. Connecticut Mutual Life Insurance 82 N. Y. 543 p. 389
- Woodruff v. Woodruff 52 N. Y. 53 p. 390
- Kingsley v. City of Brooklyn 78 N. Y. 200 at 208 p. 390, p. 396
- Sattler v. Hallock 160 N. Y. 291 p. 390
- Seymour v. Warren 179 N. Y. 1 p. 390
- Chicago v. Sheldon 76 U. S. 50 p. 390
- Topliff v. Topliff 122 U. S. 121 p. 390
- Stewart v. Stone 127 N. Y. 500 p. 390
- Lorillard v. Clyde 142 N. Y. 456 p. 390
- Dolan v. Rodgers 149 N. Y. 489 p. 390
- Herter v. Mullen 159 N. Y. 28 p. 390
- Buffalo & Lancaster Land Co. v. Bellevue Land & Improvement Co. 165 N. Y. 247 p. 390
- J. H. Labaree Co. v. Crossman 100 App. Div. 499 p. 390
- People ex rel. Immerman v. Devlin 63 Misc. Rep. 363 p. 390